24/03/2016
History
Monkstown Village Traffic Management Improvement Scheme
• Non Statutory Public Consultation took place in August and September 2012 and 78 submissions were received. • A meeting with a representative group of businesses and residents was held in January 2013. • A Report on the submissions received was presented to the 4th March 2013 DLAC meeting
UPDATE March 2016
• A presentation on the revised proposals including the public realm elements was given to the Dun Laoghaire Area Committee in April 2015 • Project update to Dun Laoghaire Councillors given prior to the Council Meeting in October 2015 • Detailed Design commenced Dec 2015
Scheme:
Architecture & Culture Department
1
24/03/2016
Additional element: Level difference at restaurants
End
- Reduce carriageway to 6m - Widen path at restuarants - Indented parking bays - Planting - Discrete drainage - Crossing point at Avoca
Current Situation
Current Situation: Avoca
2
24/03/2016
Proposed
Current Situation
Impact on parking
Existing street lighting and cables
Existing
Proposed
Impact on parking
Clifton Avenue +9 spaces
Monkstown Crescent: - Loading bays reduced in size - 1 car space lost adjacent to shops - 2 spaces lost opposite Avoca. 3 additional space at Link Road.
3
24/03/2016
Next steps‌‌. - Engage with business on Monkstown Crescent -
Detailed design completed July 2016
- Contractor appointed September 2016 - Contract duration approximately 6 months
Carrickbrennan Road
Questions?
+1 space Overall gain of 10 no. spaces
4