PORTFOLIO VAN LY
Professional Work | Educational Work
RICHMOND HOTEL
RICHMOND, VA
Scope: Adaptive Reuse Size: 128,682 SF Brand: Hyatt House - Hyatt Place Key count: 209 Status: Design Development
Richmond Hotel is a dual-brand Hyatt House + Hyatt Place located at Main and 7th St downtown Richmond. The existing building is adjacent to the Monroe Ward Historic District, which imposes certain restrictions on the design, both interior and exterior. However, we also see this as an opportunity to coordinate historic elements into our design and at the same time earn tax credits. This hotel provides 209 guestroom units, including 80 extended stay Hyatt House units and 129 transient Hyatt Place rooms. Richmond Hotel also offers great amenities: a 1600 sf fitness room and 2 meeting rooms on top floor. The 18 ft high lobby space on ground floor is dedicated to public program to include an upscale bar, lounges, and games zone that is open to both hotel guests and public use. Value is added to the living experience during the guests stay via a breakfast buffet, dining lounge, and work zones within the public space.
2
3
SECTION 1
D
C
B
A
E
SECTION 2
PARAPET 156' - 0" ROOF 154' - 0" NEW WINDOW
SECTION 3
18. KING
E MAIN ST
5. KING
LEVEL 12 142' - 0"
SECTION 4
3
2
5
4
7TH STREET
5. QQ
18. KING
LEVEL 11 130' - 0"
HYATT HOUSE
5
6
LEVEL 3
STUDIO
1 BED
2
5
5
12
3
17
8
3
17
8
3
8
3
160'6- 5 3/8" 8 6
LEVEL 4
14' - 7 7/8"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
14' 6 - 7"
14' - 7"
17
5
22
LEVEL 8
17
5
22
LEVEL 9
17
5
22
LEVEL 10
17
5
22
LEVEL 11
17
5
22
20
1
21
BENCH
LEVEL 12
SHOWER
SHOWER
TOTAL
26
%
33%
37
17
46%
21%
105
26
80%
20%
NM03B
13' - 3"
15' - 11"
14' - 7"
18. KING
UP ELEV #1
ELEV #2
5. QQ
LEVEL 8 94' - 0"
STAIR #1 104 SF
ELEV #3
18. KING
LEVEL 7 82' - 0"
4. STUDIO
14. STUDIO
N
P
R
S
X
ROOM TYPE LEGEND BOH
4. STUDIO
14. STUDIO
4. STUDIO
14. STUDIO
LEVEL 5 58' - 0"
C LEVEL 4 46' - 0"
13' - 4"
G C
HH- DEN
EM30A
HH- ONE BED HH- STUDIO
4. STUDIO
14. STUDIO
4. STUDIO
11. STUDIO
B2
LEVEL 3 34' - 0"
HP- KING
HSKP 198 SF
C1
LEVEL 6 70' - 0"
OPEN TO BELOW
B1
HP- QQ PUBLIC
AIR CHASE
B
LEVEL 2 21' - 0"
13' - 4"
BIKE STORAGE 225 SF
LINEN CHUTE
E
D
211 KEYS
UP
UP
LEVEL 10 118' - 0"
14' - 6 1/2" 18. KING
5. QQ
Stair 2 53 SF
HYATT HOUSE
3' - 8"
11.1 12
18. KING
LEVEL 9 106' - 0"
NM03A
STAIR 4 143 SF
20' - 0"
11
5. QQ
NM01 HM30B DN STAIR # X 82 SF
10
5. QQ
NEW STAIR TO 2ND FLOOR
STORAGE 392 SF
WOMEN
LOCKERS
HM08
9
UP
100 % 131 KEYS
LOCKERS
MEN
8
17
100 % 80 KEYS
WORK ROOM 574 SF
17' - 4"
BREAK ROOM 629 SF
17
6
LEVEL 6
D
KING
LEVEL 7
LEVEL 5
WALL OF ADJACENT BUILDING
7
DEN
LEVEL 2
13' - 9 7/8"
4
ADJACENT BUILDING
13' - 4"
3
TOTAL
7' - 3 3/16"
2 STOP AT MEZZANINE LEVEL
HYATT PLACE
BENCH
1
HYATT PLACE
E
66' - 3 1/4"
1
HYATT PLACE
E
F
5
4
HYATT HOUSE
2
Professional Work |Educational Work
1
B
SERVICE ELEVATOR
MEZZANINE LEVEL 11' - 0"
20' - 0"
OPEN TO BELOW
A1
ADJACENT BUILDING BAR
ADJACENT BUILDING
12' - 5 3/8"
RECEPTION
LEVEL 1 0' - 0"
HSKP STORAGE 253 SF BOH
LEVEL B1 CELLAR -12' - 0"
LOW HEAD & SILL WINDOWS 4' - 7" HEAD AND 2' - 10" SILL
1
REF. A1/ A0301
2
3
4
1 1
5
Building Section 0
5
10
20
30 FT 3
2
6
1' - 3"
7
8
ADJACENT BUILDING
2
REF. A1/ A0121
NEW SECTION 1 1/8" = 1'-0"
9
10
11
11.1 12
14' - 7"
14' - 7"
14' - 7"
1' - 11"
14' - 7"
14' - 7"
13' - 3"
15' - 11"
14' - 7"
14' - 6 1/2" 1' - 4"
14' - 7"
5
4
160' - 5 3/8" 14' - 7 7/8"
WALL OF ADJACENT BUILDING
H
UP
WD
D
ELEV #1
LUGGAGE 84 SF
FOOD PREP
DN E100 HISTORIC MAIL CHUTE
CWO
G.M, SALE & COMPUTER 422 SF
48
ELEVATOR LOBBY 599 SF
GUEST KITCHEN 520 SF
E102
SELF CHECK-IN
C 3' - 0"
G
N
P
R
S
VESTIBULE
X
RELOCATED DOORS OUTDOOR COMMONS 576 SF
REPLACE GLAZED DOORS BY FIXED WINDOW
TWO-STORY LOBBY/ LOUNGE/ BAR 4742 SF
LINEN CHUTE
J
CL
B A1
J
20' - 0"
B2
B1
HSKP STOR.
SERVICE ELEVATOR 63 SF
69' - 4 1/4"
E105
STORAGE 180 SF
13' - 4"
E106
66' - 3 1/4"
Corridor 59 SF
20' - 0"
ALLEY BELOW
ATM
H MARKET
1848
13' - 4"
PARKING GARAGE
UP N107
C1
EGRESS ONLY
1848
DN
D
SIDEWALK ELEV. -0'-10"+/-
12' - 1 1/8"
2460
WOMEN'S RESTROOM 317 SF
1' - 6"
1848
1848
MEN'S RESTROOM 268 SF
STORAGE
18
ELEV #3
BELL CART
2460
D
ELEV #2
13' - 4"
BOH KITCHEN 827 SF
2436
CWI
2436
NEW STAIR
17' - 4"
E
C
13' - 9 7/8"
H
C
VALET STATION: PARKING TO BE PROVIDED
12' - 5 3/8"
GATHERING ROOM 388 SF
LEVEL 1 - PROPOSED PLAN 1/8" = 1'-0"
Level 1- Public Space
1
2
1' - 9"
A 9.1
163' - 7 3/8"
A1
NEW SECTION 2 1/8" = 1'-0"
E MAIN STREET
LEVEL 1B- MEZZANINE LEVEL PROPOSED PLAN 1/8" = 1'-0"
9.1
A
2/13/2020 9:43:05 PM
D1
A
WALLED OFF
REF. A1/ A0301
7TH STREET
0
3
4
3
5
10
20
30 FT
5
D
Professional Work | Educational Work
Option 1- Level 7 To 12 (Hyatt Place)
1
3
2
4
5
Option 1- Level 3 To 6 (Hyatt House) F
F
E
E
D
D
Option 1- Plumbing Stack
D1
LEVEL 6 - PROPOSED PLAN 1/8" = 1'-0"
REF. 1/ A0301
4
E
A
E
F
D
C
ROOF TOPELEVATOR MACHINE ROOM 304' - 6"
B
A
N2
ROOFPARAPET - 0" 292' - 6" 156' ROOF 154' - 0"
E MAIN ST
FITNESS 1207
HSKP
12' - 0"
KING 1216
NEW WINDOW 18. KING
5. KING
LEVEL 12 280' - 6"LEVEL 12 142' - 0"
17 17
5. QQ
18. KING
LEVEL 10 118' - 0"
17
5. QQ
LEVEL 9 106' - 0"
LEVEL 8 94' - 0"
5. QQ
12' - 0"
STUDIO 709
18. KING
HSKP
LEVEL 7 82' - 0"
0%
LEVEL 8 232' - 6" LEVEL 8 94' - 0"
D KING 717
6
211 KEYS
STRUCTURAL ENGINEER
MEP ENGINEER
CIVIL ENGINEER
INTERIOR DESIGNER
---
D
LEVEL 7 220' - 6" LEVEL 7 82' - 0"
14. KING
12' - 0"
14. STUDIO
4. STUDIO
14. STUDIO
4. STUDIO
14. STUDIO
4. STUDIO
14. STUDIO
4. STUDIO
11. STUDIO
STUDIO 609
LEVEL 6 70' - 0"
HSKP
LEGEND
STUDIO 509
C
KING 417
STUDIO 409
KING 317
STUDIO 309
LEVEL 3 172' - 6" LEVEL 3 34' - 0"
11. STUDIO
HSKP
LEVEL 3 34' - 0"
ADA KING 206 8. ONE BEDROOM
TRANSFER STAIR FROM 2F TO 3F
LEVEL 2 21' - 0"
LEVEL 2 LEVEL 2 157' - 6" 21' - 0"
MEN'S RESTROOM
TWO-STORY LOBBY/ LOUNGE/ BAR
ADJACENT ADJACENT BUILDING BUILDING BAR
MEZZANINE MEZZANINE LEVEL LEVEL 147' - 6" 11' - 0"
MEN'S RESTROOM
LEVEL 1 LEVEL 1 0' - 0" 136' - 6"
EXISTING ENGINE ROOM JANITOR 399
QQ B04
REF. A1/ A0121
2
1
3
2
3
2
3
4
5
4
6
2/23/2020 12:37:36 AM
Option 1- Section
2
NEW SECTION 2 1/8" = 1'-0"
1
7
5
9' - 0"
Option 1 2- Section NEW SECTION 1 4 REF. 1/8" = 1'-0" A1/ A0121
8
6
2
10
11
11.1 12
19022 10.04.2019
A
2
5
REF. D1/ A0209
9
BASE MEZZ 126' - 0"
PROJECT NO.: SCALE: DATE: REVISIONS :
LEVEL B1a CELLAR 122' - 6"
LEVEL LEVEL B2SUB B2- SUB BASEMENT BASEMENT 115' - 6" -25' - 0"
A
NEW SECTION 1 1/8" = 1'-0"
NEW BUILDING SECTIONS
B1 LEVEL B1LEVEL CELLAR CELLAR 124' - 6" -12' - 0"
9' - 0"
LEVEL B1 CELLAR -12' - 0"
LS
SCHEMATIC DESIGN
12' - 0"
LEVEL 1 0' - 0"
BOH
1
ADJACENT BUILDING
11' - 0"
ADJACENT BUILDING
NEW STAIR FROM MEZZANINE TO 2F B
10' - 0"
B MEZZANINE LEVEL 11' - 0"
3
NEW 6 SEC 1/8" = 1'-
A0421
7
4
160' - 5 3/8" 14' - 7 7/8"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
13' - 3"
15' - 11"
14' - 7"
14' - 6 1/2"
HISTORIC MAIL CHUTE
UP
17' - 4"
KING 314
KING 315
KING 316
KING 317
KING 318
T
KING 319
U
13' - 9 7/8"
E
DEN 301
V E300 E326
JC 17 SF J
KING 313 KING 320
STORAGE. 324 73 SF
ELECTRICAL 327 73 SF
C
DEN 302
ICE 325 52 SF
E330 E302
B1 J
QQ 310
J
3' - 2 7/16"
STUDIO 309
QQ 308 356 SF
J
HSKP 329 98 SF
J
? ?
5' - 8 5/8"
DEN 307 ONE BED 312
QQ 305
STUDIO 306
KING 304
B
ROOM A1
STUDIO 311
9.1
D1
LEVEL 3 - PROPOSED PLAN 1/8" = 1'-0"
REF. A1/ A0301
5
0
5
10
20
30 FT
HH- DE
HH- ST
HP- KIN
A
Option 2- Typical Guestroom Level
BOH
HH- ON
12' - 5 3/8"
20' - 0"
STUDIO 303
B2
J
20' - 0"
DN
SERVICE ELEVATOR
D C1
2' - 10 1/2"
J
1
C LEVEL 4 184' - 6" LEVEL 4 46' - 0"
11. STUDIO
HSKP
KING 211
RECEPTION
LEVEL 5 196' - 6" LEVEL 5 58' - 0"
11. STUDIO
HSKP
LEVEL 5 58' - 0"
HYATT HOUSE
HYATT HOUSE
KING 517
LEVEL 4 46' - 0"
LEVEL 6 208' - 6" LEVEL 6 70' - 0"
11. STUDIO
© Copyright 2018. Peter Fillat Architects, Inc. All rights reserved. Peter Fillat Architects, Inc. is doing business as FILLAT + Architecture.
KING 617 4. STUDIO
13' - 4"
S
14. KING
13' - 4"
21
STUDIO 809 HSKP
18. KING
66' - 3 1/4"
22
1
KING 817 5. QQ
LEVEL 9 244' - 6" LEVEL 9 106' - 0"
14. KING
13' - 4"
5
STUDIO 909 HSKP
12' - 0"
22
KING 917
LEVEL 10 256' - 6"LEVEL 10 118' - 0"
12' - 0"
22
5
14. KING
12' - 0"
22
5
STUDIO 1009 HSKP
1432 K St. NW, SUITE 1100 | WASHINGTON, DC | 20005 Ph: (202) 373-1535 | PFARC.COM
E
15' - 0"
5
KING 1017
18. KING
17 22
LEVEL 11 268' - 6"LEVEL 11 130' - 0"
12' - 0"
12
14. KING
E
12' - 0"
TOTAL
LEVEL 11 130' - 0"
12' - 0"
CE
STUDIO 1109 HSKP
18. KING
HYATT PLACE
HYATT PLACE
5. QQ
12' - 0"
KING 1117
5
NEW WINDOW
14. KING
LEVEL 12 142' - 0"
SECTION 4
Q
PARAPET 294' - 6"
PARAPET 156' - 0" ROOF 154' - 0"
SECTION 3
F
629 E MAIN ST, RICHMOND, VA 23219
B
A
RICHMOND HOTEL
C
B
Professional Work |Educational Work
D
C
12' - 0"
E
D
HP- QQ
PUBLIC
Professional Work | Educational Work 1
F
3
2
5
4
South Elevation
9. KING
3. KING
2. KING
5. KING
4. KING
6. KING
7. KING
1. KING
8. QQ
E
HSKP
10. KING
11. KING
12. KING 20. KING
19. KING
18. KING
17. KING
D
LEVEL 12 - PROPOSED PLAN 1/8" = 1'-0"
C
15. KING
14. KING 13. KING
21. KING
Level 12- Iteration 1 D1
16. KING
REF. 1/ A0301
6
3
2
1
2
3
4
5
5
4
6
7
8
Professional Work |Educational Work
1
9
10
11
11.1
12
ASSESS & REPAIR AS NEEDED
cc BOILER
Photos: Donald Friedman
MECHANICAL 340 SF
E
D
ELEVATOR MACHINE 344 SF
DN
W
6
C1
ELECTRICAL 289 SF B
W
C dd
K
B2
TYP.
bb
B1 B bb
EXISTING SKYLIGHTS
LINEN CHUTE
A1
A 9.1
D1
ROOF- PROPOSED PLAN 1/8" = 1'-0"
1
Metropolitan floor system is a floor assembly used in the 1890s- early 1900s REF. amidst the rising demand for an inexpensive fire-rated and structurally reliable A1/ A0301 floor system in New York and Chicago. The system comprises of catenary wires embedded in a mixture of plaster-of-paris (75% by weight) and wood chips (25% by weight). These cables consist of 2 iron wires twisted together, secured to the top flange4of the beam 5 and are6placed 1" -7 1.5" apart.8 9 10 11 0
2
3
5
10
20
30 FT
11.1 12
160' - 5 3/8" 14' - 7 7/8"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
14' - 7"
13' - 3"
15' - 11"
14' - 7"
14' - 6 1/2"
NEW WINDOWS
C1
KING 1215
KING 1216
KING 1217
KING 1218
E1221
KING 1219
STORAGE 74 SF
ELECTRICAL 1225
C 13' - 4"
E1230
20' - 0"
3' x 3' SKYLIGHTS ABOVE
20' - 0"
ICE 52 SF
PRE-FUNCTION 684 SF
B2
B1
SECURITY DOOR EXIT
MEETING ROOM 2 471 SF
dd
TYP.
