ENGR - EXPO 2021 - Tech Session 3 (CIVIL) - Ponderosa Lift Station Replacement - Post Falls, Idaho

Page 1

2021

PONDEROSA LIFT STATION REPLACEMENT

BACKGROUND The Ponderosa lift station is located within Polites Park in Post Falls, ID. The objective of this project is to replace and

DESIGN TEAM: ALEXUS CONNOR, MICHAEL SPIERS, SAM GIBSON, ALEXIS BROOKS SPONSOR: MEGHANN KOLB, EI – T-O ENGINEERS

HYDRAULIC ANALYSIS

LIFT STATION DESIGN

A combination of the Colebrook-White formula

PLAN VIEW

and Darcy Weisbach equation was used to

decommission the existing triplex lift station for future peak

establish a function for total headloss as a

flows and increased infrastructure in the surrounding

function of volumetric flow rate.

community. This design is guided by the following design

𝑓𝑓 =

peak flows: 5-year Peak Flow : 810 GPM 20-year Peak Flow : 1757 GPM

log

0.25

4𝑄𝑄 πœ‹πœ‹πœ‹πœ‹πœ‹πœ‹

5.74 0.9

π‘˜π‘˜π‘ π‘  + 3.7𝐷𝐷

2

8𝑄𝑄2 𝑓𝑓𝑓𝑓 + οΏ½ 𝐾𝐾 β„Žπ‘“π‘“ = 2 4 π‘”π‘”πœ‹πœ‹ 𝐷𝐷 𝐷𝐷

SITE PLAN PROFILE VIEW

SYSTEM CURVE 80 70

Head (feet)

60 50 40 30 20 10

HYDROLOGIC ANALYSIS

The Rational Formula was used in order to estimate surface runoff of pre- and post-development. A swale was designed in order to account for the increased flow rate from the additional impervious surfaces added to the new site. Q=CiA

COST ANALYSIS Cost Estimate Civil

$58,000

Sanitary

$281,000

Total

$339,000

ACKNOWLEDGEMENTS Meghann Kolb, EI

Fritz R. Fiedler, Ph.D., P.E. Erik R. Coats, Ph.D., P.E.

200

400 1 Pump

600

800 1000 Flow (GPM)

2 Pumps

1200

Appropriate Pump Curve

Displayed on the graph are the system curves accounting for 5-year peak flow and 20-year peak flow along with an appropriate pump curve to satisfy both conditions.