DL RCC
TRA FFI C
N EW S
Saturday, 18th March 2017 – to – Friday, 24th March 2017 A public service provided by Municipal Services Department of Dún Laoghaire-Rathdown County Council. Listed below are noteworthy road works of which the Traffic and Road Safety Section has been informed. Details are supplied as per information received by 16:00 hrs. on the preceding Thursday. Emergency road works cannot be forecast. » #
New Entry Update
Estimate of Potential Disruption: *** major ** medium * minor
PROPOSED ROAD CLOSURES
Cross Avenue, Blackrock - (Temporary Closure) * Dún Laoghaire-Rathdown County Council proposes to temporarily close Cross Avenue , Blackrock at its junctions with Mount Merrion Avenue and Glenvar Park to through traffic from Monday, 10th April 2017 to Friday, 21st April 2017 both dates inclusive. The purpose of the closure is to facilitate road patching works and associated works. This work will be done on a phased basis which will allow local access to residents for the full duration of the works. The proposed diversion route will be signposted and further details will be available on our website. A Traffic Management Plan will be in operation for the duration of these works. Any interested parties may lodge an objection in writing with the Senior Engineer, Traffic Section, County Hall, Marine Road, Dún Laoghaire not later than noon on: Friday, 24th March 2017
Page 1 of 4
ROADWORKS / LANE RESTRICTIONS
»
New Entry:
»
Newtownpark Avenue, Blackrock ***
Topographical survey works will commence on Newtownpark Avenue, from its junction with Newtown Park to its junction with Stradbrook Road, during the week commencing Monday, 20th March 2017 until Friday, 24th March 2017 between 08:00 and 18:00 hrs. A Traffic Management Plan will be in operation.
»
Loughlinstown Drive, Loughlinstown **
Slit trenches and associated works will be undertaken during the week commencing Monday, 20th March 2017 until Friday, 24th March 2017 between 08:00 and 18:00 hrs. A Traffic Management Plan will be in operation.
»
Cherrywood Estate, Loughlinstown (cul de sac 1, 2, 3 and 4) *
Slit trenches and associated works will be undertaken during the week commencing Monday, 20th March 2017 until Friday, 24th March 2017 between 08:00 and 18:00 hrs. A Traffic Management Plan will be in operation.
R118 / Wyattville Dual Carriageway, Cherrywood *** The delivery of the Cherrywood Strategic Development Zone will involve significant construction works over the next 18 months in the Cherrywood area. The first phase of infrastructure provision for the Cherrywood Strategic Development Zone will be delivered by JCL the joint venture between John Cradock Ltd. /Jons Civil Engineering. Major road works began on the Wyattville Dual Carriageway between M50 Junction 16 and the N11 at Cherrywood, on 9th February 2017 and will continue for the remainder of the year. The primary focus of this phase of the infrastructure works is the upgrade of the Wyattville Roundabout to a signalised junction, and upgrade of Tullyvale Road, involving road construction, road drainage, public lighting, provision of utilities, etc. Traffic restrictions will be in place for the duration and delays can be expected. It is intended to retain two lanes of traffic inbound and outbound. Please note that Pay and Display parking on Tullyvale Road will cease permanently from 1st February 2017, however, Pay and Display parking is available adjacent to the Brides Glen Luas stop, on Cherrywood Avenue Extension.
Page 2 of 4
Pottery Road ** Construction of a new wall on the east side of Pottery Road opposite the entrance to DĂşn Laoghaire Industrial Estate (opposite Lidl) will continue until Friday, 24th March 2017 between 08:00 and 18:00 hrs. A Traffic Management Plan will be in operation.
Annaville Avenue, Blackrock ** Footpath and road restoration works will continue on Annaville Avenue until Friday, 31 st March 2017 between 10:00 and 16:00 hrs. A Traffic Management Plan will be in operation.
Mount Anville Road, Goatstown ** Works will begin on Mount Anville Road to facilitate the installation of a water main between Goatstown Road junction and Mount Anville Park, on Monday 30th January 2017 for a period of two months. Lane restrictions may be in place between the hours of 10:00 and 16:00 hours. A Traffic Management Plan will be in operation.
Public Lighting Lantern and Bracket Upgrade Works ** Public lighting lantern and bracket upgrade works will take place on: 1. 2. 3. 4. 5. 6.
Drummartin Link Road Kilmacud Road Upper Goatstown Road Rock Road Enniskerry Road Frascati Road
These works will continue until Friday, 31st March 2017. A Stop / Go Traffic Management Plan will be in operation as required.
Desmond Avenue and Cross Avenue, DĂşn Laoghaire * Public realm improvement works will continue until Friday, 31st March 2017 between 09:00 and 17:00 hrs. There will be parking and access restrictions on both of Desmond Avenue and Cross Avenue during this period. A Traffic Management Plan will be in operation. Page 3 of 4
M50/M11 - Northbound/Southbound Information on planned road works along the M50 can be found at: http://m50concession.com/operation-maintenance/planned-road-works/
End
Page 4 of 4