3' - 6"
FITNESS 1613 SF
HSKP
W 176 SF
10' - 8 11/16"
MEETING ROOM 3 536 SF
MEETING ROOM STORAGE 232 SF
STORAGE 147 SF
12' - 5 3/8"
3' - 0"
20' - 0"
B
13' - 4"
SCULPTURE
6' - 0"
M 177 SF
20' - 0"
7' - 6 7/8"
SERVICE ELEVATOR
66' - 3 1/4"
KING 1214
J
KING 1213
13' - 4"
17' - 4"
E1226
KING 1212
D
ELEVATOR LOBBY 419
E1200
17' - 4"
W
13' - 9 7/8"
15' - 3 1/4"
HOSPITALITY SUITE 1201 458 SF
HISTORIC MAIL CHUTE
8' - 11 1/4"
E 7' - 4"
A1
A 9.1 3' X 3' SKYLIGHT ABOVE
3' X 3' SKYLIGHT ABOVE
Level 12- Iteration 2 A1
REF. A1/ A0301
LEVEL 12 - PROPOSED PLAN 1/8" = 1'-0"
0
1
2
3
5
4
7
10
20
30 FT
5
6
A1 A2
8 HH- ONE BED
Professional Work | Educational Work
A4 A5
9 Professional Work |Educational Work
1
3
2
1
2
3
4
5
6 ADJACENT BUILDING
F 14' - 7 7/8"
14' - 7"
14' - 7"
14' - 7"
5
4
7
8
9
160' - 5 3/8"
14' - 7"
10
11
11.1
12
A1
14' - 7"
14' - 7"
A0401
13' - 3"
15' - 11"
14' - 7"
14' - 6 1/2"
WALL OF ADJACENT BUILDING
E DN UP
6' - 5"
HB01 HB02
DN
PUMPS
(OPEN TO BELOW)
C1
HB03
F.EL 122' - 6" F.EL 124' - 6"
HB09
13' - 4"
17' - 4"
EB117B
HB04
HB10
SW GEAR
DN
MECHANICAL 104
C
5' - 0"
F.EL 122' - 6"
RAMP
DN
F.EL 124' - 6"
MECH.
F.EL 122' - 6"
B1
DN
VAULT
UP
F.EL 119' - 0"
MEN
WOMEN
B
HB05
FORMER RETAIL
A1
20' - 0"
UP
F.EL 126' - 0"
SPRINKLER CONTROL VALVE
ENGINEER OFFICE
SPRINKLER CONTROL VALVE
D
LIFT
EXERCISE STORAGE
A SPRINKLER CONTROL VALVE ROOM
SIDE WALK ELEV -10'-6"+/-
ELEV -17'-0"+/-
D1 Cellar - Existing Plan LEVEL 0B - CELLAR - EXISTING PLAN 1/8" = 1'-0"
1
B2
13' - 4"
UP
A0402 B090
SERVICE ELEVATOR
ELECTRICAL
HB06
STEEP RAMP
12' - 5 3/8"
1
13' - 4"
DN
MAIL ROOM
D
3' - 10" 1' - 6"
UP
DN
FIRE ESCAPE ABOVE
20' - 0" ALLEY
PARKING GARAGE
E
EXISTING BOILER ROOM BELOW (TWO STORY DEEP)
F.EL 123' - 6"
B090
0' - 6" 5' - 0 1/2"
ENGINE ROOM
F.EL 115' - 6"
WATER HEATER ABOVE
FIRE CONTROL ROOM
2
ELEVATOR LOBBY F.EL 124' - 6"
2
REF. A1/ A0301
3
9.1
5
4
7TH STREET
0
5
10
20
30 FT
F
1
C
2
3
4
5
69' - 1 3/8"
F.EL 119' - 4"+/- V.I.F
2
14' - 7 7/8"
3
14' - 7"
4
14' - 7"
5
14' - 7"
6
PLAN ROOM ABOVE
EXISTING BOILER ROOM (TWO-STORY HIGH) 822 SF
WATER HEATER ABOVE
9
10
11
11.1 12 LEVEL 1 136' - 6" LEVEL B1 CELLAR 124' - 6"
D
LEVEL B1a CELLAR 122' - 6"
17' - 4"
25' - 9 1/2"
32' - 0 1/2"
7' - 0"
2 B090
ALLEY
E
NEW PLATFORM
UP
28' - 1 1/2"
UP FL. EL. 123'-6"
8
E
F.EL 115' - 6" +/- V.I.F
DN HBB02
7
8' - 11 1/4"
1
LEVEL B2- SUB BASEMENT 115' - 6"
C
B
2 Cellar - Existing Section 2
REF. A1/ A0101
EXISTING SECTION B Copy 2 1/8" = 1'-0"
1
2
3
4
5
6
7
8
9
10
11
11.1 12
D
VAULT 87
MAIL ROOM 89
FORMER RETAIL 61
FORMER RETAIL 61
EXERCISE 54
MEN 55
WOMEN 56
ELECTRICAL 91
9' - 0"
A
12' - 0"
LEVEL 1 136' - 6"
A1
LEVEL 0A- SUB BASEMENT - EXISTING PLAN 1/8" = 1'-0"
1
3
4
C
1 Cellar - Existing Section 1 EXISTING SECTION B Copy 1 1/8" = 1'-0"
LEVEL B1a CELLAR 122' - 6" LEVEL B2- SUB BASEMENT 115' - 6"
REF. A1/ A0301
2
LEVEL B1 CELLAR 124' - 6"
REF. D1/ A0101
10
5
E MAIN STREET
BASEMENT MEZZANINE 102
13' - 9 7/8"
RAMP BELOW (SUB-BASEMENT)
66' - 3 1/4"
8' - 11 1/4"
F.EL 126' - 0"
DN
3
2
5
4
A0302
6
A1
1
2
3
D1 A0612
4
5
6
7
8
9
10
11
11.1 12
163' - 5 3/8"
14' - 7 7/8"
14' - 7"
A1
14' - 7"
14' - 7"
14' - 7"
D1 A0613
14' - 7"
13' - 3"
15' - 11"
14' - 7"
C2 A0613
14' - 6 1/2"
H
A0706
T
D
LAUNDRY 909 SF
E.L. = 123' - 6"
E.L. = 121' - 3"
E.L. = 122' - 6"
NEW RAMP
DN
HB10
A0720
SECURITY STATION 105 SF
EB10
3' - 7"
G
N
P
R
S
F.EL 122' - 6"
X
DN
D
NEW RAMP 14' - 8"
10' - 2"
UP
E 3' - 7"
ELECTRIC SERVICE ROOM (1922) 388 SF
B
TYP.
