Monthly Progress Report Partnership Name: Your Name: PG&E Program Manager: Reporting Month and Year:

LGEAR Tulare/Kings Maureen Hoff Dave Christensen May 2013

I. Expense Summary Table

Budget Item

Current Month Billing

Admin Marketing Implementation SER

$579.31 $1,345.27 $2,964.47 $792.00

Total

$5,681.05

Budget To Date Invoiced to Date Total [Includes T&M Contract Current Amount Month] $3,497.88 $18,000.00 $3,577.29 $ 32,000.00 $12,868.66 $65,000.00 $3,151.35 $65,000.00 $180,000 .00 $23,095.18

Remaining

$14,502.13 $28,422.71 $52,131.34 $61,848.65 $156,904.83

% Remaining Budget 80.57% 88.82% 80.20% 95.15% 87.17%

II. Energy Savings Summary Table

Total Energy Savings

Goals

Installed Savings To Date Current % of Plan Month

To Date Cumulative

% of Goal

Gross Installed kW Gross Installed kWh Gross Installed Therms

III. Program Overview (Non-Strategic Energy Resources Activities Only): 1. Please give a summary of project activities per budget category over the past month including major milestones, meetings, and lessons learned. Please exclude SER activities. a. Administration: