Monthly Progress Report Partnership Name: Your Name: PG&E Program Manager: Reporting Month and Year:
LGEAR Tulare/Kings Maureen Hoff Dave Christensen April 2013
I. Expense Summary Table
Budget Item
Current Month Billing
Admin Marketing Implementation SER
$834.96 $579.05 $4,131.76 $349.47
Total
$5,895.24
Budget To Date Invoiced to Date Total [Includes T&M Contract Current Amount Month] $2,918.57 $18,000.00 $2,232.02 $ 32,000.00 $9,904.19 $65,000.00 $2,359.35 $65,000.00 $180,000 .00 $17,414.13
Remaining
$15,081.43 $29,767.98 $55,095.81 $62,640.65 $162,585.87
% Remaining Budget 83.79% 93.02% 84.76% 96.37% 90.33%
II. Energy Savings Summary Table
Total Energy Savings
Goals
Installed Savings To Date Current % of Plan Month
To Date Cumulative
% of Goal
Gross Installed kW Gross Installed kWh Gross Installed Therms
III. Program Overview (Non-Strategic Energy Resources Activities Only): 1. Please give a summary of project activities per budget category over the past month including major milestones, meetings, and lessons learned. Please exclude SER activities. a. Administration: