Project Pegasus

Project Update Works continue apace including: • M&E first fix installation throughout the building • Installation of new fourth floor structural steel • Intumescent painting to the new structural steel • Carpentry to the new mansard roof structure including the new dormer windows • Installation of new copper for gutters & dormers • Refurbishment of existing windows throughout • Installation of roof light steel • Reinstallation of library joinery • Flat roof membrane installation to the new mansard • Fit-out of ground floor washrooms • Installation of drylining throughout the building

The Sir Robert McAlpine Special Projects site team offices are based in the former Treasury Office. If you have any comments, concerns or questions about the construction activities you can contact john.walker@srm.com 07866 783 710 The permitted site working hours are from: 8.00am to 6.00pm Monday to Friday 9.00am to 2.00pm Saturday (when required)

You can keep up to date with activities on site by signing up for the weekly construction update which gives a two week forward view of what is happening on site. You can sign up for this newsletter via innertemple.org.uk/project-pegasus

22 INNERVIEW

Hilary Term


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.