Saturday, 3rd February 2018 – to – Friday, 9th February 2018 A public service provided by Municipal Services Department of Dún Laoghaire-Rathdown County Council. Listed below are noteworthy road works of which the Traffic and Road Safety Section has been informed. Details are supplied as per information received by 16:00 hrs. on the preceding Thursday. Emergency road works cannot be forecast. » #

New Entry Update

Estimate of Potential Disruption: *** major ** medium * minor

PROPOSED ROAD CLOSURE

»

Section 75, Roads Act, 1993 Temporary closure of Kelly’s Avenue, Dún Laoghaire

Dún Laoghaire-Rathdown County Council has received an application from John Sisk and Sons (Holdings) Ltd), Wilton Works, Naas Road, Dublin 22 to temporarily close Kelly’s Avenue, Dún Laoghaire from its junction with George’s Place to its junction with Crofton Road to through traffic from Monday, 12th February 2018 to Friday, 2nd March 2018. The purpose of the closure is to allow service connections for the new Rapid Delivery housing development at George’s Place, Dún Laoghaire. A Traffic Management Plan will be in place and the diversion routes will be clearly signposted. Local Access will be maintained at all times. Any interested parties may lodge an objection in writing with the Senior Engineer, Traffic Section, County Hall, Marine Road, Dún Laoghaire not later than noon on 8th of February, 2018 or email traffic@dlrcoco.ie

Page 1 of 5


Section 75, Roads Act, 1993 Temporary closure of Kellystown Road, Rathfarnham, Dublin 16 Dún Laoghaire-Rathdown County Council proposes to temporarily close Kellystown Road, Rathfarnham, Dublin 16. The proposed closure will be from Tuesday, 20th March 2018 to Friday, 13th April 2018. The purpose of the closure is to facilitate drainage works between the junction with Ticknock Road and “Briarwood”. The proposed traffic diversion will be via Ticknock Road and Harold’s Grange Road and vice versa. A Traffic Management Plan will be in operation and the diversion clearly signposted. Local access to Kellystown Road, via College Road/Harold’s Grange Road junction will be maintained at all times. Any interested party may lodge an objection in writing with the Senior Engineer, Traffic Section, Dún Laoghaire-Rathdown County Council, Marine Road, Dún Laoghaire, Co. Dublin or via e-mail to traffic@dlrcoco.ie on or before noon on Thursday 1st March, 2018.

ROAD CLOSURES

»

Section 75, Roads Act, 1993 Extension to Temporary Closure of St. Fintan’s Park, Deansgrange

Dún Laoghaire-Rathdown County Council has received an application to extend the temporary closure of St. Fintan’s Park. The road closure will be from the end of the green area to the junction of St. Fintan’s Park with Abbey Court. This closure is proposed from 9.00 to 5.00pm each day from Friday, 2nd February 2018 to Friday, 23rd February 2018. Pedestrian and local access will be maintained at all times. The proposed diversion routes will be via Abbey Road and Deansgrange Road. A traffic and pedestrian management plan will be in place and diversions will be clearly signposted.

#

Section 75, Roads Act, 1993 Temporary closure of Killiney Road, Killiney

Dún Laoghaire-Rathdown County Council has made an order to temporarily close Killiney Road, Killiney from Ballinclea Road to Avondale Park from Tuesday, 13th February 2018 to Friday, 16th February 2018 inclusive, in order to facilitate road and footpath restoration works by the Roads Maintenance Section, Dún Laoghaire-Rathdown County Council. The proposed diversion route is via Avondale Park-Avondale Road-Cluny Grove-Ballinclea Road or Barnhill Road-Saval Park Road-Dalkey Avenue and vice versa. A Traffic Management Plan will be in operation and local access will be maintained. Page 2 of 5


ROADWORKS / LANE RESTRICTIONS

»

Killiney Road and Anglesea Park ***

Footpath and road restoration works will commence on Tuesday, 13th February 2018 until Friday, 16th February 2018 between 08:00 and 18:00 hrs. There will be a road closure on Killiney Road between Ballinclea Road and Albert Roundabout between 08:00 and 18:00 hrs. from the 13th - 16th February 2018. A Traffic Management Plan will be in operation and a diversion route will be in place.

