Angola LNG Project Progress Photos
May 2009 to May 2010
Angola LNG Project Progress Photos May 2009 to May 2010
May 28, 2010
ISBL - APRIL 26, 2009
LNG – TANK B 10A/10N – GTGS 01S/01R – CRYO RACK 01N – PROPANE CONDENSER
01A–COMPRESSORS
ISBL - MAY 10, 2010 10A/10N – GTGS
01S/01R – CRYO RACK 01N – Propane Condenser
01A–COMPRESSORS
01G – Methane Liquification Cold Box
TANK AREA - 15 Feb 2009 LNG – TANK A/B
LNG – PROPANE & BUTANE TANK
LNG – CONDENSATE TANK
LNG – TANK A & B
TANK AREA - MAY 10, 2010
LNG – PROPANE & BUTANE TANK
LNG – CONDENSATE TANK
01N-PROPANE CONDENSER RACK
OSBL EAST SIDE - 27 MAY 2009 01A - COMPRESSORS 08A-WET & DRY FLARE
11A – CONTROL BUILDING 11A - BUILDINGS
OSBL EAST SIDE - 16 MAY 2010
01N-PROPANE CONDENSER RACK 01A - COMPRESSORS
08A-WET & DRY FLARE
10H – CONTROL BUILDING
11A - BUILDINGS
MARINE & TANK AREA - 12 April 2009
LNG – CONDENSATE TANK
LNG JETTY
MARINE FLARE
LNG – PROPANE & BUTANE TANK
LPG JETTY
CHEC – MARINE FLEET PB JETTY
MARINE & TANK AREA - 10 April 2010
LNG – CONDENSATE TANK
MARINE FLARE
LNG – BUTANE TANK
LNG JETTY
LPG JETTY
PB JETTY
6500 BED CAMP - 26 Apr 2009 “D” BLOCK UNDER CONST.
5000 MAN DINER UNDER CONST.
WTP/STP PLANT
6500 BED CAMP - 21 Feb 2010 WTP/STP PLANT
1st Steel Erection for Propane Condenser Pipe rack (Area 01N)
May 28, 2009
Today – Propane Condenser Pipe rack (Area 01N)
May 27, 2010
1st erection of Vessel 1V-1421/22/23 & 1V-1411/12/13 Knock out Suction Drum At Propane Refrigeration (Area 1J)
Aug 03, 2009
Today – Propane Refrigeration (Area 01J) Suction Drums Behind 01J Steel
May 27, 2010
Erection of Frame 7 South Compressor
Oct. 05, 2009
Today – Compressors (Area 01A)
May 27, 2010
1st Erection of GTG (Area 10A/10N)
Aug. 27, 2009
Today – Gas Turbine Generators (Area 10A/10N)
May 27, 2010
Erection of CO2 Absorber (Area 01C) (1,125 Tons)
Oct. 28, 2009
Erection of CO2 Absorber (Area 01C) (1,125 Tons)
Oct. 28, 2009
Erection of CO2 Absorber (Area 01C) (1,125 Tons)
Oct. 28, 2009
Today – CO2 Absorber (Area 01C)
May 27, 2010
Setting of Ethylene Refrigeration Cold Box (Area 01H)
January 14, 2009
Today – Ethylene Refrigeration Cold Box (Area 01H)
May 27, 2010
Erection of Heavies Removal Column 1V-1701 (Area 01F) (540 Tons)
January 19, 2009
Erection of Heavies Removal Column 1V-1701 (Area 01F) (540 Tons)
January 19, 2009
Today-De-ethanizer 1V- 1702 & Heavies Removal Column 1V-1701 (Area 01F)
May 27, 2010
Erection of Dry Flare Stack (Area 08A)
May 27, 2010
Today – LNG Tanks A & B
LNG TANK B
LNG TANK A
May 27, 2010
Today – LNG Propane & Butane Tanks
BUTANE TANK PROPANE TANK
07D PIPE RACK
May 27, 2010
Great work…. Great Team…
Bechtel & Sub-contractors LNG Team