Jonathan Lawrence Turner Architectural Portfolio
Contents Professional Experience
Brion Jeannette Architecture Straub Pettitt Yaste
Intermediate Technical Drafter/Project Assistant Architectural Internship
004
014
Educational Experience
Neurodiversity in Architecture
Masters Thesis
Integrated
Undergraduate Studio
Interior Design
Undergraduate Studio
Lakeview Project
Undergraduate Studio
Geographical Integration
Undergraduate Studio
022
034
040
044
048
Selected Works
054
Resume & Personal Information
064
2
3
BRION JEANNETTE ARCHITECTURE
Firstline Residence
While working at BJA one project that I assisted on was the Firstline Residence. For this project the existing residence was demolished and a new 3-story single family residence with subterranean basement, attached 3-car garage, & roof deck was constructed. This project was completed in a team setting & I worked under the guidance and supervision of Brion Jeannette & Wun Sze Li.
My technical assistance on this project was spread throughout multiple parts of the construction document set of plans. Specifically my role was to: prepare project plans and drawings, organize drawing set for city submittal, pick up plan redmarks, adjust plans per design changes, update drawings to comply with city comments during plan check, etc... The ownership of these drawings belongs to Brion Jeannette Architecture.
6
7
8
9
10
11
12
13
MICHIGAN DEPARTMENT OF CORRECTIONS RECORD STORAGE WAREHOUSE FILE NO: 472/19173.CDP 1780 E. PARNALL ROAD JACKSON, MI 49201
SHEET INDEX
SHEET INDEX
"R" REVISED DRAWING, "N" NEW DRAWING
"R" REVISED DRAWING, "N" NEW DRAWING
DELETED DRAWINGS: NONE
DELETED DRAWINGS: NONE
DWG # DRAWING NAME A00 COVER PAGE A01 DEMO PLAN A02 DEMO ELEVATIONS A03 NEW WORK A04 ENLARGED FLOOR PLAN A05 NEW WORK LVL 2 A06 RCP A07 ELEVATIONS A08 SECTIONS A09 ELEVATIONS AND DETAILS A10 DOOR SCHEDULES AND DETAILS 01 ARCHITECTURAL: 11
ISSUED FOR
DATE
ARCHITECT OF RECORD:
MDOC & DTMB
STRAUB PETTITT YASTE
1780 E Parnall Rd Jackson, MI 49201 CONTACT: DAVE ALBRECHT
850 NORTH CROOKS SUITE 200 CLAWSON, MI 48017 T: 248.658.7777 F: 248.658.7781 CONTACT: RICHARD MANN W: www.straubpettittyaste.com
STRUCTURAL:
ELECTRICAL ENGINEER:
RICHARD KOZLOWICZ
TAC ASSOCIATES LLC
850 NORTH CROOKS SUITE 200 CLAWSON, MI 48017 T: 248.658.7777 F: 248.658.7781 CONTACT: RICHARD MANN W: www.straubpettittyaste.com
4321 EAST CAMDEN RD. OSSEO MI. 49266 T: 517.254.4789 F: 517.254.4886 CONTACT: THOMAS CROW W: http://www.tac-associates.com
DRAWING NAME
ISSUED FOR
DATE
M00
MECHANICAL GENERAL INFORAMTION & HVAC EQUIPMENT SCHEDULES M01 LEVEL 1 MECHANICAL DEMOLITION PLAN M02 LEVEL 1 & LEVEL 2 MECHANICAL ALTERATION PLANS M03 LEVEL 1 & LEVEL 2 PLUMBING ALTERATION PLANS 03 MECHANICAL: 4 .E001
SYMBOL LIST, LIGHTING FIXTURE SCHEDULE, AND DRAWING INDEX FLOOR PLAN - ELECTRICAL DEMOLITION FIRST FLOOR PLAN - ELECTRICAL NEW WORK PARTIAL FIRST FLOOR PLAN - LIGHTING NEW WORK PARTIAL FIRST FLOOR PLAN - LIGHTING NEW WORK SECOND FLOOR PLAN - ELECTRICAL NEW WORK PARTIAL SECOND FLOOR PLAN - LIGHTING NEW WORK PARTIAL SECOND FLOOR PLAN - LIGHTING NEW WORK PARTIAL FIRST FLOOR PLAN - POWER & SYSTEMS NEW WORK E202 PARTIAL FIRST FLOOR PLAN - POWER & SYSTEMS NEW WORK E211 PARTIAL SECOND FLOOR PLAN - POWER & SYSTEMS NEW WORK E212 PARTIAL SECOND FLOOR PLAN - POWER & SYSTEMS NEW WORK E300 POWER ONE-LINE DIAGRAM - DEMOLITION E301 POWER ONE-LINE DIAGRAM - NEW WORK E310 ELECTRICAL SCHEDULES E311 ELECTRICAL SCHEDULES E400 MISCELLANEOUS WIRING DIAGRAMS AND DETAILS E401 MISCELLANEOUS WIRING DIAGRAMS AND DETAILS E402 MISCELLANEOUS WIRING DIAGRAMS AND DETAILS EX100 FIRST FLOOR PLAN - EMERGENCY EGRESS LIGHTING PHOTOMETRY EX110 SECOND FLOOR PLAN - EMERGENCY EGRESS LIGHTING PHOTOMETRY 04 ELECTRICAL: 21 TOTAL DRAWINGS: 37 .ED100 E100 E101 E102 E110 E111 E112 E201
PROJECT NUMBER: 1904 OWNER:
DWG #
S01 STRUCTURAL PLAN 02 STRUCTURAL: 1
CODE DATA: USE GROUP: B & S-1 SEPARATION REQUIRED: NO SEPARATION CONSTRUCTION TYPE: 11-B EXISTING BUILDING HEIGHT: 22' EXISTING BUILDING AREA: 12,000 GSF BUILDING IS NOT SPRINKLED
MECHANICAL ENGINEER:
MICHIGAN DEPARTMENT OF CORRECTIONS
106
POTAPA-VAN HOOSEAR
RECORD STORAGE WAREHOUSE FILE NO: 472/19173.CDP 1780 E. PARNALL ROAD JACKSON, MI 49201
48653 VAN DYKE AVE. SHELBY TOWNSHIP, MI 48317 T: 586.997.0922 CONTACT: KARL POTAPA W: kpotapa@pveng.net
1904 © 2018 STRAUB PETTITT YASTE
Straub Pettitt Yaste
850 NORTH CROOKS ROAD SUITE 200 CLAWSON, M ICHIGAN 48017-1311
RO
AD
PRELIMINARY
CO OP
ER
NOT FOR CONSTRUCTION
E. PARNALL ROAD PROJECT SITE LOCATION: 1780 E. PARNALL ROAD JACKSON, MI 49201
10/10/2019 9:42:47 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
248-658-7777 PHONE 248-658-7781 FAX
EXISTING BUILDING
STRAUB PETTITT YASTE ARCHITECTURE
COVER PAGE
A00
SRA Record Storage Warehouse
While working at SPY the project that I assisted with the most was the SRA Record Storage Warehouse. For this project the existing warehouse was remodeled to accommodate a large scale file storage system and create a comfortable office space for personnel to operate out of. For this project I worked under the guidance and supervision of Rick Mann. 14
D29 D01
D17
D29
D10
M
D35
A D15
D07
D01
FD
D07
D32
D03
D23
FD
FD
D09
D10
D03
D06 D23
D17 D25
FD
D23
D03
D16
FD
D23
FD
FD
D23
D29 FD
D23
D12
D10
D03 FD
D11
D11
D01
D23
D28
D22 D10
D03
D23
D08
D24 D25 D26
D01
D23 D09
D
D10
D10
FD
D24
D31
FD
D03
FD
D10
D23
D27
D21
E D30 D05
D19 D20 D21
C
L
FD
D12 D13 D14 D15 D16 D17 D18
D23
D10
D18
D11 D02
D10
FD
D10
B
D10
D13
D05
D09
D01
D23
D23
D06
D23
D01 D02 D03 D04 D05 D06 D07 D08
D14
D07
K
D10
D10
D11
D08
EXISTING RAMP
D28
D29
SAWCUT OPENING IN EX INSTALLATION OF NEW PRECAST CONCRETE LIN
D30
SAWCUT AND REMOVE INSTALLATION OF NEW EXISTING DOCK LELVEL REMOVE GYPSUM WAL FROM EXISTING ROOM. REMOVE A/C CONDENS
D31 D32 D10
D22
D35
D10
REMOVE EXISTING DOO REMOVE QUARRY TILE F REMOVE 6" CMU WALL. REMOVE 8" CMU WALL. REMOVE 12" CMU WALL. REMOVE TOILET FIXTURE REMOVE SINK AND ASS REMOVE OVERHEAD DO TRACK AND MOTOR. REMOVE CARPET FLOOR FROM SPECIFIED LOCAT REMOVE PORTION OF C CONTRETE FOOTINGS A REMOVE SLIDING CAGE COMPONENTS. PREP ALL EXPOSED MA PREP FLOORING FOR PA REMOVE CASED OPENIN REMOVE GYPSUM CLAD REMOVE METAL CHAINL REMOVE 4" RAISED CON PREP ALL CONCRETE FL LEVELING. EXISTING 8" CMU WALL REMOVE DRINKING FOUN REMOVE MASONARY UN EXISTING CMU WALL. REMOVE DOCK LEVELER PREP FOR NEW CONCRE SAWCUT AND REMOVE PIPE BELOW FLOOR. PA SAWCUT AND REMOVE REMOVE PARTITIONS AN REMOVE WOOD FRAIME AND ALL COMPONENTS SAWCUT NEW DOOR OP MASONRY WALL. SAWCUT OPENING FOR NEW CMU AS NEEDED. LINTEL.
F D13 D08
D10 D20 D01 D01
D10
G D07
D26
D04
D04
D06
D01 D19
D27
D26
D10
1
ers\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
A01
D19
Level 1 Demo
0'
SCALE: 1/8" = 1'-0"
8'
16'
ELECTRICAL PANEL FEEDS OUTSIDE RECEPTACLES ALONG PARKING LOT.