17' - 4 13/16"
C
F.EL 122' - 6"
F.EL 124' - 6"
DN
11' - 0"
NEW RAMP
SLOPE = 1:12
EL. 124'-6"
DN
F.EL 123' - 5"
F.EL 124' - 6"
NEW RAMP
13' - 0"
NEW ELECTRICAL ROOM 477 SF
DN
SLOPE = 1:12
5' - 6 1/2"
10' - 0"
E.L. = 120' - 0"
QQ B04
ONE BED B05
QQ B03
QQ B02
EB110 16' - 9 3/8"
ONE BED B01
STORAGE 4 64 SF
FP
5' - 9"
A ADA ENTRY FLUSH
12' - 4 3/4"
2' - 0"
ELEV 117'- 4" +/-
LOADING/ EMPLOYEE ENTRACE
D1 Cellar - Proposed Plan
REF. A1/ A0301
LEVEL 0B - CELLAR - PROPOSED PLAN 7 1/8" = 1'-0"
6
9.1
SIDEWALK ELEV -10'-6"+/-
D1 D2 A0537
D1 D3 A0518
6' - 0"
12' - 0"
A1 A0301
F.EL 126' - 0"
FIRE CONTROL ROOM 165 SF
1 A0422
A1
F.EL 124' - 6" 20' - 0"
NEW RAMP
UP
NEW LIFT
DN
12' - 0" SLOPE = 1:12
B
9' - 4 1/2"
5' - 0"
Z
E.L. = 119' - 0"
B2
B1
F.EL 124' - 6"
gg NEW CUT INTO FLOOR
4' - 5 1/4"
SERVICE ELEVATOR
PORTICO ABOVE
F.EL 124' - 6"
2' - 9"
E.L. = 119' - 0"
UP
14' - 8" SLOPE = 1:12
DN
SORT DIRTY
2
SHELVES
E.L. = 122' - 6"
24' - 2" SLOPE = 1: 9.7
T
PURCHASING/ HSKP OFFICE 153 SF
JANITOR 47 SF
C1
F.EL 124' - 6"
F.EL 122' - 6"
HB09
E.L. = 123' - 6"
NB100
69' - 4 1/4"
UP
SLOPE = 1: 10.2
ALLEY
E.L. = 120' - 0"
V
8' - 2 7/8"
10' - 0" SLOPE = 1:10
2 A0701
D
USE NEW DOOR
cc F
HB01
20' - 0"
1 A0423
E.L. = 123' - 6"
UP
E.L. = 123' - 6"
4' - 0"
ee
RELOCATED BEAM ABOVE
UP
DN
gg
E
V
STAIR 4 UP 101 SF
ELEVATOR LOBBY RESWING DOESN'T 126 SF WORK; MUST
EXISTING MEP ROOM
LINEN STORAGE 205 SF
NEW PLATFORM
FIRE PUMP 149 SF
EXISTING BEAM ABOVE TO BE RELOCATED
V
W
SLOPE = 1:12
NEW BEAM ABOVE RUN PERPENDICULAR
DN
ELEV #3
3' - 4"
4' - 0"
EMPLOYEE RESTROOMS 215 SF
5' - 0"
UP
F.EL 123' - 6"
ELEV #2
E MAIN STREET
STORAGE
W
ELEV #1
EXISTING MEZZANINE
NEW STAIR
EXISTING BEAM ABOVE TO BE CUT
T
DN
8' - 11 1/4"
F.EL 126' - 0"+/- V.I.F
7' - 9"
EXISTING RAMP BELOW (SUB BASEMENT)
17' - 4"
F.EL 115' - 6"
DN
A4 A0706
14' - 7"
D3 A0612
WALL OF ADJACENT BUILDING
4' - 10 1/16"
F.EL 119' - 4"+/-
1
7TH STREET
ELEV -6'-0" +/D3 A0517
---
D1 A0517
2
A1
A0421
A0421
A0303
0
5
10
20
30 FT
A0302 A1
F
1
2
3
4
5
69' - 7 3/8" 1' - 4"
14' - 7 7/8"
14' - 7"
F.EL 119' - 4"
14' - 7"
14' - 7"
F.EL 115' - 6"
1
1
4
PLAN ROOM
A0707
F
1432 K St. NW, SUITE 1100 | WASHINGTON, DC | 20005 ABOVE Ph: (202) 373-1535 | PFARC.COM
3
4
D
STRUCTURAL ENGINEER
BOILERS AND WALLS REMOVED HENRY
BOTTLE STORAGE
F.EL 115' - 6"
E
RECOMMENDED GREASE TRAPS- ABOVE GROUND
ADAMS, LLC. 600 BALTIMORE AVE ROOM TOWSON, MD 21204 475 SF (410) 296-6500
CAN WASH
BALZER & ASSOCIATES, INC. 15871 CITY VIEW DR, SUITE 200 MIDLOTHIAN, VA 23113 (804) 794-0571
UP
DN
MEP ENGINEER
W
D
CIVIL ENGINEER
NEW PLATFORM
INTERIOR DESIGNER
RD JONES + ASSOCIATES, INC. 8401 CONNECTICUT AVE, SUITE 900 CHEVY CHASE, MD 20815 (240) 330-1860
FIRE PUMP 324
C
E.L. = 123' - 6"
E.L. = 123' - 6"
E.L. = 123' - 6"
gg
LINEN STORAGE 205 SF
LAUNDRY 909 SF
E.L. = 123' - 6" UP
