NR_ Heritage Care and Development WW+P

Page 1

Design Guidelines NR/GN/CIV/100/05

Heritage: Care and Development



Document Verification

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 1/130

Revision Information Name Anthony Dewar

Frank Anatole

Department or Role Professional Head Buildings & Architecture, Technical Authority

Description of changes: First Issue

Disclaimer Department or Role Senior Architect Buildings & Architecture, Technical Authority

It is the responsibility of the Designer and / or Contractor to ensure that projects are compliant with all legislation. Compliance with this guidance does not absolve them of these responsibilities. This document is for guidance purposes only.

Department or Role

Where the guidance cannot be followed this shall be evidenced and an alternative shall be proposed to the project sponsor or Technical Authority.

Developed by Name Weston Williamson + Partners

1.0 July 2020

Principal Architect Buildings & Architecture, Technical Authority

Technical Lead Name Boaz Yariv

Version: Date issued:

Alan Baxter Ltd Boaz Yariv

Buildings & Architecture, Technical Authority

Robert Thornton

Principal Architect (Retired) Network Rail

Compiled by Weston Williamson + Partners


How to use this document

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 2/130

1 Section 1 Introduction: Summary of the document and direction on implementing the following guidance.

5

2

3

4

Section 2 Understanding the Network Rail Estate:

Section 3 Planning and the Legal Context:

Section 4 Project Planning and Management:

Architectural and historical overview of Network Rail’s stations and structures.

Advice for producing planning and listed building consent applications and recommended consultation with authorities and stakeholders.

Outlining the necessary responsibilities, duties and understanding required to achieve project realisation.

6

7

A

Section 5 Design Considerations:

Section 6 Existing Elements:

Section 7 Maintenance & End of Life:

Appendices A–D:

Considerations to undertake for good practice in the maintenance and development.

General guidance on the approach to repairs and building work on the more common station building elements, and where problems have been experienced.

Advice on maintenance considerations and good practice, and what to do when a structure has reached the end of its life, and a new use cannot be found or it cannot be repaired.

→ → → → → → →

Definitions Legislation and Guidance Image Credits Processes Useful Contacts Awards Case Studies

Hint and tips: To quickly navigate this document click on any of the sections or titles on this page. To return to the contents page you can click on the Double Arrow symbol.

6.1

Click on this symbol to navigate to the section indicated.


How to use the guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 3/130

The Network Rail Document Suite

Our Principles of Good Design 000 Series

Idiom

You are here Design Guidelines NR/GN/CIV/100/05

→ Heritage: Care and Development

100 Series 200 Series 300 Series 400 Series

TECHNICAL USER MANUALS (TUMS)

Full Guidance Document Suite

NR STANDARDS

Strategic Planning Design Compliance Operational Property

OTHER NR DOCUMENTS

This guidance has a Network Rail standards Green status, and the contents do not require derogation A full list of relevant documents, and other guidance suite documents is contained in the appendix.