D35
D09 D10
J
D29
GENERAL NOTES: • GUT EXISTING BUILDING WITHIN EX ROOF. • ALL PIPES, LOUVERS, & MECHANIC REMOVED IN ARCHITECTURAL, MEC DRAWINGS ARE TO BE PATCHED W EXISTING. EXCEPTIONS: • WALL OF EXISTING SOUTH/EAST C • INSULATION AND EXISTING ROOF I
D29
H
I
Scale: 1/8" = 1'-0"
/2019 9:42:49 AM
My technical assistance on this project was spread throughout multiple parts of the design development & construction documentation phases. Specifically my role was to: field measure and draft as-built conditions, prepare preliminary design plans for design review meetings, draft construction document set, pick up office redlines, etc.. The ownership of these drawings belongs to Straub Pettitt Yaste 0'
8'
16'
108
B
FD
P03
A01-B
G
P06
110
B
P07
4'-0"
4'-0"
4'-0"
4'-0"
3'-6"
3'-6"
3'-6"
P02
R E CO R D S T O R AGE 12
A01-D
P02
102
108
115
110 112
111
A01-B
K
P01
3'-6" TO 4'-0" R21 BATT INSULATION
A01-I P07
UP
H
A01-G
2
16'
A03
Scale: 1/8" = 1'-0"
1 A07
Level 1 New Work
0'
SCALE: 1/8" = 1'-0"
P07 8'
16'
3'-6"
P07
HEAD HEIGHT
J
BLINDS (BY OWNER)
30" x 48" CLEAR FLOOR SPACE P07
106
ALUMINUM A01-H STOREFRONT
Scale: 1/8" = 1'-0"
A08 NEW METAL PANEL SIDING TO MATCHA01-I EXISTING
H
F
I
SEALANT ALL SIDES @ FRAME CONT
Level 1 New Work SCALE: 1/8" = 1'-0"
0'
8'
16'
Scale: 1/8" = 1'-0"
1 A03
PLASTIC LAMINATED SILL.
A03
_turnerjl1.rvt
STOREFRONT
INSIDE
SEALANT ALL SIDES @ FRAME CONT
Str OUTSIDE
OUTSIDE
Pe HEAD DETA
1" INSULATED 1" INSULATED GLASSGLASS
7 1/8"
Ya
W2 -
PRECAST 8" CONCRETE PANEL
2x4 BLOCKING A01-I
3 5/8 STUDS R21 BATT INSULATION GYPSUM WALL BOARD
A01-I
W3 - SILLI DETAIL Typical Window Details SCALE: 1 1/2" = 1'-0"
GYPSUM WALLBOARD
JAMB VIEW
4"
CONTINUOUS SEALANT 2x2 ACT GRID GYPSUM ON 3LAMINATED 5/8" PLASTIC METAL STUDS SILL. @ 16" O.C.
ALUMINUM STOREFRONT WINDOW.
7/8"
6"
NEW METAL PANEL EXISTING CONCRETE MASONRY SIDING TO MATCH EXISTING GROUT CORES GYPSUM SHEATHING AIR AND MOISTURE BARRIER HAT CHANNELS @ 24" O.C.
FOR OPENINGS 2x4 BLOCKING WIDER THAN 5'-0" FINISH FACE PROVIDE #4 BAR 3 5/8 STUDS OF ADJACENT STIRRUPS @ 8" OC WALL WHERE MAXGYPSUM , GROUTWALL BOARD APPLICABLE COURSE ABOVE LINTEL SOLID
PRELI
NOT FOR C
S F
P L B
HEAD HEIGHT BASE TRIM
2x6 BLOCKING
3
BLINDS (BY OWNER) ALUMINUM STOREFRONT
A03
- CMU JAMB DETAIL W3W1 - SILL DETAIL SEALANT ALL SIDES @ FRAME CONT
Typical Window Details SCALE: 1 1/2" = 1'-0"
INSIDE HEAD DETAIL
16
ALUMINUM STOREFRONT OUTSIDE INSIDE
8"
P02
112
111
3
© 2018 STRAUB P
JAMB VIEW SILL DETAIL
H P07
BLINDS (BY OWNER) SEALANT ALL SIDES @ FRAME CONT ALUMINUM
4"
- CMU STUD HEADHEAD DETAIL W4W2 - METAL DETAIL
P07
J
BASE TRIM 2x4 BLOCKING A WINDOW HEAD.
HEAD DETAIL HEAD DETAIL
CONTINUOUS SEALANT
3'-6"
1 A07
1904
HEAD HEIGHT
HEAD HEIGHT
G
GROUT CORES
13'-9"
FOR OPENINGS WIDER THAN 5'-0" PROVIDE #4 BAR STIRRUPS @ 8" OC MAX , GROUT COURSE ABOVE LINTEL SOLID
108
UP
A01-B
GYPSUM SHEATHING PRECAST CONCRETE AIR AND MOISTURE BARRIER LINTEL WITH (4) @ #5 HAT CHANNELS BARS GROUTED SOLID. 24" O.C.
SEALANT ALL 2x6 BLOCKING SIDES @ FRAME CONT BLINDS (BY OWNER)
P02 W4 - METAL STUD HEAD DETAIL
110
3'-6"
113
P01
NEW METAL PANEL SEE FLOOR PLANS SIDING TO MATCH FOR PARTITION TYPE EXISTING
GYPSUM WALLBOARD
1" INSULATED GLASS
ALUMINUM STOREFRONT FD WINDOW.
3'-6" TO 4'-0"
FILE NO: 472/19 1780 E. PAR JACKSON, M
7/8"
COURSE ABOVE LINTEL SOLID
107
FD
6"
FOR OPENINGS WIDER THAN 5'-0" PROVIDE #4 BAR STIRRUPS @ 8" OC R21 BATT INSULATION MAX , GROUT
OUTSIDE
A01-D
7 1/8"
EXISTING CONCRETE MASONRY
4'-0" 4'-0"
3'-0"
2'-9 1/4"
3'-6" TO 4'-0"
10/10/2019 9:42:55 AM
2'-0" 3'-4"
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
2
A03
1
RECORD STOR WAREHOUSE 2x2 ACT GRID 4 A07
1 A03
BASE TRIM
2
109
A01-J
MICHIGAN D CORRECTIO
SILL DETAIL
P03
PRECAST 8" CONCRETE PANEL SCALE: 1 1/2" = 1'-0"
2x2 ACT GRID
A05
FD INSIDE
P05 HEAD DETAIL P02
FD
A01-A
2x6 BLOCKING P02 1 A07
W
GENERAL NOTES: PATCH EXISTING CONCRETE SLAB ON GRADE. PRECAST 8"
G
OPENING WIDTH
8'
I
A03
SEE PLANS
0'
J
A01-B
P02
W3 - SILL DETAIL Typical Window Details
108
GYPSUM SHEATHING A01-I AIR AND MOISTURE BARRIER P07 HAT CHANNELS @ 24" O.C.
A01-D
GYPSUM WALLBOARD P03
E7/8"
13'-9"
A01-B
112 105
6"
A01-I
4'-0"
3'-6"
A01-D
P03
UP
4'-0"
4'-0"
3'-6"
113
13'-9"
k
2'-9 1/4" P01
3'-0"
3'-6" TO 4'-0"
3'-6" TO 4'-0"
3'-6"
P04
3'-0"
A01-J
4'-0"
2'-0" 3'-4"
3'-0"
2'-9 1/4"
4'-0"
1 A03
109
3
3
A01-D
W
A05
P01
114
P02
FD
P03
4'-7 1/8"
FD
D
P04
G
P06 P07
A05
FD
P05 P02
A01-F
P05
2
C
100
P01
P03
2 A07
P04
F
106
A01-H
L
109
P03
EXISTING CONCRETE MASONRY
30" x 48" CLEAR FLOOR SPACE
P02
P07
A05
FD
P02
P07 A01-A
P03
2
P05
A01-D
A01-A
F
106
CATWALK FD SUPPORT
P01
ALUMINUM STOREFRONT WINDOW.
GROUT CORES
30" x 48" CLEAR FLOOR SPACE
A01-H
A01-J
P03
A01-A
SILL DETAIL
1
A08
A01-G
P04
P07
P02
3'-0"
B
A01-D
4'-0"
3'-0"
K
A01-G
E
2 A03
A01-H A01-I
OPENING HEIGHT
4'-0"
4 A07
OPENING WIDTH
4'-0"
UP P06
W4 - METAL STUD HEAD DETAIL
A01-D
SEE PLANS
4'-0"
P04
OUT
NEW METAL SIDING AND INSULATION. REFERENC HEAD PARTITION DETAIL... INSTALL NEW CART LIFT. TYPICAL FOR TWO. INFILL DICK LEVELER PIT WITH CONCRETE SLAB DECK AND 8"CONCRETE MASONARY WALL. CARPET TILE 4 ON CONCRETE SLAB. A07 EXTEND EXISTING 8" CMU WALL TO UNDERSIDE JAMB CONCRETE PLANK FLOOR. APPROXAMINTE ONE NEW CONCRETE PAD. BROOM FINISH. MINIMUM 6 SIZE: 4'x4' CONTINUOUS SEALANT 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD PLASTIC SIDE.LAMINATED SILL. 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD SIDE. WITH SOUND ATTENUATION INSULATION. 2x4 6" BLOCKING METAL STUDS 5/8" FIRE CODE X GYPSUM WA SIDE. 3 5/8EACH STUDS 3 5/8" METAL STUDS 5/8" FIRE CODE X GYPSUM GYPSUM WALL BOARD BOARD EACH SIDE. 3 5/8" METAL STUDS 5/8" ABUSE RESISTANT GY BOARD EACH SIDE. WITH SOUND ATTENUATION 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD WITH R-13 BATT INSULATION.