GAR HOLDING
WATER HEATER ABOVE
D
17' - 4"
BALZER & ASSOCIATES, INC. UP 200 15871 CITY VIEW DR, SUITE MIDLOTHIAN, VA 23113 (804) 794-0571
UP
2
5 F.EL 126' - 0"
8' - 11 1/4"
EXISTING RAMP
2
E
RECYCLING
DN
2
3
2
NEW FIRE RATED DOOR AND WALL
ALLEY
10' - 0" SLOPE = 1:10
C
D
A1 1
LEVEL 0B1- SUB BASEMENT PROPOSED PLAN 1/8" = 1'-0"
REF. A1/ A0301
2 C
C
B
E.L. = 120' - 0"
24' - 2"
UP
10' - 2"
E.L. = 121' - 3"
PURCHASING/ HSKP OFFICE 422
E.L. = 122' - 6"
SLOPE = 1: 9.7
SLOPE = 1: 10.2
14' - 8"
E.L. = 122' - 6"
BOH CORRIDOR 398
DN
SLOPE = 1:12
DN
SORT DIRTY
14' - 8"
UP
UP
E.L. = 119' - 0"
SLOPE = 1:12
629 E MAIN ST, RICHMOND, VA 23219
D
RICHMOND HOTEL
E
© Copyright 2018. Peter Fillat Architects, Inc. All rights reserved. Peter Fillat Architects, Inc. is doing business as FILLAT + Architecture.
PARKING GARAGE
301 A3
1
UP
B ONE BED B05
E.L. = 119' - 0"
12' - 0"
DN
E.L. = 120' - 0"
D3
SLOPE = 1:12
2
FIRE CONTROL ROOM 325
3
4
LEVEL 0B - CELLARBOH-LAUNDRY-FURNITURE 1/4" = 1'-0"
D1 Cellar - BOH Laundry REF. D1/ A0201
11
LEVEL 0B BOH-LAUN 1/4" = 1'-0
5
6
Phone: (561)- 516 1684
PERMIT SET :: 10.17.2019
D
C
Professional Work | Educational Work
E
B
10/16/2019 11:11:42 AM
A
1
2
3
4
5
RESIDENCE INN ROOF TOP WASHINGTON D.C. Level 10 - Scope of Work
Scope: Adaptive Reuse Size: 128,682 SF Brand: Hyatt House - Hyatt Place Key count: 209 Status: Construction Permit
Roof Deck Level Scope of Work
12
6
7
Professional Work |Educational Work
Roof Deck Level- Life Safety Plan
Level 10 - Life Safety Plan
13
1
3
2
4
5
6
7
C
REMOVE POOL DECK SURFACE, ROOF TAPERED INSULATION, AND MEMBRANE
EXISTING ROOF SURFACE TO REMAIN
REMOVE POOL DECK SURFACE, ROOF TAPERED INSULATION, AND MEMBRANE
F
F EXISTING FLOOR SLAB TO REMAIN
B EXISTING FLOOR SLAB TO REMAIN
ROOF TERRACE 97' - 3"
EXISTING CONCRETE BEAMS
EXISTING CONCRETE BEAMS
REMOVE POOL BASIN AND STRUCTURE BELOW. SEE STRUCTURAL DRAWINGS.
1432 K St
KLINE EN 9240-A MO MANASSA (703) 331-1
E
E
CS CONSU 1300 PICC ROCKVILL (301) 977-7
N/A
BY OWNE
REMOVE ALL CURBS
LEVEL 10 87' - 1"
D
D
21' - 8"
Building Section 1 - Demolition REF. A1/ A106
Building Section 1- Demolition 3/4" = 1'-0"
4
2
1
5' - 0"
INFILL PORTION OF WALL OPENING AFTER REMOVING DOOR
REMOVE EXISTING DOUBLE DOOR
C
REMOVE ALL CURBS AND RAILING
REMOVE ALL RAILING
REMOVE POOL DECK SURFACE, ROOF TAPERED INSULATION AND MEMBRANE
C
EXISTING CONCRETE BEAMS
REMOVE POOL DECK SURFACE, ROOF TAPERED INSULATION, AND MEMBRANE
EXISTING FLOOR SLAB TO REMAIN
EXISTING FLOOR SLAB TO REMAIN
EXISTING ROOF SURFACE BEYOND TO REMAIN ROOF TERRACE 97' - 3"
EXISTING CONCRETE BEAMS
B
© Copyright 2018. Peter Fillat Architects, Inc. All rights reserved. Peter Fillat Architects, Inc. is doing business as FILLAT + Architecture.
D1
B
REMOVE POOL BASIN AND STRUCTURE BELOW. SEE STRUCTURAL DRAWINGS.
BUILD
PROJECT SCALE: DATE: REVISION
SCHEMATIC DE
A
A
10/16/2019 11:12:48 AM
REMOVE ALL CURBS
A1 1
LEVEL 10 87' - 1"
Building Section 2 - Demolition REF. A1/ A106
Building Section 2- Demolition 3/4" = 1'-0"
2
DESIGN DEVEL
REMOVE ALL CURBS
3
4
14
5
6
7
A
15 Professional Work |Educational Work
1
2
F
3
C
NEW TEMPERED GLASS RAILING
5
4
HRA WATERPROOFING
6
7
NEW COMPOSITE DECK. SEE STRUCTURAL DRAWING
E6 A701
NEW ROOF RIGID INSULATION R-30
NEW INTERIOR FLOOR TO MATCH WITH NEW ROOF SURFACE
NEW BEAM BEYOND. SEE STRUCTURAL DRAWING
NEW DECK SURFACE. 24"x 24" BISON WOOD TILE ON BISON ADJUSTABLE PEDESTALS
F
B ROOF TERRACE 97' - 3"
NEW CURB NEW 2x4 CEILING JOISTS @ 24" O.C.
LIVING
2' - 8"
7' - 11"
1' - 3 1/2"
KITCHEN
MEP
1' - 0"
E
CS CONSULTING ENGINEERS, INC. 1300 PICCARD DR, SUITE 104 ROCKVILLE, MD 20850 (301) 977-7644
CIVI
N/A
2' - 6"
INTERIOR
BY OWNER
B1 A901
Sim
LEVEL 10 87' - 1"
D
D
21' - 8"
C
Building Section 1 - New Construction
Building Section 1- New Construction 3/4" = 1'-0"
4
REF. B1/ A107
2
NEW DOOR WITH SIDELIGHTS BEYOND
C
1 NEW TEMPERED GLASS RAILING
NEW DECK SURFACE. 24"x 24" WOOD TILE ON ADJUSTABLE PEDESTALS EXISTING CONCRETE BEAM
NEW ROOF RIGID INSULATION R-30
HRA WATERPROOF
NEW CURB
NEW COMPOSITE ROOF DECK. SEE STRUCTURAL DRAWINGS
EXISTING FLOOR SLAB
EXISTING CONCRETE BEAM
NEW ROOF SURFACE
EXISTING FLOOR SLAB
0' - 7"
NEW I BEAMS- SEE STRUCTURAL DRAWINGS
ROOF TERRACE 97' - 3"
B
A
PERMIT SET
PHASES
BUILDING SECTIO NEW CONSTRUCT
NEW CONSTRUCTION
7' - 6"
TO MATCH OTHER ROOMS ON LEVEL 10. TYPICAL.
7' - 11"
B
KITCHEN
10/16/2019 11:12:55 AM
© Copyright 2018. Peter Fillat Architects, Inc. All rights reserved. Peter Fillat Architects, Inc. is doing business as FILLAT + Architecture.
D2
801 NEW HAMPSHIRE AVENUE NW, WASHINGTON D.C., 20037
1' - 0"
TO MATCH OTHER ROOMS ON LEVEL 10. TYPICAL.
DRESSING AREA
E6 A601
6' - 11 1/4"
7' - 11"
7' - 1"
BATHROOM
TO MATCH OTHER ROOMS ON LEVEL 10. TYPICAL.
NEW GWB CEILING
E
KLINE ENGINEERING & CONSULTING 9240-A MOSBY ST., MANASSAS, VA 20110 (703) 331-1284
NEW GWB CEILING
TO MATCH OTHER ROOMS ON LEVEL 10. TYPICAL.
NEW 2x4 CEILING JOISTS @ 24" O.C.
1432 K St. NW, SUITE 1100 | WASHINGTON, DC | Ph: (202) 373-1535 | PFARC.COM
STRUCTURA
NEW GWB CEILING
TO MATCH OTHER ROOMS ON LEVEL 10. TYPICAL.
B1 A901
NEW 2x4 CEILING JOISTS @ 24" O.C.
RESIDENCE INN ROOFTOP FOGGY BOTTOM
NEW 2x4 CEILING JOISTS @ 24" O.C.
A3 A701
4' - 0"
ROOF TERRACE 97' - 3"
EXISTING TO REMAIN
PROJECT NO.: SCALE: DATE: REVISIONS:
LIVING A
19015
10.17.20
SCHEMATIC DESIGN
07.15.2019
DESIGN DEVELOPMENT
08.17.2019
LEVEL 10 87' - 1"
A2 1
2
Building Section 2 - New Construction
Building Section 2- New Construction 3/4" = 1'-0"
REF. B1/ A107
3
4
16
5
6
7
A402
17 Professional Work |Educational Work
Professional Work | Educational Work
MOXY HOTEL WASHINGTON D.C. Scope: Full Architectural Size: 74,000 SF Key count: 200 Status: Completed Nov 2018 Role: Award Presentation Drawings
Moxy DC’s iconic glass and steel facade compliments the historic fabric of K street.
Photo: FILLAT+ Architecture ARCHITECT
FILLAT+ Architecture DESIGN LEAD
Peter Fillat III, AIA, LEED AP
BRAND Moxy by Marriott International
18
CONTRACTOR
MEP Metropolitan Engineering | Shapiro - O’Brien
Professional Work |Educational Work
Site Plan and Roof
Roof Plan & Site Plan
.
.
.
.
.
. .
.
.
.
.
.
.
.
.
.
HSKP
.
.
.
. .
.
.
.
HSKP
.
.
.
. .
.
.
.
.
.
GREEN ROOF
.
.
.
.
. .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
GREEN ROOF
0
30 FT
.
.
.
.
.
.
20
30 FT
LEVEL 6 - TYPICAL TOWER GUESTROOM LEVELS
.
.
. .
10
.
.
.
LEVEL 3
5
.
20
.
10
.
5
.
0
1432 K ST NW | SUITE 1100 | WASHINGTON, DC 20005 | 202. 373.1535 | FILL AT.COM WASHINGTON | BALTIMORE | NEW YORK | SAN DIEGO 11TH & K HOTEL 13018
THIRD FLOOR & TYPICAL GUESTROOM LEVEL
0
5
10
20
30 FT
Level LEVEL33
11TH & K HOTEL 13018
SCALE:
1/16" = 1'-0"
DATE:
06.22.2018
0
5
10
20
30 FT
Level TypicalTOWER Tower LEVEL6 6 --TYPICAL GUESTROOM LEVELS Guestroom Level THIRD FLOOR & TYPICAL GUESTROOM LEVEL
19
SCALE:
1/16" = 1'-0"
DATE:
06.22.2018
Professional Work | Educational Work
The building façade is truly unique in the District and that, in addition to its prime location, has made it a natural draw.