Contents

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 4/130

Section 1 INTRODUCTION

Page

Introduction

09

1.1

The Guide — An Overview

10

1.2

Background

11

Section 2 UNDERSTANDING THE NETWORK RAIL ESTATE

Page

The Network Rail Estate 2.1 2.2 2.3 2.4

Section 3 PLANNING AND THE LEGAL CONTEXT

Page

23

4.1

Responsibilities and Penalties

41

3.1

Ownership of the Buildings

24

4.2

42

3.2

Planning Law and the Railway Companies

25

4.3

Project Management, Programmes and Applications

3.3

Listing

28

Conservation Areas

31

3.5

Tree Preservation Orders

32

15

3.6

Archaeology

33

History

16

3.7

Buildings at Risk

34

Architectural and Historic Significance

17

3.8

Urgent Works

36

3.9

Repair Notices and Enforcement

37

Upgrading the Historic Estate

19 20

Page

Planning and the Legal Context

3.4

Designation Databases & Managed Stations

Section 4 PROJECT PLANNING AND MANAGEMENT

3.10

Railway-specific Legislation

38

4.4

The Conservation Management Plan The Heritage Partnership Agreement

Section 5 DESIGN CONSIDERATIONS

48 50

Page

Design Considerations

53

5.1

Guidance

54

5.2

Design Principles

55

5.3

New Interventions

58

5.4

New Equipment

59

5.5

Containment of Services

61

5.6

Items Removed during Works

62


Contents

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 5/130

Section 6 EXISTING ELEMENTS

Section 7 MAINTENANCE & END OF LIFE

Page

Existing Elements

65

6.1

Roofing Elements

66

6.2

Rainwater Goods

68

6.3

External Walls

69

6.4

Windows

70

6.5

Doors

71

6.6

Painting and Decorating

72

6.7

Internal Walls

73

6.8

Ceilings and Cornices

74

6.9

Floors and Platforms

75

6.10

Canopies

7.1

Maintenance-related Design Considerations

Page 83

Appendix C Contacts and Awards Useful Contacts

105 107

National Records Centre

108

7.2

Planned Maintenance

85

The Railway Heritage Trust

109

7.3

Redundancy and Alternative Use

87

Awards

110

88

Appendix D

7.4

Demolition and Dismantling

Appendices Appendix A

Page

76

Document References Definitions

89 90 91 99

6.11

Statues and Monuments

78

Legislation and Guidance

6.12

Damp and Fire Proof Protection

79

Image Credits Appendix B Processes GRIP Process Diagram

101 102

Project Manager’s Heritage Checklist

103

Case Studies Great Western Main Line Electrification

111 113

King’s Cross Station

119

High Level Bridge

124

New Uses for Old Rooms

127


Image 0.1 Bournemouth station, Grade II listed


Heritage Introduction

1


Image 1.1 Glasgow Central station concourse, Category A listed


Introduction

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 9/130

Network Rail owns and manages an operational infrastructure of significant historic and architectural importance in an international arena. This document provides practical guidance to the legislative framework which, in the national interest, protects the unique qualities of the historic estate and also provides advice as to how best to maintain it in the appropriate condition related to its operational functionality and cultural importance.

Section 4 Design guidance The guide then deals with design issues and offers general guidance for historic fabric and, focussing particularly on stations, new elements such as platform paving, roof canopies, fixtures, fittings and services. Additional guidance is given to cover the care and long-term maintenance of the building fabric. Appendix Supporting information Useful information is contained in a series of appendices, along with project case studies.

Section 2 Historical overview The guide begins by giving a brief history of the Network Rail estate in order to highlight the cultural significance of the different types of buildings and structures in its ownership. This information is included to ensure the works proposed can be considered in the correct context. Section 3 Legislative framework The guide goes on to describe the legislation and consents framework protecting Listed Buildings, buildings within a Conservation Area, Scheduled Monuments, Tree Preservation Orders and Areas of Archaeological Interest. It also suggests appropriate time-scales to anticipate when planning projects to allow the necessary discussions with the concerned parties.

Image 1.2 Bury St Edmunds station, Grade II listed


Introduction 1.1 The Guide — An Overview The guidance in this document represents Network Rail’s commitment to the heritage in its care. Although focussed primarily on listed buildings in the Network Rail estate, the advice in the Guide is of equal relevance to buildings in conservation areas and to other listed or historically valuable structures such as bridges and viaducts, which merit a similar level of care. 1.1.1 Advice to Staff, Projects and Contractors The Guide is intended for use by all Station Managers, RAMs, Train Operating Companies, lessees, tenants and occupiers and by anyone designing or carrying out works on the network, to ensure there is consistency in the way the heritage estate is managed and maintained. The Guide sets out principles describing ‘good practice’ and offers ‘direction based on experience’ to illustrate how intelligently developed proposals, the choice of materials and well thought out interventions can enhance the value of a historic structures and have a positive effect on its operational performance and appearance. London King’s Cross and the Royal Border Bridge at Berwick are good examples of how contemporary work can sit well within historic fabric to the benefit of both parts.