OPENING HEIGHT
4'-0"
1
A08
A01-D
1" INSULATED GLASS
7 1/8"
A01-F A01-G
OPENING HEIGHT
4'-0"
P01
114
OUTSIDEAND CATWALK SYSTEM
HEAD DETAIL
OPENING HEIGHT
4'-0"
4'-7 1/8"
107
4'-0"
P03
3
OFFICE. NEW STA AND CAT NEW MET PARTITION A01-F INSTALL N PRECA A01-G INFILL DIC DECK AND A01-H CARPET T A01-I EXTEND E CONCRET A01-J NEW CON SIZE: 4'x4' 2x2 ACT GRID P01 3 5/8" ME SIDE. P02 3 5/8" ME SIDE. WIT FOR OPENINGS P03 WIDER 6" METAL THAN 5'-0" EACH SID PROVIDE #4 BAR @ 8" O P04 STIRRUPS 3 5/8" ME MAX , GROUT BOARD EA COURSE ABOVE P05 LINTEL 3 5/8" ME SOLID BOARD EA P06 3 5/8" ME P07 3 5/8" ME WITH R-13 A01-D
OFFICE. PATCH EXISTING C NEW STAIR. CONSTRUCT AS PART OF STORAGE
A01-B
INSIDE
A05
P04
E 3'-0"
P04
UP 4'-0"
103
A01-B
K
A01-F
P03
A01-A
STOREFRONT
D
110
UP
3'-0"
A 115
FIREPOXY E RAFIN T
SEALANT AL SIDES @ FR CONT SEALANT ALL SIDES @ FRAME EPOXY FINISH EXPOSED CONCRETE FLOORING W GENERAL NOTES: CONT
BLINDS (BY OWNER)
P04 A01-H
A01-D
2x6 BLOCKING
GENERAL NOTES: PATCH EXISTING CONCRETE SLAB ON GRADE. ALUMINUM
P02
P01
100
P01
102
3
C
I
P07
L
A05
H
P07
J
2
A08
M
104
P04 A01-B
A01-I A01-I A01-A P07
P03
D
R E CO R D S T O R AGE 12
114
4'-0"
3'-0"
P01
3'-6" TO 4'-0"
CCATWALK SUPPORT
3'-6"
P04
13'-9"
A01-F
P03
10/10/2019 9:42:55 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
A01-B
3'-6"
P04
3'-0"
3'-6"
105
2'-0"
3'-6"
115
4'-7 1/8"
3'-6"
3'-6"
1 A07
P01
16'
Scale: 1/8" = 1'-0"
3'-6"
3'-6"
101
102
4'-0"
3'-6"
100
L 8'
SCALE: 1/8" = 1'-0"
4'-0"
A01-A P07
3 A07 0'
4'-0"
P04
Level 1 New Work
2 A07
3'-0"
4'-0"
4'-0"
P03
A01-B
RECORD SUPPORT CATWALK S T O R AGE 12
4'-0" 4'-0"
104
UP
CATWALK SUPPORT
A03
4'-0"
3'-6"
13'-9"
2
4'-0"
111
2'-9 1/4" 4'-0"
112
4'-0"
111
4'-0"
113
P01
4'-0"
4'-0"4'-0" 3'-6" 3'-6" 3'-6"TO 3'-6" 4'-0" 4'-0" 4'-0"
A01-H
4'-0"
P01
4'-0"
101
4'-0"
104
4'-0"
P04
4'-0"
4'-0"
4'-0"
107
4'-0"
105
4'-0"
101
4'-0"
2'-0" 3'-4"
4'-0"
3'-0"
UP A01-J
A01-B
OPENING HEIGHT
13'-9"
109
A01-A
A01-B
OPENING HEIGHT
A01-H 2 A03
P06
A01-H P02
A01-A
SEE PLANS
FD
103
P01
A01-H
P01
4'-0"
A01-D
P05 P02
103
EPOXY FINISH EXPOSED CONCRETE FLOORING WITHIN OFFICE. NEW STAIR. CONSTRUCT AS PART OF STORAGE SHELVES AND CATWALK SYSTEM A01-D NEW METAL SIDING AND INSULATION. REFERENCE PARTITION DETAIL... A01-F INSTALL NEW CART LIFT. TYPICAL FOR TWO. A01-G INFILL DICK LEVELER PIT WITH CONCRETE SLAB ON METAL DECK AND 8"CONCRETE MASONARY WALL. A01-H CARPET TILE ON CONCRETE SLAB. A01-I EXTEND EXISTING 8" CMU WALL TO UNDERSIDE OF NEW 2 CONCRETE PLANK FLOOR. APPROXAMINTE ONE COURSE A03 A01-J NEW CONCRETE PAD. BROOM FINISH. MINIMUM 6" THICK. SIZE: 4'x4' P01 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD EACH SIDE. 1 P02 A03 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD EACH 7/8" 6" INSULATION. SIDE. WITH SOUND ATTENUATION P03 6" METAL STUDS 5/8" FIRE CODE X GYPSUM WALL BOARD NEW METAL PANEL EACH SIDE. SIDING TO MATCH EXISTING P04 3 5/8" METAL STUDS 5/8" FIRE CODE X GYPSUM WALL R21 BATT INSULATION BOARD EACH SIDE. GYPSUM SHEATHING AIR AND MOISTURE BARRIER P05 3 5/8" METAL STUDS 5/8" ABUSE RESISTANT GYPSUM WALL HAT CHANNELS @ BOARD EACH SIDE. WITH SOUND ATTENUATION INSULATION. GYPSUM WALLBOARD 24" O.C. P06 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD ONE SIDE. HEAD HEIGHT P07 3 5/8" METAL STUDS 5/8" GYPSUM WALL BOARD ONE SIDE. WITH R-13 BATT INSULATION. BASE TRIM
A
OPENING WIDTH
FD
3'-6"
A01-H
4'-0"
2
A05
A01-H
3'-6"
OUTSIDE
7 1/8"
SEALANT ALL SIDES @ FRAME CONT
W1 -2 4"
NEW WORK INSIDE
HEAD DETAIL
1" INSULATED GLASS
W4 - METAL STUD HEAD DETAIL
1
W2 - CMU HEAD DETAIL
SILL DETAIL
JAMB VIEW
CONTINUOUS SEALANT
B
A S
OUTSIDE
G WIDTH
3'-6"
OPENING HEIGHT
3'-6"
107
CATWALK SUPPORT
4'-0"
3'-6"
P02
3'-6"
P01
3'-6"
P01
3'-6"
2'-0"
2'-0"
K SUPPORT
3'-6"
OPENING HEIGHT
A 4'-0"
3'-6"
4"
2'-0"
L
3'-1"
A02-D
4'-0"
4'-11"
A02-D
M A E
10'-8"
9'-10 1/2"
A04
M A I N O F F I CE 1
14'-8"
3
K
8'-0"
CARPET TILE
4'-6 1/8"
UP
7'-7 1/2"
7'-2 1/2"
12
11'-7 3/4"
PRINTER AREA
COPY AREA
14'-8"
A02-F
A02-A
B
8'-0" 2'-0"
10
A09
F
EPOXY COATING
CARPET TILE
A09
6'-8"
AD MI N I S T RA T I V E O F F I CE 4
EPOXY COATING
2
A05
9
A02-B
8'-0"
10 5/8"
COPY AREA
CARPET TILE
15'-1"
A09
6'-5"
1
FD
4
A02-D
8'-0"
A03-G
R E TE NTI ON O F F I CE 2
12'-0"
5"
FD
BA T HR O O M 7
A09
2
E N T RY V E S T I B U LE 6
1'-8"
3
11
7'-1"
3'-4"
A09
C
EPOXY COATING
CARPET TILE
15'-6 1/8"
EPOXY COATING
G L
1'-6"
7
D
A09
8
21'-11"
5
3
C A R T LI F T 13
3
A05
D E LIVE R Y ROOM 3
M A I N O F F I CE 9
9'-7 1/2"
13
4
A09
11'-7 1/2"
4 1/2"
6'-0"
J
H
4'-10" 22'-2 5/8"
6'-0"
A02-D
E UP
1'-10"
4'-8"
A02-D
I J
1
A04 10/10/2019 9:42:57 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
4 1/2"
10'-5 7/8"
4'-7 1/8" A10
A02-E
EPOXY COATING
B R E AK R O O M 8 EPOXY COATING
9'-8 5/8"
A10
8'-0"
FD 6
11'-9 3/4"
8'-8"
CARPET TILE
A DA B A T HR O O M 5
NEW WORK LEVEL 1 SOUTH OFFICE SCALE: 1/4" = 1'-0"
0'
4'
8'
Scale: 1/4" = 1'-0"
2
A04
NEW WORK LEVEL 1 NORTH OFFICE SCALE: 1/4" = 1'-0"
I
0'
4'
8'
Scale: 1/4" = 1'-0"
17
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 22x22
2
A08
M
A
5'-7 7/8"
1'-3 1/2"
3 A07
INSTALL RAILINGS AS REQUIRED
CATWALK SYSTEM
5"
200
M E C H A N I CA L 10
I
MEZZANINE SYSTEM
B 10
A09
A
C
5"
200
M E C H A N I CA L 10
Level 4 20' - 0"
L D MEZZANINE SYSTEM
202
B
10
203
13
UP
A09
E
115'-1"
74'-2 1/4"
UP
K
1
A08
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 24x24
13'-9"
C
CONTINOUS METAL RUNNER. Level 4
8" HOLLOW CORE CONCRETE SLABS.20' - 0"
L
STEEL CLOSURE PLATE OR ANGLE
D 202
2
13
A09
OPEN TO BELOW
MATERIAL WOOL INSULATION
115'-1"
E UP
K
8" HOLLOW CORE SLAB 1-HR FIRE RATING
AIR / VAPOR BATTIER.
A05
13'-0"
203
Level 3 8' - 0"
1
A08
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 24x24
13'-9"
BUTLER RIB II METAL SIDING PANEL.
G CONTINOUS METAL RUNNER.
8" HOLLOW CORE CONCRETE SLABS.
SCALE: 1/8" = 1'-0"
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 19x10
G
Level 2 New Work SCALE: 1/8" = 1'-0"
5" 5'-7 7/8"
201
3'-0" 10/10/2019 9:43:01 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
s_Storage_turnerjl1.rvt
18
1 A07
1
5"
H
MATERIAL WOOL5/8" INSULATION GYPSUM SHEATHING
0'
8'
16'
Scale: 1/8" = 1'-0"
J OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 20x14
I OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 19x10
EXISTING 6" CONCRETE SLAB ON GRADE
Level 2 0"
OVERHEAD
FOUNDATION WALL
HORIZONTAL REINFORCING AT 8'-0" AFF
23'-7 3/4"
A05
6" METAL STUD WALL.
Scale: 1/8" = 1'-0"
M E C H A N I CA L 11
8" HOLLOW CORE STUD. SLAB 3 5/8" METAL 1-HR FIRE RATING
AIR / VAPOR BATTIER. HAT CHANNELS @ 24" O.C.
BUTLER RIB II METAL SIDING PANEL. EXISTING CONCRETE MASONRY
16'
UP
STEEL CLOSURE PLATE OR ANGLE 5/8" GYPSUM WALL BOARD
6" METAL STUDS @ 16" O.C. GYPSUM SHEATHING R-13 BATT INSULATION AIR/VAPOR BARRIOR
Level 3 8' - 0"
I
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 20x14
HORIZONTAL REINFORCING AT 8'-0" AFF
14'-0" ± EXISTING OVERHEAD DOOR OPENING
A05
Level 2 New Work
8'
A05
J
1 A07
0'
2
5'-7 7/8"
M E C H A N I CA L 11
UP
1
F
201
3'-0"
23'-7 3/4"
2'-0" CLEAR
R-13 BATT INSULATION
INSTALL 30X30 ACESS DOOR
3
A05
2 A07
F
MIN. 8'-0"
7 3/4"
OPEN TO BELOW
13'-0"
A09
2 A07
2'-0 CLEA
I
INSTALL 30X30 ACESS DOOR
3
A05
MIN. 8'-0"
CATWALK SYSTEM
MIN. 8'-0"
A08
M
INSTALL RAILINGS AS REQUIRED 74'-2 1/4"
14'-0" ± EXISTING OVERHEAD DOOR OPENING
1'-3 1/2"
7 3/4"
OPENING IN FLOOR. FIRE STOP 1-HR RATING. SIZE: 22x22
2
5'-7 7/8"
3 A07
UP
Level 1 -3' - 4"
6" METAL STUDS @ 16" O.C. GYPSUM SHEATHING AIR/VAPOR BARRIOR
5/8" GYPSUM WALL BOARD
HAT CHANNELS @ 24" O.C.