Photo: FILLAT+ Architecture
The interior of the lobby space opens in its entirety to the street with vertical bi-fold doors which create an expansive indoor outdoor semi private urban space. The bar radiates out into a small market, a comfortable lounge, and a large outdoor terrace filled with games and places to gather. The space in front of the historic structure becomes a recreational garden sidewalk cafĂŠ space. These new activations significantly improve the K street urban space.
FILLAT + A R C H I T E C T U R E
1432 K ST NW | SUITE 1100 | WASHINGTON, DC 20005 | 202. 373.1535 | FILL AT.COM WASHINGTON | BALTIMORE | NEW YORK | SAN DIEGO
North - South Section
20
Professional Work |Educational Work
BALLPARK HOTEL WASHINGTON D.C. Status: On the board Site: Navy Yard District
21
DES MOINES FEDERAL COURTHOUSE DES MOINES, IA Roles: Revit modeling & rendering. Collaborators: Nathan McKewon (Revit modeling & diagrams), Deep Chaniara (Photoshop & section drawing).
A scheme that fuses a federal courthouse with the buzz of commercial activity and dense residential presence for Des Moines. The biggest challenge was implementing Residential, Commercial, and a Federal Courthouse onto a single site, where security is a high priority. The Courthouse is centralized and secured in the center of the site to address security concerns. The courthouse is represented as a simple large cube to heighten its clear monumentality to the public. The Commercial component was implemented as a source of activity but also security. The surrounding food and retail centers were placed to activate the center of the site. Restaurant, Bars, and CafĂŠs were all centralized within the bottom floor of the courthouse to serve as an activated buffer. The original scheme called for an elevated urban dwelling for the residential component, raising it high in the air over the courthouse for dynamic river and city views for residents.
22
23 Professional Work |Educational Work
Professional Work | Educational Work
LEVEL 4 TYPICAL MEZZ.
LEVEL 3 COURTROOM
LEVEL 2 ADMINISTRATIVE
LEVEL 1 BUILDING ACCESS
LEVEL -1 PARKING & SALLYPORT
Jury
JURY
Judge
JUDGE
Secure
SECURE
Public
PUBLIC
Clerk
CLERK
Courthouse Circulation Diagram
Commercial
COMMERICAIL
24
Professional Work | Educational Work
Typical Courthouse Plan (5th, 7th, 9th, and 11th)
Mezzanine Level (4th, 6th, 8th, 10th, and 12th)
N
* PU= Public Elevator PR= Prisoner’s Elevator JD= Judge’s Elevator JU= Jury’s Elevator BK= Back-up Elevator S = Services HC= Holding Cell
Special Proceeding Floor Plan (3rd)
Admin Level Plan (2nd)
N 0
25
5
10
20 m
Professional Work | Educational Work
Grand Ave.
North-South Section looking East
Indoor Urban Street
26
Professional Work | Educational Work
Courthouse Atrium
Courtroom Interior
27
28
Residential Urban Terrace
Delux Apartment Interior
29
WHERE DO WE GO FIRST?
BOARD SKATING..
LET‛S CHECK OUT THERMAL BATH.. BOARD SKATING!
WHAT A PLACE!
I CAN FEEL THE OCEAN FROM HERE
TEHEE !
HUFF ! HUFF !
WATERFRONT THERMAL BATH AND RECREATION CENTER
SEATTLE, WA
Roles: Revit modeling & diagrams. Collaborators: Youeun Lee (rendering) Jordan Washington (floor plans)
This project as a part of the new Seattle Riverfront, aim viding thermal bath services and outdoor recreational ac erfront master plan removes the Alaskan Highway, whic physically and visually blocking the access to river from t
This site is pier 62 and 63, across from a new building w river proposed in the new riverfront design by the city, re the riverfront. Therefore, this building not only provide space for outdoor recreational activities that welcomes building provides bike path and running track within it posed by the Seattle Riverfront Organization.
30
Professional Work | Educational Work
Columns
Horizontal Structural Elements
Walls
Thermal Bath Floor
ms to connect the river to the city by proctivities for the community. The new Rivch sat in between the city and the river, the city.
Bike Path Levels
with a view platform looking over to the erouting the street that used to run along es thermal bath services, but also public s the community, particularly biking. The and connects to the new bike path proExploded Axon Diagram
31
Professional Work | Educational Work
Bike path diagram
Bike Path
Second Floor Opening
32
33 Professional Work | Educational Work
34
I WILL GO TO UPPER LEVEL FOR A MASSAGE !
THIS IS AWESOME! THE OCEAN VIEW IS REALLY BEAUTIFUL !
35
Professional Work | Educational Work
RIVERWALK PUBLIC BOAT HOUSE AND BIKE SHOP DES MOINES, IA Individual Project The main point of this project is to connect the public path to the Des Moines River, and provide public space that engages the community in both indoor and outdoor activities along the Riverwalk including biking, kayaking, indoor rowing, and gathering in the public courtyard.
36
37 Professional Work | Educational Work
38
Professional Work | Educational Work
39 Professional Work | Educational Work
40
Professional Work | Educational Work
41 Professional Work | Educational Work
Professional Work | Educational Work
REVIT TRAINING COURSE Individual Project
Architect: Visioarq Arquitectos QL House, Faro, Portugal
42
43 Professional Work | Educational Work
44
45
VAN LY
lybaovan@gmail.com