»

Newtownpark Avenue, Blackrock *** (Night Works)

GRP survey works will commence on Friday, 9th February 2018 until Wednesday, 14th February 2018 between 20:00 and 05:00 hrs. A Give/Take and 4-Way Junction Control Traffic Management Plan will be in operation.

»

Old Connaught Avenue, Bray ** (Nigth Works)

A GPR survey of Old Connaught Avenue carriageway from its Junction with Cois Cairn to Dublin Road will be undertaken on Monday night - 5th February 2018 during the hours of 20:00 and 06:00 hrs. A Traffic Management Plan will be in operation.

»

N11 – Southbound between the Clonkeen and Johnstown Junctions **

Public lighting column and lantern upgrade works will commence on Monday, 5th February 2018 until Friday, 27th April 2018 between 10:00 and 16:00 hrs. and 19:30 – Midnight (if required). A Traffic Management Plan will be in operation for the duration of the work.

#

Wyattville Road Pedestrian and Cycle Scheme *** (Night Works)

Work commenced on the Wyattville Road Pedestrian and Cycle Scheme on Monday, 8th May 2017 between 08.00 and 18.00 hrs. - Monday to Friday. The scheme involves the upgrade of Wyattville Road between Wyattville Close and Churchview Road and is expected to continue until February 2018.

Page 3 of 5


Final resurfacing is scheduled to commence on Sunday, 11th February 2018 from 19:30 06:00 hrs. (night works) and continue until Friday, 16th February 2018. A Traffic Management Plan will be in operation for the duration of the works.

#

Ballinteer Road, Dundrum ***

Stone wall construction, bank formation and tree removal between Lynwood and Ailsbury Lawns will continue between 10:00 and 16:30 hrs. until Friday, 16th February 2018. A Traffic Management Plan will be in operation.

#

Avoca Ave/ Grove Ave/ Priory Ave Junction **

Public lighting column installation works will continue until Friday, 9th February 2018. A Stop/Go Traffic Management Plan will be in operation.

R118 / Wyattville Dual Carriageway, Cherrywood *** Works are well advanced on the delivery of the first phase of the road infrastructure for the Cherrywood Strategic Development Zone by JCL, the joint venture between John Cradock Ltd. and Jons Civil Engineering. This involves major road works along the Wyattville Dual Carriageway, between the M50 Junction 16 and the N11 at Cherrywood. This work is expected to continue until March 2018.

Balally Drive and Balally Estate, Dundrum*** Watermain rehabilitation works will continue on Balally Drive and in the Balally estate until Friday, 9th February 2018 approximately. A Traffic Management Plan will be in operation.

Westminster Road, Foxrock - Stanford Park Development *** Road works for the main foul and storm connections from the development into the main lines on Westminster Road at Cairn Hill junction will take place from 8th January 2018 until 16th February 2018 between 10:00 and 16:00 hrs. A Stop/Go System will be in place.

Page 4 of 5


N11 – Northbound between the Clonkeen and Johnstown Junctions ** Public lighting column and lantern upgrade works will commence on Monday, 29th January 2018 until Friday, 27th April 2018 between 10:00 and 16:00 hrs. and 19:30 – Midnight (if required). A Traffic Management Plan will be in operation for the duration of the work.

Public Lighting Lantern and Bracket Upgrade Works ** Public lighting lantern and bracket upgrade works will take place on: 1. Kilmacud Road Upper 2. Sandyford Road 3. Deansgrange Road 4. Clonkeen Road 5. Blackthorn Drive 6. Kill Lane/Avenue 7. Enniskerry Road 8. Clonskeagh Road 9. Leopardstown Road 10. Kilmacud Road Lower 11. Cornelscourt Hill 12. Avoca Ave These works will continue until Friday, 21st December 2018. A Stop / Go Traffic Management Plan will be in operation as required.

Clonard Road, Sandyford * Road repairs on Clonard Road will commence on Monday, 29th January 2018 until Friday, 16th February 2018 between 08:00 and 18:00 hrs. A Traffic Management Plan will be in operation.

M50/M11 - Northbound/Southbound Information on planned road works along the M50 can be found at: http://m50concession.com/operation-maintenance/planned-road-works/

End

Page 5 of 5


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.