3 5/8" METAL STUD.
6" METAL STUD WALL.
H
5/8" GYPSUM SHEATHING
EXISTING D TO REMAIN.
EXISTING 6" CONCRETE SLAB ON GRADE
Level 2 0"
EXISTING CONCRETE MASONRY FOUNDATION WALL
Level 1 -3' - 4"
2
A05
Partition Detail Wall SCALE: 1/2" = 1'-0"
3
A05
Partition Detail SCALE: 1/2" = 1'-0"
EXISTING D
EXISTING CO FOUNDATIO
PATCH EXISTING METAL SIDING.
6'-8"
A07
SCALE: 1/8" = 1'-0" PATCH SIDING
NEW PRECAST LINTEL
REF: A03NEW PRECAST LINTEL
G
NEW PRECAST LINTEL
NEW WINDOW. NEW WINDOW. REFERENCE DETAIL W4REFERENCE IN DRAWINGDETAILS: 3-A03 W1, W2, & W3 IN DRAWING 3/A03 & DRAWING 3-A04
NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 IN DRAWING 3/A03
F
2
K F
NEW PRECAS
West Elevation K
E
A07
NEW PRECAST LINTEL NEW PRECAST LINTEL
PATCH SIDING
PATCH EXISTING METAL SIDING.
NEW PRECAST LINTEL NEW PRECAST LINTEL
6'-8"4'-0"
H G East Elevation
6'-8"
8" = 1'-0" CAST LINTEL REF: A03
PATCH SIDING
NEW WINDOW. REFERENCE DETAIL W4 IN DRAWING 3-A03 & DRAWING 3-A04
6'-8"
4
evation H
NEW PRECAST LINTEL
SCALE: 1/8" = 1'-0"
D
E
REF: A03
2
A07
NEW PRECAST LINTEL
CWest Elevation D SCALE: 1/8" = 1'-0"
C
NEW PRECAS NEW PRECAST LINTEL
PATCH SIDING NEW PRECAST LINTEL NEW WINDOW. REFERENCE DETAILNEW PRECAST LINTEL NEW WINDOW. NEWSIDING. WINDOW. REFERENCE DETAIL NEW WINDOW. PATCH EXISTING METAL SIDING. PATCH EXISTING METAL PATCH EXISTING METAL PATCH EXISTING METAL SIDING. W1, W2, & W3 W4 IN DRAWING 3-A03 NEW WINDOW. REFERENCE DETAIL SIDING.REFERENCE DETAILS: NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 W4 IN DRAWING 3-A03 REFERENCE DETAILS: W1, W2, & W3 W4 IN DRAWING 3-A03 & DRAWING 3-A04 IN DRAWING 3/A03 1 13 3/A03 & DRAWING 3-A04 IN DRAWING 3/A03 IN DRAWING & DRAWING 3-A04
REF: A03
A07
East Elevation REF: A03
SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"
PATCH EXISTING METAL SIDING.
SCALE: 1/8" = 1'-0"
PATCH EXISTING METAL SIDING.
PATCH EXISTING METAL SIDING. PATCH EXISTING METAL SIDING. K
F
E
REF: A03
PATCH EXISTING METALDSIDING.
13
2
A09
REF: A03
A07
West Elevation SCALE: 1/8" = 1'-0"
REF: A03
C
B
A
4'-0"
C
REF: A03
A07
A09
D E LIVE R Y B ROOM 3
REF: A03
Level 4
8'
A08
SCALE: 1/4" = 1'-0"
SCALE: 1/4" = 1'-0"
ELEVATIONS
SI
3/4"
I
L
J
I
L
J
A08
3
HOLOW CORE PRECAST CONCRETE
A08
Catwalk Floor Detail SCALE: 1 1/2" = 1'-0"
Level 4 20' - 0"
L
SCALE: 1 1/2" = 1'-0"
1904
Catwalk Floor Detail SCALE: 1 1/2" = 1'-0"
1904 SHELVING UNITS.
1904
8"
3'-6" 8"
3'-6"
3'-6"
6'-8"
6'-8"
ORTH
6'-8"
Level 2 0" Level 2 0"
A08
OFFICE AND STACKS SECTION SCALE: 1/4" = 1'-0"
6'-8"
Level 3 8' - 0"
IBC COMPLIANT STEEL PLATE STAIRS
OAD
CATWALK
PRELIMINARY
248-658-7777 PHONE 248-658-7781 FAX
NOT FOR CONSTRUCTION
SCALE:
Straub Pettitt Yaste
NOT FOR CONSTRUCTION
E
850 N SUITE 2 CLAWSON, M
248-658-7777 PH 248-658-7781 FAX
PRELIMINA
CATWALK
NOT FOR CONSTRUCT
IBC COMPLIANT STEEL PLATE STAIRS
3'-6"
IBC COMPLIANT STEEL PLATE STAIRS
SCALE: 1/4" = 1'-0"
SCALE: 1/4" = 1'-0"
ROOKS
CLAWSON, M ICHIGAN 48017-1311
6'-8"
HOLOW CORE PRECAST CONCRETE
FAX
UITE
PRELIMINARY
8" 8" Level 3 8' - 0"
1
CatwE
850 NORTH CROOKS ROAD SUITE 200 CLAWSON, M ICHIGAN 48017-1311
Straub CATWALK 248-658-7777 P e t248-658-7781 titt N C R Y a s t e S 850200
CATWALK
3'-6"
Level 4 Level 3 20' -8'0"- 0"
A08
A08
PHONE
SHELVING UNITS.
SECTIONS
8"
10/10/2019 9:43:08 AM
HOLOW CORE PRECAST CONCRETE
Straub Pettitt Yaste
SHELVING UNITS.
SHELVING UNITS.
A08
3
© 2018 STRAUB PETTITT YASTE
© 2018 STRAUB PETTITT YASTE
Level 3 8' - 0"
10/10/2019 9:43:08 10/10/2019 AM 9:43:08 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
J
HOLOW CORE PRECAST CONCRETE
Level 4 20' - 0"
Level 2 0"
SCALE:
RECORD STORAGE
© 2018 STRAUB PETTITT YASTE
I
Catw
RECORD STORAGE WAREHOUSE WAREHOUSE MICHIGAN DEPARTMENT OF FILE NO: 472/19173.CDPFILE NO: 472/19173.CDP CORRECTIONS 1780 E. PARNALL ROAD 1780 E. PARNALL RO RECORD STORAGE JACKSON, MI 49201 JACKSON, MI 49201 WAREHOUSE FILE NO: 472/19173.CDP 1780 E. PARNALL ROAD JACKSON, MI 49201
33 Catwalk Floor Detail A08
HOLOW CORE PRECAST CONCRETE
CORRECTIONS
1 1/2"
3/4" 1 1/2"
J
3
A08
MICHIGAN DEPARTM A07 MICHIGAN DEPARTMENT OF CORRECTIONS
1 1/2"
L
1 1/2"
SCALE: 1 1/2" = 1'-0"
C E
OFFICE SECTION OFFICE SECTION
6'-8" HIGH DOOR
Catwalk Floor Detail
U NU M
3
6'-8" HIGH DOOR
J
L URI BUS E P
L
U NU M
A08
A08
J
SCALE: 1/4" = 1'-0"
L URI BUS E P
22
I L
OFFICE SECTION
3/4"
2
A08
16'
Scale: 1/8" = 1'-0"
STATE OF MICHIGAN
0'
U NU M
NOT FOR CONSTRUCTION
R E TE NTI ON O F F I CE 2
L URI BUS E P
PRELIMINARY
R E TE NTI ON O F F I CE 2
C E
1'-4 5/8"
1'-4 5/8"
1'-4 5/8"
3
850 NORTH CROOKS ROAD SUITE 200 CLAWSON, M ICHIGAN 48017-1311
248-658-7777 PHONE 248-658-7781 FAX
6'-8" HIGH DOOR
OFFICE AND STACKS SECTIONSECTION 11 OFFICE FICE AND STACKS SECTION AND STACKS
E: 1/4" = 1'-0"
D E LIVE R Y ROOM 3
6'-8" HIGH DOOR
DNETILOINVERY R ETE O F F IR CEOOM 2
8" HOLLOW CORE DECKS.
Straub Pettitt Yaste
R C U M S P I
AD MI N I S T RA T I V E O F F I CE 4
8" HOLLOW CORE DECKS.
