CA Assignment One

Page 1

LIQUID AMBER HOUSE


8

EXTERNAL WALL LININGS, EXTERNAL VAPOUR BARRIER

11

INTERNAL LININGS, INSULATION AND WATERPROOFING

10

SERVICES ROUGH IN RADIANT FLOOR

2

BORED PEERS FOUNDATION WORK

3

FOOTINGS AND GROUND SLAB

5

TIMBER FRAMING

7

DOOR AND WINDOW INSTALLATION

4

STEEL FRAMING

LIQUID AMBER HOUSE BY ZEN ARCHITECTS

Drawn by:

TONI PRINGLE 837644 Date:

09/08/2017 DRAWING / PLAN GROUND FLOOR PLAN 1:50 @ A3 Dwg no.

01


1

DEMOLITION, SITE PREPARATION, SET OUT

9

ROOF LINING AND ROOF PLUMBING

EXTERNAL WALL LININGS, EXTERNAL VAPOUR BARRIER

6

8

ROOF FRAMING

5

TIMBER FRAMING

11

INTERNAL LININGS, INSULATION AND WATERPROOFING

7

4

DOOR AND WINDOW INSTALLATION

STEEL FRAMING

2

BORED PEERS FOUNDATION WORK

SECTION AA

Scale - 1:50 @ A3

LIQUID AMBER HOUSE BY ZEN ARCHITECTS

Drawn by:

TONI PRINGLE 837644

3

FOOTINGS AND GROUND SLAB

Date:

09/08/2017 DRAWING / PLAN SECTION AA 1:50 @ A3 Dwg no.

02


1 DEMOLITION, SITE PREPARATION, SET OUT

IN-GROUND SERVICES AND FOUNDATIONS

FOOTINGS AND GROUND SLAB

STEEL FRAMING

TIMBER WALL AND FIRST FLOOR FRAMING

ROOF FRAMING

1.1 Demolition of existing single storey brick veneer home 1.2 The class ‘P’ site is excavated to achieve the desired level and cellar allowance; allowing at least 3m deep bored peers to be founded in clayey sand 1.3 A 50mm minimum packing sand bed along with appropriate site fill where organic material and soft material have been removed is required to sit under the future slab

2.1 Appropriate timber form-work is set out within the cellar and around the concrete slab set out 2.2 Appropriate service pipes (toilets, sinks, showers, and drainage) are put in place where necessary - penetrations of pipes and plumbing fittings will be taped in construction sequence #3 2.3 600 and 900 Ø bored peers are poured and cured in accordance to engineers details

3.1 Slab and beams shall be cast upon a 0.2mm minimum thickness polythene vapor barrier 3.2 All reinforcement shall be laid and taped in place in accordance to engineers specifications 3.3 170mm thick slab to be pored throughout and cured in accordance to engineers detail

4.1 Structural steel columns (89 x 5.0 square hollow section) are erected in accordance to engineers drawings 4.2 Unless noted otherwise all steel columns shall have a 10mm base plates with 2 - M16 chemset anchors

5.1 Top and bottom plates are fixed to either end of 90 x 45 MGP10 studs at 450mm centres 5.2 Bottom plates are fixed to concrete slab via M10 anchors at 900mm centres 5.3 Temporary bracing and propping is used in addition with diagonal tension straps and/or plywood bracing 5.4 First floor beams and joist are erected in accordance to the engineers member schedule and plan; with 19mm particleboard flooring to continue over top 5.5 First floor wall framing is erected

6.1 Roof framing is erected in accordance to SAA National Timber Framing Code and AS1720 - SAA Timber structures code 6.2 Where rafters and ceiling joist are parallel with masonry walls fix M12 anchors at 900 centres

LIQUID AMBER HOUSE


DOORS AND WINDOWS

EXTERNAL WALL LININGS, EXTERNAL VAPOUR BARRIER

ROOF LINING AND ROOF PLUMBING

SERVICES ROUGH IN

INTERNAL LININGS, INSULATION AND WATERPROOFING

INTERNAL FITTINGS, FIXTURES AND JOINERY

7.1 Installation of windows in accordance to architectural drawings window schedule

8.1 Installation of appropriate sarking and waterproofing membranes to ground and first floor framing 8.2 Masonry construction shall comply with AS3700 - SAA Masonry Code - all load bearing bricks shall be pressed commons 8.3 Installation of all other external finishes including: painted matrix panels, stained timber shiplap, timber recycled ironbark, timber battens stained,

9.1 1 Installation of appropriate sarking and waterproofing membranes to roofing 9.2 1 Installation of appropriate metal roofing fixed over sarking 9.3 1 Installation of appropriate gutters, flashings and cappings (generally colourbond finish), downpipes 9.4 Abide rainwater harvesting notes in architectural during set for correct specifications and systems

10.1 Internal services are fitted including, wiring, switchboards, meter box, down pipes and radiant floor heating

11.1 Insulation batts are fitted to stud wall cavities and ceiling 11.2 Internal linings; including plaster, tiling, timber and floor finishes are fitted

12.1 Final paint work is complete 12.2 Joinery is complete 12.3 Connection to services 12.4 Timber framed pergola is fitted 12.5 Final touch ups are made to the house before completion

TONI PRINGLE | 837644 | LIQUID AMBER HOUSE| ZEN ARCHITECTS


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.