1.1.2 Support for consultation and applications The guide is also intended as prior information before approaching the local planning authority (city, borough or district), the statutory national heritage bodies (Historic England, Historic Environment Scotland and Cadw) and other bodies consulted during the planning process (such as the Victorian Society, the Twentieth Century Society and local archaeological services). Its purpose is briefly to inform and advise all those having a railway heritage property within their control and care: → of the basic town planning and legal framework protecting a listed building or a building within a conservation area → of the need to consult with heritage experts, consultants and the local planning authority at an early stage in the project → of a legal requirement to obtain formal consents in advance of commencing any works, → of the need to guide works in a way sympathetic to the heritage context whilst simultaneously meeting current railway operational and commercial needs

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 10/130

It is not the aim of this Guide to provide exhaustive instructions or comprehensive specifications for the conservation of listed buildings and structures — these can be found elsewhere and tailored appropriately. 1.1.3 Pointers to further information The appendices give points of contact within Network Rail and list publications available from a variety of sources that should be consulted as necessary for further legislative and technical guidance. A glossary is not provided but readers may wish to refer to the Historic England Definitions referenced in Appendix A. To assist sponsors, project managers, engineers and contractors in de-risking the heritage aspects of a project and its programme, a project checklist is included as Appendix B. Together with the co-located planning process diagram, this checklist is to be used to ensure that the right steps are specified and undertaken at the appropriate GRIP stage. In all cases, at an early stage (prior to GRIP 3) it is essential to consult with the Network Rail architects and route town planners listed in Appendix C.

→ of the need to undertake works in a way that protects the long-term value of the premises or structure Refer to: Project Manager’s Heritage Checklist


Introduction 1.2 Background

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 11/130

1.2.1 The Network Rail Estate Network Rail owns and manages a unique and historically important estate and infrastructure. As the birthplace of railways and of many subsequent innovations, the system in Great Britain retains many features of international significance.

1.2.2 Ownership and management The UK railway system currently comprises a number of independent Train Operating Companies (TOCs) and Freight Operating Companies (FOCs) with trains and rolling stock run over infrastructure that is owned, managed and maintained by Network Rail.

1.2.3 Character and significance The geographical distribution of Network Rail’s historic infrastructure is widespread. Most of it dates to the 19th century, and all styles of architecture and engineering are reflected in all manner and size of buildings and structures.

Network Rail is among the largest land and property owners in the UK and ranks in importance alongside the Church of England, the Ministry of Defence, the Crown Estate and the National Trust. Network Rail is, however, different in that its buildings and structures are intrinsic parts of our national infrastructure, where heavy physical wear and tear are exacted on every part of the estate and its infrastructure.

The ‘operational property’ elements within the Network Rail building portfolio are maintained by designated ‘asset stewards’ although day-to-day management and care rests with the leaseholder or tenant. The exceptions to this are the ‘Managed Stations’ where Network Rail is both owner and manager.

In many cases, the early railway companies pioneered new styles and concepts, particularly in creating large-span structures, train sheds and long-span bridges. Often these make a significant contribution to the landscape or urban area in which they sit and, as such, the buildings and structures have a value beyond their intrinsic worth.

Unlike most owners of historic structures, Network Rail is expected to provide up-to-date facilities to enable a largely 19th century network to function as a 21st century railway.

The international significance of the UK rail network is widely acknowledged. The Forth Railway Bridge was inscribed as a World Heritage Site by UNESCO in 2015 and elsewhere railways are an important contributor to other World Heritage Sites, such as the Great Western in Sydney Gardens, Bath or the Midland Main Line in the Derwent Valley.


Introduction 1.2 Background

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 12/130

1.2.4 Listed buildings and structures Recognition of the architectural, historical and cultural significance of the estate has resulted in a large number of Network Rail’s buildings being protected by law through the process of ‘listing’, by scheduling as a monument or by designation of a conservation area or other area of special interest. Of the overall total of over 580,000 listed buildings in the UK, over 1,400 are railway buildings and structures.

Almost all works to listed buildings and structures may require listed building consent. To carry out unauthorised works to a listed building is a criminal offence, for which Network Rail could be prosecuted and fined.