6'-11 3/8"
6'-8" HIGH DOOR
D E LIVE R Y ROOM 3
6'-111'-4 3/8" 5/8"
M A I N O F F I CE 9
© 2018 STRAUB PETTITT YASTE
R E TE NTI ON O F F I CE 2
6'-11 3/8"
AD MI N I S T RA T I V E O F F I CE 4
6'-8" HIGH DOOR
6'-8" HIGH DOOR
Level 2 0"
10/10/2019 9:43:06 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
6'-8" HIGH DOOR
Level 2 0"
Level 4 20' - 0"
10/10/2019 9:43:06 AM 10/10/2019 9:43:06 AM C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt rage_turnerjl1.rvt
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
M A I N O F F I CE 9
12 ADMINISA09 T RA T IVE O F F I CE 4
Level 2 0"
HOLOW CORE PRECAST CONCRETE
8"
1'-4 5/8"
M A I N O F F I CE 9
Level 3 8' - 0"
I
A09
SCALE: 1/4" = 1'-0"
A09
6'-11 3/8"
OFFICE SECTION
6'-111'-4 3/8" 5/8"
A08
Level 3 8' - 0"
12
6'-11 3/8"
Level 3 8' - 0"
E: 1/4" = 1'-0"
TUCK POINT EXTERIOR MASONARY WALLS
12
D E LIVE R Y ROOM 3
6'-11 3/8"
2
FICE SECTION
3'-6"
TUCK POINT EXTERIOR MASONARY WALLS
AD MI N I S T RA T I V E O F F I CE 4
6'-8" HIGH DOOR
6'-8" HIGH DOOR
6'-11 3/8"
Level 4 20' - 0"
1904
1'-4 5/8"
1'-4 5/8"
Level 20'2- 0" 0"
4'-0"
WAREHOUSE FILE NO: 472/19173.CDP 1780 E. PARNALL ROAD JACKSON, MI 49201
South Elevation SCALE: 1/8" = 1'-0"
NEW PRECA NEW WINDOW. NEW WINDOW. REFERENCE DE REFERENCE DETAIL ETENTION 3/ INRDRAWING IN HOLLOW DRAWINGCORE 3/A03 8" O F F I CE DECKS. 2
A
NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 MICHIGAN DEPARTMENT OF RE3/A03 TE NTI ON IN DRAWING O F F I CE A CORRECTIONS NEW PRECAST LINTEL 2 RECORD STORAGE
QU
SCALE: 1/8" = 1'-0"
1
REF: A03
B
SI
ROOM
3 South Elevation TUCK POINT EXTERIOR MASONARY WALLS
SCALE: 1/8" = 1'-0"
C I
D D E LIVE R Y
A07
C
DESIGN AND DESIGN CONSTRUCTION AND CONSTRUCTION DIVISIONDIVISION
A07 13
REF: A03
ROBERT C. ROBERT HALL, RA, C. HALL, NCARB, RA,DIRECTOR NCARB, DIRECTOR
1
A08
13
A09
D
NEW PRECAST LINTEL
NEW PRECAST LINTEL
DEPARTMENT DEPARTMENT OF TECHNOLOGY, OF TECHNOLOGY, MANAGEMENT MANAGEMENT AND BUDGET AND BUDGET STATE FACILITIES STATEADMINISTRATION FACILITIES ADMINISTRATION
12
1
SCALE: 1/8" = 1'-0"
IN DRAWING 3/A03
NEW PRECAST LINTEL
South Elevation
R C U M S P I
1
A08
TUCK POINT EXTERIOR MASONARY WALLS
A07
REF: A03
A09
QU
NEW LOUVER K E COORDINATE WITH MECHANICAL AD MI N I S T RA T I V E O F F I CE TUCK POINT EXTERIOR K MASONARY WALLS E 4
SCALE: 1/8" = 1'-0"
13
1
1'-4 5/8"
1
A08
1'-4 5/8"
A07
A09
4'-0"
12'-0" 8'-0" A09
C I
REF: A03
8'-0"
12
11SouthSouth Elevation Elevation
NEW WINDOW. NEW WINDOW. REFERENCE DE REFERENCE DETAIL IN DRAWING 3/ IN DRAWING 3/A03
3/4"
SCALE: 1/8" = 1'-0"
12
NEW PRECA
NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 IN DRAWING 3/A03
NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 IN DRAWING 3/A03
6'-11 3/8"
F
C
STATE OFSTATE MICHIGAN OF MICHIGAN
A07
D
6'-11 3/8"
REF: A03
F
North Elevation
E
NEW PRECAST LINTEL
1'-4 5/8"
North Elevation SCALE: 1/8" = 1'-0" REF: A03
K
NEW PRECAST LINTEL
A09
North Elevation
6'-11 3/8"
3
8'-0"
NEW LOUVER COORDINATE WITH MECHANICAL
NEW LOUVER NEWA03 PRECAST LINTEL REF: A03 SCALE: 1/8" = 1'-0" REF: COORDINATE H G NEW WINDOW. NEW WINDOW. WITH MECHANICAL REFERENCE DETAILS: W1, W2, & W3 REFERENCE DETAILS: W1, W2, & W3 A D M I N I S T RA T IVE Level 4 IN DRAWING 3/A03 IN DRAWING 3/A03 M A I N O F F I CE M A I N O F F I C E O F F I CE 20' - 0" 6'-8" HIGH DOOR 6'-8" H G HIGH DOOR 9 9 4
levation
8" = 1'-0"
W1, W2, & W3
F NEW LOUVER COORDINATE WITH MECHANICAL
6'-11 3/8"
Level 3A07 8' - 0"A07
NEW WINDOW. REFERENCE DETAILS: REFERENCE IN DETAILS: W1, W2, &3/A03 W3 DRAWING IN DRAWING 3/A03
NEW LOUVER COORDINATE WITH MECHANICAL
1'-4 5/8"
NEW PRECAST LINTEL
33
NEW PRECAST LINTEL NEW WINDOW.
4'-0"
4'-0"
8" = 1'-0"
NEW PRECAST LINTEL
NEW WINDOW. REFERENCE DETAILS: W1, W2, & W3 IN DRAWING 3/A03
13
A09 8'-0"
G
NEW PRECAST LINTEL
Elevation
1
A08
4'-0"
H
12'-0" 8'-0"
4'-0"
4'-0"
12'-0"
Level 4 20' - 0"
SCALE: 1/8" = 1'-0"
A07
REF: A03
1
A08
A09
A07 PATCH EXISTING METAL SIDING.
G
22WestWest Elevation Elevation
A08
East Elevation
12'-0"
A07
12'-0"
8" = 1'-0"
44
B
REF: A03
NEW PRECAST LINTEL
evation
PATCH EXISTING
PATCH EXISTING METAL SIDING.
INFILL MASONARY WALL
4'-0"
PATCH NEWSIDING PRECAST LINTEL
ECAST LINTEL
PATCH EXISTING METAL SIDING. INFILL MASONARY WALL
INFILL MASONARY WALL
PATCH EXISTING METAL SIDING.
4'-0"
INFILL OPENING
INFILL OPENING
PATCH EXISTING METAL SIDING.
INFILL OPENING
6'-8" 4'-0"
PATCH EXISTING METAL SIDING. INFILL OPENING
4'-0"
INFILL OPENING
INFILL OPENING
IBC COMPLIANT STEEL PLATE STAIRS
SECTIONS
19 A08
A08
6"
2'-8"
PAPER TOWEL DISPENSER
4'-0"
3'-2"
FLOOR MOUNTED TOILET
T.P. DISPENSER
1'-3"
3'-6" 2'-10"
GRAB BARS
1'-3"
1
A09
Elevation 2-A
SCALE: 1/4" = 1'-0"
REF: A04
2
A09
Elevation 2-B
SCALE: 1/4" = 1'-0"
3
A09
REF: A04
Elevation 2-C SCALE: 1/4" = 1'-0"
REF: A04
4
Elevation 2-D
A09
SCALE: 1/4" = 1'-0"
5
A09
REF: A04
PAPER TO DISPENS
6" 1'-6"
MIRROR
T.P. DISPENSER
2'-10"
1'-8"
Elevation 1-A
SCALE: 1/4" = 1'-0"
REF: A04
6
Elevation 1-B
A09
M
SCALE: 1/4" = 1'-0"
REF: A04
7
A09
Elevation 1-C SCALE: 1/4" = 1'-0"
REF: A04
I
EXPANTION JOINT COVER FASTEN TO CONCRETE
CATWALK PLANKS
MAX 1"
GROUT CORES SOLID ALONG EXPOSED EDGE. 8" HOLLOW CORE PLANKS
6 1/4" 3 1/2"
W16x40
4"
4"
8"
FILL VOID WITH MINERAL WOOD INSULATION
W16x40
7/8"
1'-11" MAX.
3 5/8"
20 x 12 DUCT
8'-0"
1'-4 5/8"
12 x 20 DUCT CATWALK SUPPORT STRUCTURE TYPICAL
1'-4 5/8"
Level 3 8' - 0" 8'-4"
Level 3 8' - 0"
5/8"
5/8"
3 5/8"
1'-11" MAX.
3 1/2"
9 1/2"
2'-4 1/4"
4 1/2"
4 7/8"
3'-4 1/4" 8"
6" METAL STUD @ 16" O.C. 5/8"
6.21
10 A09
Soffet Section
SCALE: 1 1/2" = 1'-0" REF: A04
4 7/8"
5/8"
5/8" GYPSUM ON 3 5/8" METAL STUD @ 16" O.C.
TO CONCRETE SLAB
J
11 A09
Soffet Exterior Wall Section SCALE: 1 1/2" = 1'-0" REF: A04
6.21 Level 3 8' - 0"
J
M
Level 2 Existing 8' - 0"
APPROX 1'-6" SAWCUT EXISTING CONCRETE SLAB
VERIFY WITH LIFT MANUFACTURER
20
5" ± 6" TAPE NEW VAPOR BARRIER TO EXISTING OVERLAP MIN 4"
4" - 6"
6"
4" MIN GRANULAR FILL
#4 DOWELS @ 24" O.C. MIN 6" INTO EXISTING SLAB. SET WITH EPOXY. MIN 12" INTO NEW SLAB.
10/10/2019 9:43:12 AM
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
Level 2 0"
6x6 W2.1 WWF
14
A09
6X6 W21 WWF
NEW VAPOR BARRIOR.
