MEADOWSWEET DAIRY June 8 to July 10th (4 week period)
Cottage area comes together
Early June
Finishing touches on the bones of the cottage area, getting ready to install granitecrete and plants
Planting and granitecrete go well
Installing Dogwoods
mid June
Transplanting the Lemon
Ron arrives with the mailbox (finally)... but it looks fantastic
end of June
tailgate pour for the subslab
Some nice photos of the garden and our lovely Amy
Getting ready to start the Silo area, first find the new home for our arcing whale driftwood...
Some photoshop ideas for the layout
begining of July
excavation of area begins
Tuesday, June 2nd
Tile ordered, getting sub slabs and pathway ready.