Listed buildings are classified by grade to show their relative importance. These grades are explained in more detail in Section 3.3

Network Rail is a Central Government body and it therefore follows the Protocol for the Care of the Government Historic Estate (published online by Historic England). The Government is committed to setting a good example in the care of its historic estate and to this end the Protocol sets out a consistent, coordinated approach to protecting all heritage assets through procurement, estate management (maintenance, repair and alteration) and disposal procedures.

Recognition of the importance attached to a particular building or structure and complete understanding of what is meant by listing, scheduling and conservation areas, is fundamental to the care and development of Network Rail’s architectural and engineering heritage. It is hoped that this Guide will help to ensure new works are carried out in a way which respects what is significant about the original building or structure whilst satisfying the operational requirements of the present and aspirations for the future.

Image 1.3 Nottingham station, 1904 reconstruction, Grade II*

All works to listed, protected or otherwise sensitive historic structures should be undertaken by suitably qualified professionals with expertise in this field.

The Railway Heritage Trust (RHT) is able to offer advice and provide grants to improve the heritage features of buildings and structures that are listed or within conservation areas. They can also help find new uses for such buildings and structures when they no longer have operational use on the railway. Further details on the RHT can be found in the Appendix.


Heritage Understanding the Network Rail Estate

2


Image 2.1 The Forth Bridge, Category A listed


The Network Rail Estate

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 15/130

The assets of Network Rail, include 32,000 kilometres of track and associated signalling and electrical control equipment providing a network of more than 16,000 route kilometres, 40,000 bridges, tunnels and viaducts, 8,000 level crossings, 2,500 stations, 90 light maintenance depots and connections to over 1,000 freight terminals. Buildings around the Network Rail estate survive from all periods of the railway’s history and more than 1,450 items are listed as being of architectural or historic interest — including over 380 station buildings, 639 viaducts and bridges, 65 tunnels, 67 signal boxes, 4 hotels, 40 memorials, gates and clocks and over 250 other buildings or structures. Network Rail owns buildings and structures within all categories of ‘listing’ as scheduled in the Introduction, although most fall into the Grade II or Category C band. Some examples of structures falling within Grade I or Category A are London Paddington Station, London King’s Cross Station, Bristol Temple Meads Station, Glasgow Central Station and the Forth Bridge. The number of buildings listed should not be thought of as static because architectural periods, styles and technical innovations are continually being re-assessed and additions are regularly made to the lists. The Network Rail Route Town Planning teams should be consulted for the most up-to-date information. Image 2.2 Downham Market, 1846 Grade II listed. Refurbished 2017 to commemorate Network South East


Understanding the Network Rail Estate 2.1 History

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 16/130

The infrastructure now owned by Network Rail and for which it has responsibility was built or acquired from the early 19th century onwards, although a few buildings date from earlier times periods where, for example, the assets of a canal company were purchased. From its beginning in the 1830s, the massive growth in railway construction ensured that by the 1860s the railway map of the UK contained the majority of main lines that are still in use today. Through a process of change and modernisation, the railway estate continued to develop, mainly piecemeal, but often through concerted programmes of activity. In the 1930s financial incentives were offered to modernise the railways and many stations were rebuilt. Many other were badly damaged during the Second World War

Pre-Grouping Era These are the earliest stations, from 1830s to 1922. A good example is Wellingborough Station

Big Four Era Between 1923 and 1947 the railways were principally ran by four companies, following the Railways Act 1921

Nationalisation - British Rail Nationalisation took place in 1948, with an international modern style used widely

Privatisation In 1997 the railway was privatised, with train operating companies operating the majority of stations

Significant changes took place after nationalisation in 1948: rationalisation, which caused the closure of much of the network, and modernisation of the remaining lines. Route modifications and the installation of electrification equipment took place from the 1960s onward. During this period many stations were rebuilt for Coventry and Harlow Town.