6 7/8"
4'-7 1/8"
COMPA
12 A09
Section 1
SCALE: 1 1/2" = 1'-0" REF: A04
14 A09
Cart Lift Secion - Callout 1 SCALE: 1 1/2" = 1'-0"
13 A09
Cart Lift Secion SCALE: 1/2" = 1'-0"
REF: A04
I
GENERAL NOTES
I
Elevation 3 - A SCALE: 1/4" = 1'-0"
REF: A04
FRIDGE BY OWNER
Level 3 8' - 0"
Level 3 8' - 0"
3'-0"
FILL VOID WITH MINERAL WOOD INSULATION EXISTING CONCRETE SLAB
2'-0"
2'-8"
8"
4
A10
5
Casework Elevation
A10
SCALE: 1/2" = 1'-0"
Level 2 0"
Level 2 0"
3
A10
4
Casework Section SCALE: 1/2" = 1'-0"
A10
2
SEALANT ALL SIDES @ FRAME CONT
1904
CORRIDOR SIDE
FOR OPENINGS WIDER THAN 5'-0" PROVIDE (2) 6" DEEP STUDS WITH TOP AND BOTTOM RUNNER. SECURE TO STUDS AT EA END 1/2" TYP EACH SIDE
- WWF 6X6 W21
1/4" CLEAR 1/4" CLEAR 6 7/8"
No Threshold D4 No Threshold D4 No Threshold D4 No Threshold D4 4'-7 1/8"
D3 D3 D3 D3
No Rating No Rating 45 MIN 45 MIN 5"
COMPACTED GROUND
13 A09
Cart Lift Secion SCALE: 1/2" = 1'-0"
REF: A04
SEE EXTERIOR AND INTERIOR SEALANT ALL ELEVATIONS SIDES @ FRAME
2 A09
ELEVATIONS AND DETAILS
5/8"
Door Details
3' - 0" 3' - 0" 3' - 0" 3' - 0"
7' - 0" 7' - 0" 6' - 8" 6' - 8"
G G F F
HM HM HM HM
-
OPENING WIDTH
2"
HEAD HEIGHT 6'-10"
REMOVABLE MULLION
3
2"
CMU LINTEL WITH (2) # 5 BARS GROUTED SOLID, TWO 8" MINLEAVES BEARING, EA SIDE
2"
RECORD WAREHO FILE NO 1780 E ONEJACKSO LEAF
1904
FRAME 2 - SEE SCHEDULE
1
© 2018 ST
DOOR - SEE SCHEDULE
D2 - CMU HEAD DETAIL
GLASS 1" CLEAR INSUL 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1" CLEAR INSUL 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1" CLEAR INSUL -
D3 - METAL STUD JAMB DETAIL
MECHANICAL 200 MECHANICAL 201 LIFT 1 1/2" = 1'-0"202 A10CARTSCALE: CART LIFT 203 Level 2 Existing: 4 TOTAL DOORS: 21
MICHIG CORRE
OPENING WIDTH
SEE FLOOR PLANS FOR PARTITION TYPE
TWO LEAVES
CONT
D4 - METAL STUD HEAD DETAIL
PRELIMINARY
8'-0"
2"
2"
PRECAST CONCRETE LINTEL
F
2" 2"
FIRE RATING No Rating No Rating 45 MIN No Rating 45 MIN No Rating No Rating No Rating No Rating No Rating No Rating No Rating No Rating No Rating 45 MIN 45 MIN
G
DOOR WIDTH
SILL
FRAME - SEE SCHEDULE
SEE PLANS
THRESHOLD ALUM No Threshold No Threshold No Threshold No Threshold ALUM No Threshold No Threshold ALUM ALUM No Threshold No Threshold No Threshold ALUM No Threshold No Threshold
RD
HEAD HEIGHT 6'-10"
GLASS - SEEFLUSH DOOR VERT-LIFT DOOR FLUSH DOOR ELEVATIONS FOR W/ HALF LITE FRAME HDWE TYPE, GT-05 UNO TYPE MATERIAL FINISH GLASS SET REMARKS 2 Metal - Painted - Grey 1 INSULATED DOOR DOOR SCHEDULE 2 HM Metal - Painted - Grey 2 "R" REVISED DOOR, "N" NEW DOOR 2 HM Metal - Painted - Grey 3 S t r4a u b 1 HM Metal - Painted - Grey DELETED DOOR(S): NONE GROUT FRAMES 1 HM Metal - Painted - Grey - P e 5t t i t t 850 NORTH CROOKS ROAD SOLID. 2 HM Metal - Painted - Grey - Y a 2s t e SUITE 200 JAMB VIEW CLAWSON, M ICHIGAN 48017-1311 OPENING SIZE DOOR 1 HM Metal - Painted - Grey 4 OPNG # ROOM NAME WIDTH HEIGHT TYPE MATERIAL FINISH 1 HM Metal - Painted - Grey 6 248-658-7777 PHONE FAX RETENTION OFFICE 100 6' - 0" 6' - 6" G HM 1 HM Metal - Painted - Grey 7248-658-7781 INSULATED DOOR RETENTION OFFICE 101 6' - 0" 6' - 8" G ACOUSTIC HM 1 HM Metal - Painted - Grey 8 INSULATION TO RECORD STORAGE 102 6' - 0" 6' - 8" G MATCH HMPARTITION 1 HM Metal - Painted - Grey 6 MAIN OFFICE 103 3' - 0" 6' - 8" G HM 1 HM Metal - Painted - Grey 4 DELIVERY ROOM 104 3' - 0" 6' - 8" F HM 1 HM Metal - Painted - Grey 5 BACK TO BACK ADMINISTRATIVE OFFICE 105 6' - 0" 6' - 8" G DOUBLE HM STUDS 1 HM Metal - Painted - GreyNOT -FOR CONSTRUCTION 9 INSULATED DOOR ADMINISTRATIVE OFFICE 106 3' - 0" 6' - 8" F WITHHM 1 HM Metal - Painted - Grey 10 VERT-LIFT DOOR RUNNER ON BATHROOM 107 3' - 0" 6' - 8" F OPENING HM SIDE 1 HM Metal - Painted - Grey 10 VERT-LIFT DOOR SECURED TO EA ENTRY VESTIBULE 108 3' - 0" 6' - 6" G OTHER HM @ 16" OC OVERHEAD DOOR ADMINISTRATIVE OFFICE 109 3' - 0" 6' - 8" G HM DOWEL NEW SLAB INTO EXISTING SLAB 4 @ 24" O.C. ADA BATHROOM 110 3' - 0" 6' - 8" F INSULATION HM AT WALLS MAIN OFFICE 111 3' - 0" 6' - 8" G RESTROOM HM 1 HM Metal - Painted - Grey 4 BREAK ROOM 112 3' FINISH - 0" FACE 6' - 8" G ONLY. HM 1 HM Metal - Painted - Grey 4 OF ADJACENT RECORD STORAGE 113 3' WALL - 0" WHERE 7' - 2" G HM 1 HM Metal - Painted - Grey 10 VERT-LIFT DOOR CART LIFT 114 3' APPLICABLE - 0" 6' - 8" F HM 1 HM Metal - Painted - Grey 10 VERT-LIFT DOOR CART LIFT 115 3' - 0" 6' - 8" F HM WLF DELIVERY ROOM 116 8' - 0" 8' - 0" Level 1 Existing: 17
10/10/2019 9:43:15 AM
HM HM14 A09 HM HM
GLASS 1" CLEAR INSUL 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1" CLEAR INSUL 1/4" CLEAR 1/4" CLEAR 1/4" CLEAR 1" CLEAR INSUL -
DETAILS HEAD JAMB D2 D1 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D2 D1 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3
C:\Users\JonTurner\Documents\1904_Sra_Files_Storage_turnerjl1.rvt
G G F F
DOOR FINISH -
FOR PARTITION TYPE
5/8"
DOOR HEIGHT
© 2018 STRAUB PETTITT YASTE
OPENING SIZE # WIDTH HEIGHT TYPE MATERIAL 6' - 0" 6' - 6" G HM 6' - 0" 6' - 8" G HM 6' - 0" 6' - 8" G HM 3' - 0" 6' - 8" G HM 3' - 0" 6' - 8" F HM G HM LIFT6' - 0" 6' - 8" RER 3' - 0" 6' - 8" F HM 3' - 0" 6' - 8" F HM 3' - 0" 6' - 6" G HM 3' - 0" 6' - 8" G HM 3' - 0" 6' - 8" F HM 3' - 0" 6' - 8" G HM 3' - 0" 6' - 8" G HM 3' - 0" 7' - 2" G HM 3' - 0" 6' - 8" F HM 3' - 0" 6' - 8" F HM 8' - 0" 8' - 0"
FOR OPENINGS WIDER THAN 5'-0" PROVIDE #4 BAR OPENING STIRRUPS @ 8" OC WIDTH MAX , GROUT COURSE ABOVE LINTEL SOLID
9"
RECORD STORAGE WAREHOUSE FILE NO: 472/19173.CDP 1780 E. PARNALL ROAD 1 JACKSON, MI 49201
STC-50 MIN
INSULATION AT RESTROOM WALLS ONLY. OPENING SEE FLOOR PLANS WIDTH
OPENING WIDTH 6" 6"
METAL STUD WIDTH RUNNER, RETURN UP AND SECURE TO STUDS @ EA END
2"
2"
MICHIGAN DEPARTMENT OF ONE LEAF CORRECTIONS
OPENING HEIGHT
2" OPENING HEIGHT
TWO LEAVES
REMOVABLE MULLION
3
2"
2"
GLAZING TYPE (SEE 088000) HOLLOW METAL THRESHOLD/TRANSITION
F R AM E TY P E S
3'-6"
FLUSH DOOR
7' - 0" 7' - 0" 6' - 8" 6' - 8"
GT HM TR
SEE SCHD
1/2" MIN
FLUSH DOOR W/ HALF LITE
TWO LEAVES
A
ALUM ALUMINUM SCALE: 1/2" = 1'-0"
D O OR T Y P E S
OPENING HEIGHT
F
OPENING WIDTH
2"
G
2"
2" SEE EXTERIOR AND INTERIOR ELEVATIONS
11'-0"
OPENING HEIGHT
OPENING HEIGHT
2"
9"
OPENING WIDTH
OPENING HEIGHT
4 7/8"
OPENING WIDTH
2"
4 7/8"
OPENING HEIGHT
OPENING WIDTH
5
Casework Elevation ABBREVIATIONS
4 7/8"
8"
OPENING WIDTH 6" 6"
3'-6"
1'-0"
SCALE: 1 1/2" = 1'-0"
F R AM E TY P E S
3' - 0" 3' - 0" 3' - 0" 3' - 0"
1. ADD "ADA" PUSH BUTTON TO DOOR REFER TO PLAN FOR LOCATION. 2. ADD "KEY READER" TO DOOR REFER TO PLAN FOR LOCATION. REFER TO SECURITY DRAWINGS. 3. DOOR SIZE TO ALIGN WITH EXTERIOR MULLIONS/GLAZING. COORDINATE FINAL SIZE. 4. PAINT EXTERIOR SIDE OF DOOR AND FRAME TO MATCH ADJACENT METAL SIDING. 5. PROVIDE FLOOD PLANKING 6. SEE EXTERIOR ELEVATIONS FOR FRAME TYPE/ELEVATION. 7. INSULATED EXTERIOR DOOR. 8. DOOR TO ALWAYS BE LOCKED W/ KEY (INSIDE STAIR). 9.2'-0" SMOKE EVACUATION DOOR (TIE TO POWER AND2'-6" FIRE± ALARM SYSTEM). 2'-0" 2'-8" 10. PAINT EXTERIOR SIDE OF DOOR AND FRAME TO MATCH ADJACENT METAL SIDING. 11. KEYPAD DOOR6'-8" HARDWARE FOR HOME TEAM. 12. DOOR SIZE TO ALIGN WITH EXTERIORMULLIONS/GLAZING. COORDINATE FINAL SIZE. 13. PAINT PUBLIC SIDE OF DOOR AND FRAME TO MATCH ADJACENT ACCENT WALL.
6X6 W21 WWF
Slab joint detail
2"
4 1/2"
3'-0"
6'-8"
n
OVEN BY OWNER REMARKS
NEW CONCRETE SLAB
#4 DOWELS @ 24" O.C.
2'-6" ±
2"
2'-0"
OPENING HEIGHT
Level 2 0"
OPENING HEIGHT
3'-0"
1'-6" 4"
2"
9
A09
REF: A04
OPENING HEIGHT
TOASTER OVEN BY OWNER
SCALE: 1/4" = 1'-0"
JAMB VIEW
THRESHOLD ALUM No Threshold No Threshold No Threshold No Threshold ALUM No Threshold No Threshold ALUM ALUM No Threshold No Threshold No Threshold ALUM No Threshold No Threshold
DETAILS HEAD JAMB 7SILL 3/4" D2 D1 D4 D31/4" D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D2 D1 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3 D4 D3
GROUT FRAMES SOLID
FIRE RATING No Rating No Rating 45 MIN No Rating 45 MIN No Rating No Rating No Rating No Rating No Rating No Rating No Rating No Rating No Rating 45 MIN 45 MIN 2"
MICROWAVE BY OWNER
Elevation 1-D
A09
8"
8
3/4"
REF: A04
OPENING WIDTH
SCALE: 1/4" = 1'-0"
3'-0"
Elevation 1-C 2'-0"
OPENING HEIGHT
-6"
7
A09
REF: A04
1'-6" 3/4" 1'-5" 3/4"
1'-6" 3/4" 1'-5" 3/4"
CALE: 1/4" = 1'-0"
1'-6" 3/4" 1'-5" 3/4"
3'-0"
2'-10"
FLOOR MOUNTED TOILET.
Level 3 8' - 0"
Elevation 1-B
A. ALL HOLLOW METAL FRAMES SHALL BE GROUTED SOLID. B. INSTALL EXTERIOR FRAMES WITH 1/4 INCH SHIM AND JOINT SEALANT AROUND PERIMETER OF FRAME. C. MASONRY LINTELS AND STEEL LINTELS ARE INDICATED ON STRUCTURAL DRAWINGS. D. GLASS TYPES FOR DOORS ARE INDICATED IN NOTES COLUMNS OF DOOR AND FRAME SCHEDULE OR IN SPECIFICATIONS. GLASS TYPES FOR FRAMES ARE INDICATED ON FRAME ELEVATIONS OR IN SPECIFICATIONS. E. EXTERIOR WINDOW FRAME TYPES ARE INDICATED ON FLOOR PLAN WITH HEXAGON SYMBOL. F. OVERHEAD COILING DOORS, GRILLES AND SECTIONAL DOORS WIDTH H AND HEIGHT DIMENSIONS INDICATED IN DOOR AND FRAME SCHEDULE REPRESENT FURNISHED OPENING SIZE. CONTRACTOR TO COORDINATE EXACT SIZE OF DOOR WITH MANUFACTURER. G. FRAME MANUFACTURER SHALL COORDINATE LOCATIONS OF CONCEALED CONDUIT AND J-BOXES REQUIRED FOR SECURITY SYSTEM HARDWARE PRIOR TO MANUFACTURING OF HOLLOW METAL FRAMES AND COORDINATE WITH SECURITY HARDWARE AND DEVICES. H. PROVIDE HEAD RECEIVERS AT ALUMINUM STOREFRONTS AND CURTAINWALLS AS REQUIRED FOR FRAME AND STRUCTURAL DEFLECTION. I. SEE SPECIFICATIONS 087100 HARDWARE FOR HARDWARE SET NOTED IN DOOR SCHEDULE. J. MAX AIR LEAKAGE RATE FOR DOORS TO BE 0.2 CFM/SF K.2'-0" REFER3/4" TO FLOOR PLANS FOR PARTITION TYPES. L. ALL DOORS TO BE 1 3/4" THICK UNLESS NOTED OTHERWISE. M. DOOR OPENING SIZES ARE INSIDE FRAME DIMENSIONS. N. ALL HOLLOW METAL FRAMES TO BE 2" THICK UNLESS NOTED OTHERWISE. MICROWAVE FRIDGE O. PROVIDE DOOR SILENCERS AT ALL FRAMES WITH STOPS (3 PER LEAF). BY OWNER BY P.OWNER ALL DOORS AND FRAMES TO BE CUSTOM COLORED TO MATCH COLOR INDICATED. Q. REFER TO FINISH LEGEND/KEY ON A-621 FOR FINISHES. TOASTER
H
SEE PLANS
6"
1'-6" 3/4" 1'-5" 3/4"
3'-0"
PAPER TOWEL DISPENSER
HM HM HM HM
FRAME H FINISH GLASS Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey -NOT Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey Metal - Painted - Grey -
HM HM HM HM
Metal - Painted - Grey DOOR S Metal - Painted - Grey Metal - Painted - GreyDETAILS Metal - Painted - Grey -
TYPE MATERIAL BULLNOSE 2 CORNER, TYP, 2 HM EXCEPT AT 2 HM ADJACENT WALLS
1 1 2
HM HM HM
1
HM
FINISH FACE 1 HM OF ADJACENT 1 WHERE HM WALL APPLICABLE 1 HM
1 HM GROUTED SOLID, FULL 1 HEIGHTHM 1 1 1 1
PRE
D1 - CMU JAMB DETAIL 1/4" CLEAR 1/4" CLEAR -
No Threshold No Threshold No Threshold No Threshold
D4 D4 D4 D4
D3 D3 D3 D3
No Rating No Rating 45 MIN 45 MIN
1 1 1 1
21
Abstract This thesis establishes a foundational understanding of current autism-friendly design approaches and conceptualizes new methods in research and design. Early on in the research an intimate connection between architecture and occupant wellness is established. Which is then applied from the perspective of occupancy driven design tactics. Specifically focusing on people with Autism Spectrum Disorder (ASD), the research constructs an inclusive framework that can be used as a design instrument that guides architectural decision making or as an analytical tool for reviewing precedent studies. Lastly, this framework is implemented in a design proposal that tests and demonstrates applications. An autism-friendly design approach places emphasis on inclusive design practices, evidence-based architecture, intentional spatial construction, and occupant wellness allowing architecture to respond to the intimate needs of occupancy.
Neurodiversity in Architecture
Confronting the Agency of Autism Within the Built Environment
This thesis was developed within the masters of architecture graduate program at the University of Detroit Mercy and won the The 2020 Bruno Leon Top Architectural Thesis Award. Project scope, research methods, area of interest, and depth of research were all student driven and assessed by the graduate professors & external jurors.
Chapters 01
Typological Analysis
02
Understanding Occupancy
03
Sensory Spaces
04
Meaning in Home
05
Immersion Environments
06
Review of Expert Approaches
07
Synthasis into Framework
08
Case Study Analysis
09
Universal Design Discussion
10
Conceptual Building
11
Reflection
12
References & Figures
Building Proposal Concept Statement The objective of the proposed building will be to structure an integrated experience through spatial design and programmatic functions. This facility fosters an approach to autism-friendly design that integrates people with ASD and the general population. In turn, this creates an environment that advocates for an educational awareness and understanding of ASD through programmatic prescriptions and specific design strategies. To achieve this integration of occupancy, the programmatic functions need to include a public attraction, occupational component for people with ASD, and educational elements. Additionally, the manifestation of autism-friendly design strategies will be interwoven with neuro-typical spaces as a reflection of the intended occupancy. This will test and demonstrate concepts found in the research, which will serve as an example of how these findings can be applied.
This section of the portfolio will focus on the building that was designed to embody the thesis research and demonstrate design practices that incorporate autism-friendly design practices. Professor Wladek Fuchs - Advisor Magda Mostafa - External Advisor
Site Location The site includes a historically designated 8,000 SF Googie Style building that was constructed in 1971 by African-American Detroit architect Nathan Johnson. Originally opening as Stanley Hong’s Mannia Café, the existing building features a prominent façade along the south and west elevations and an expressive main entry, both of which are specified to be preserved. Located in the Milwaukee Junction Neighborhood, the site is zoned for mixed-use and surrounded by parking lots, smallscale industrial, and residential properties.
As-Built Massing Diagram
As-Built South Elevation The selected site for this design proposal was chosen to take advantage of an existing network of assets in the surrounding area that are dedicated to educating, diagnosing, and treating children with ASD. Situated on the threshold between a dense urban center and the suburbs, this site provides an accessible geographic location.
ue,
24
265
Ea
Mi.
D
o
tim
al st B
ven re A
it etro
DETROIT, MI
Project Location : Detroit Michigan
Legend 1) Bus stop & QLINE Access 2) Detroit Amtrack Transit Station 3) University Pediatriciands Autism Center 4) DMC Harper Hospital 5) Childrens Hospital of MI Specialty Center 6) Henry Ford Hospital 7) Henry Ford Autism Center
Asset/Location Map
Figure-Ground Diagram
25
Program & Proposed Layout The design solution incorporates an intimate connection with Wayne State which allows for a collaborative partnership that adds to the existing network of education, research, treatment, and outreach for people with ASD. This is embodied in the programming of the facility. Which is specified as -
Sensory CafÊ – Restaurant Public Gallery Fitness Center Community Resource Center Art Studios And a Roof-deck Sculpture Garden
These programmatic components respond to the design approach as well as research findings, placing emphasis on the interaction between programmatic articulation and architectural form.
26
Exterior Perspective - Proposed Building
27
Site Plan
West Elevation PRODUCED BY AN AUTODESK STUDENT VERSION
Conceptual Exterior Perspective
Program: - Art Studio
- Community Resource Center
- Art Gallery (Second Floor)
- Fitness Center
- Public Art Gallery
Exploded Axonometric`
- Sensory Café – Restaurant 29
SENSORY SPACE
GROUP FITNESS ROOM
MEN'S LOCKER ROOM
WOMEN'S LOCKER ROOM
CARDIO
GYM ENTRY AND RECEPTION
FREE WEIGHTS
UP
WOMEN'S LAV.
Sensory Space MEN'S LAV.
RESISTANCE TRAINING
COMMUNITY ENGAGEMENT CENTER
ELEVATOR
Cardio Training
ELEVATOR UP ART GALLERY
WOMEN'S LAVATORY
PANTRY
WALK IN FRIDGE/ FREEZER
MEN'S LAVATORY
BACK OF HOUSE
CARE - RESTAURANT
Cafe View First Floor Plan
GALA-CAFE
OFFICE / WORKSHOP
COLLABORATIVE ART STUDIO GROUP WORK ROOM
LEAD MANAGERS OFFICE / WORKSHOP
Collaborative Art Studio DN
PRODUCED BY AN AUTODESK STUDENT VERSION
INDIVIDUAL OFFICE / WORKSHOP
COMMUNITY RESOURCE CENTER
ELEVATOR
MANAGEMENT OFFICES
CONFERENCE / WORKSHOP
Elevator
DN GALLERY - CAFE CONT.... LOUNGE SPACE?
SENSORY ROOM
Workshop - Conference Room
ROOF DECK
SCULPTURE GARDEN
Roof Deck - Sculpture Garden
Second Floor Plan
31
Bridging the Gap This building prioritizes engagement with surrounding communities, students, and people with ASD. It additionally serves as a pillar for the community that advocates connection, communication, and education. Through the construction of a gradient of autism-friendly environments, a diverse range of spaces and programmatic functions create an inclusive environment where the general population and people with ASD can interact.
32
33
Section Perspective - Residential 34
Site Perspective
West Elevation
INTEGRATED
Professor James Leech & Kristin Nelson
To design a fully integrated building coordinating structural, mechanical, and environmental systems into one cohesive building. This juxtaposition between Detroit Mercy and the Fitzgerald community creates the potential for shared and multipurpose spaces both to foster interaction and build community among constituent user groups. An architecture that protects and enhances the environment while contributing to human health and wellness. Through the implementation of sustainable environmental strategies and building practices.
Site & Building Footprint
Circulation Spaces
Fenestration and Finishes Programmatic Massing Faรงade Articulation Schematic Massing Diagram
Interior Perspective - Second Floor Residential 36
Third & Fourth Typical Floor Plan
Second Floor Plan
First Floor Plan 37
5 1
2
3
Second Floor - Market
4 Detail Section Key Notes 1) Roof Construction EPDM Membrane Rigid Insulation Dowel Laminated Timber 2) Typical Floor Construction Concrete Decking Hydrofoam Radiant Heating System Dowel Laminated Timber 3) Exterior Wall (Residential Units) Cembrit Rain Screen Cladding System Continuous Thermal Break Rigid Insulation SIP Wall Construction Interior Finish Material Gypsum Wall 4) Exterior Wall (Public Facade) Perforated Metal Panel - Solar Shade Aluminum Store Front System 5) Photovoltaic System
38
Detail Section
Section Perspective - Market
39
Interior Perspective - Bar 40
Furniture Plan
INTERIOR DESIGN
Professor Syed Ahsan
This project allowed for complete control of interior design including ceiling height, lighting, furniture, and construction of additional elements. The only stipulation was that nothing can be taken away from the provided floor plan. There was close attention to paths people would take through this ground floor. Ceiling heights were used to express a change in program and give a sense of containment in lounging areas. 41
Floor Finish Plan
42
Interior Perspective - Reception
43
Site Plan
44
West Elevation
East Elevation
LAKEVIEW HOTEL
Professor Syed Ahsan
The design problem was to create a hotel that would take full advantage of the view and follow building codes. With a site location that was centered around a vacant piece of property near an airport in Bay city Michigan. There are multiple programs that function within this hotel including a restaurant, banquet hall, and back of house hotel services. 45
First Floor Plan
46
First Floor Enlarged Plan - Entrance/Lobby
47
Exterior Perspective
48
Rendered Site Plan
GEOGRAPHICAL INTEGRATION
Professor Claudia Bernasconi
A design project about placing two duplexes on a residential site in Cincinnati. The context, communal spaces, integrating the building with the site, and addressing the view were all priorities in the design process. The intention behind this design was to create a centralized courtyard there the surrounding buildings would frame the communal space. A lifted structure would reach towards a lower embedded unit and create a interlocking relationship. The parking would overlook the site serving as the first 49 entry point and providing an uninterrupted view of the city.
Conceptual Massing Perspective
50
Exterior Perspective - Street View
Structure Detail 51
52
Unit 1 - Second Floor Plan
Unit 2 - Second Floor Plan
Unit 1 - First Floor Plan
Unit 2 - First Floor Plan
Exterior Perspective - Courtyard
53
54
2019 Summer Design Fellowship Shepley Bulfinch Competition Submission
SELECTED WORKS
- Jonathan Turner
This section is composed of sketches, renderings, and photos from an assortment of different projects I have been apart of. To display a diverse depth of skills and interests that are always being improved. 55
CANOPY -
PROVIDING LIGHTING AND ACOUSTICAL CONTROL WITHIN THE SPACE.
SPEAKER PROVIDING AUDITORY AMBIENCE SURROUNDING THE INSTILLATION.
STRUCTURAL SUPPORTS.
PERFORATED THRESHOLD ENCOURAGING INTERACTION, SENSORY STIMULATION, AND DYNAMIC SIGHT-LINES.
Experimental Instillation The intent of this installation was to design spaces for the wellness of those with Autism Spectrum Disorder in a higher education environment. Many students with ASD reported that on campus they wanted more accommodations, such as increased awareness of what ASD is, more sensory spaces on campus to recharge, and more acceptance of self-stimulatory behavior. This also correlates with the research findings that architecture can improve the attention span, behavioral temperament, and response time of those with ASD. Sensory stimulation can calm them down when factors such as acoustics, lighting, and tactile aspects are considered. This installation engages with these factors to create a space for all people to enjoy, but is specifically designed with ASD students in mind to recharge their senses. 56
INFORMATION BOARDS THE INTENT OF THE INSTILLATION
57
Stereoscopic Panorama Immersive technologies were investigated as an additional layer to this study requiring that each room include an immersive 360° rendering. This exploration allowed for aspects of spatial design and perception to be viewed through the lens of virtual reality technologies. Starting with one of the foundational aspects of virtual reality, the stereoscopic panorama grid [figure ##] structures a specific aspect ratio and layout allowing flat images to be mapped on a sphere. A variety of grid layouts allow for the creation of various environments and settings. Modern architectural modeling and rendering programs are capable of generating immersive imagery that can be viewed from any smartphone. Through immersive technologies conceptual spaces can be viewed and experienced, allowing for architects and clients to further develop and refine the built environment.
58
Phase One The first room in this sequence is staged as a controllable environment that adheres to autism-friendly design strategies. Through the use of adjustable lighting, an adaptable layout, and moveable furniture. A dynamic nature within this space creates an adaptable environment that responds to occupancy. Additionally, simple unambiguous spatial expression allows for a sense of occupant comfort and expectation within the environment. Granting occupants a sense of order and consistency as they define use and ambiance within the room.
Phase Two The second group therapy room introduces daylighting through the form of a central skylight. This allows for natural light to enter the space with minimum visual distractions and creates a dynamic uncontrollable element within the room. An accent wall with decorative acoustical paneling serves as a defining feature, grounding a directional style of organization. Although the room still includes autism-friendly elements these adjustments in form and expression shift the power of spatial definition away from the occupants.
Phase Three The third room in this series primarily features a direct connection with exterior conditions through four windows to a busy street, this creates a visual and auditory distraction from interior therapy activities. The ability for interior subdivisions within the room has been removed and replaced with a central shared workstation. Changing the room dynamic to functioning as one shared space that encourages social interaction and self-awareness/management.
59
Exterior Perspective - Rolling Garden
Vertical Studio Project - Winter UDM 2019 60
North Elevation - Enlarged
North Elevation - Enlarged
South Elevation - Enlarged 61
Exterior Perspective - Main Entry
62
Interior Perspective - Cafe over Lobby
Interior Perspective - Office
Section63 A
Jonathan Lawrence Turner Assoc. AIA (810) 614-1259
5082 Edinger Ave. Huntington Beach, California 92649
www.linkedin.com/in/JonLTurner
Education:
Skills:
University of Detroit Mercy • M.Arch - April 2020 3.79 GPA • B.Arch - April 2019 3.61 GPA Oakland Community College • A.Arch - April 2017 3.45 GPA
• AutoCAD
• DIALux
• Sketch-up
• 3Ds Max
• Rhino
• Illistrator
• Autodesk Revit
• Microsoft Office
Interests:
• Photoshop
• V-Ray
• InDesign
• Bluebeam Revu
• Lumion
• Navisworks
• Sefaira
• Bim 360
• • • •
64
JonTurner385@Gmail.com
Technical Drafter & Project Assistant
Parametric Design Building Theory Inclusive design practices Evidence-based architecture
• NCARB Record #851505
23%
Professional Experience BRION JEANNETTE ARCHITECTURE - Newport Beach, CA Intermediate Technical Drafter & Project Assistant - June 2020 - Feb. 2021 • • • • •
Gather requirements and data for potential and ongoing projects. Such as: zoning code, HOA design standards, city/HOA submittal requirements, CBC/CRC, etc..) Draw detailed and rough scale plans for structures, based upon preliminary concepts, sketches, and other provided data. Work closely with architects and project managers to prepare fully-detailed architectural drawings & respond to city comments to acquire plan approval. Coordinated with consultants to prepare necessarry documents for submittals. Coordinate with city to submit & pick up plans for plan check review. As well as perform over the counter review for construction revision submittals.
STRAUB PETTITT YASTE ARCHITECTS - Clawson, MI Architectural Intern - Apr. 2019 - Mar. 2020 • • • • • •
Contact: Rick Mann (248) 658-7777
Contacted with and discussed architectural projects with clients Prepared cost estimates for project construction Organized client meetings and prepared documents for meetings Analyzed and documented existing site and building conditions for new projects Drafted full project documentation for large scale commercial projects Coordinated with engineering consultants for the creation of mechanical, electrical, and structural documents
DETROIT MERCY FACILITIES DEPARTMENT - Detroit, MI Architectural Intern - Sept. 2017 - Apr. 2019 • • • •
Contact: Bonnie Jeannette (949) 645-5854
Contact: Rodney Warren (313) 993-1240
Met with clients and facilitated the establishment of project scope Drafted full construction documentation for renovation projects Communicated with bidders, prepared documentation for RFIs, and the selection of the contractor Supervised construction by assessing quality, completeness, and solving issues as they arose
DETROIT MERCY TEACHING ASSISTANT - Detroit, MI TA for VisCom - Aug. 2018 - Mar. 2020
Contact: Bryan Shisakly (586) 879-3223
GCI INVESTMENTS COMPANY LTD - Oakland, MI Carpenter/Handyman - Apr. 2015 Aug. 2017
Contact: Doug Otero (248) 390-1976
• • •
• • •
Taught several classes covering skills in Auto-Cad, Revit, 3ds Max, and V-ray Effectively assisted undergraduate (UG) students with understanding of material covered in class Met with UG students on a flexible schedule and provided supplemental instruction outside of class
Responsible for all tasks related to the demolition and renovation of residential housing projects Assisted in the construction of new elements such as custom casework, staircases, walls, decks, and sidewalks Individually performed instillation of furnishings and finish materials
65
66