Understanding the Network Rail Estate 2.2 Architectural and Historic Significance Railway buildings contain evidence relating to the progress during the most significant period of industrial change in the world, prior to that experienced over the second half of the 20th century. As pioneers, the UK railways should be viewed in a world context when evaluating their cultural and historic significance. All styles of architecture are represented in the Network Rail estate; from Cottage Orné to Brutalist and from Tudor to Art Deco. As well as the more well-known railway company engineers and builders such as Isambard Kingdom Brunel, Robert Stephenson and William Cubitt, many respected architects were employed to undertake extensive building works. These include Sir Matthew Digby Wyatt at Paddington, John Dobson at Newcastle, David Mocatta at Brighton, Francis Thompson at Cambridge and Chester, William Tite at Carlisle and Perth. Buildings connected to the railways have generally not only survived major social and industrial changes, but are still functioning in the role for which they were designed — which is the case with very few other industrial buildings of a similar age. No other institution has as many structures and buildings so widely scattered across the UK.

The local station is generally easily identifiable whether it be for its position in town, or its architectural style or inherent details. These may include fences, ironwork, valances or components including platforms, footbridges, canopies, ticket halls, lamp-posts and signals. In some instances, the overall disposition of the buildings gives the impression of a small village with the station at its heart. In some towns and cities, the number of railway buildings in one location is so great the station name has become synonymous with the urban district: Victoria station in London comes to mind in this respect. Stations are not only an entry point to the train services provided by the Train Operating Companies — they also serve as a gateway and can be the first and last impression of a place for visitors arriving by train. Most people are aware of the stations that serve them near their workplace or residence and generally want to see their station carefully looked after as an important asset for the community.

Image 2.3 Cottage Orné style at Ridgmont station in Bedfordshire

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 17/130


Understanding the Network Rail Estate 2.2 Architectural and Historic Significance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 18/130

To meet the demanding technical requirements of railway operation, and the ambitions of its promoters, engineers designed thousands of structures, advancing existing technologies and materials and inventing new types. It is a testament to the skill of the Stephensons, Brunel, Joseph Locke and many others that these are still operational today, and Network Rail is the owner of some of the most famous and historically important engineering structures in the world. To begin with these engineers adapted designs developed for canals and turnpike roads to create bridges, viaducts and tunnels, but often built on a hitherto unprecedented scale. George Stephenson’s Sankey Viaduct (1830, Grade I) is the world’s first and has recently had OLE installed. Of the many that followed, perhaps Ribblehead on the Settle & Carlisle is the most celebrated. Many are listed. Early tunnels, too, were heroic civil engineering undertakings, such Brunel’s Box Tunnel and Robert Stephenson’s Kilsby. Often they have highly architectural portals in a range of styles. Most early railway bridges were masonry – brick or stone – and this continued to be the norm for thousands of minor structures, often beautifully built despite their humble status. But iron, and later steel were adopted for more challenging circumstances. These do not survive as well as masonry structures because iron and steel are prone to corrosion and stress, but they include amongst their number pioneering and exceptionally important examples of Victorian engineering, and national icons:

Stephenson’s High Level Bridge between Newcastle and Gateshead and the Conwy tubular bridge, Brunel’s hybrid Royal Albert Bridge, Saltash, and the Forth Railway Bridge, the first large scale structural use of steel, and now a World Heritage Site.

Image 2.4 Barmouth viaduct, grade II* listed

Refer to Case Study 3: High Level Bridge


Understanding the Network Rail Estate 2.3 D esignation Databases & Managed Stations

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 19/130

2.3.1 Designations Databases Network Rail’s database of its listed buildings, structures, scheduled monuments and conservation areas sits within the GeoRINM geospatial records. This database is updated regularly by Network Rail’s Land Information team and is the single source of reference. However, it should be noted that new listings are continuously being made or upgraded, new scheduled monuments are being added every year, and conservation areas are often extended and new ones are created. Therefore, the database may become regularly out of date. Advice should always be sought from the Network Rail Route Town Planning Manager in respect of the planning status of any site where works are proposed. 2.3.2 Managed Stations Whilst Network Rail is the owner of all railway infrastructure in England, Scotland and Wales, the majority of the 2500+ stations are managed and operated by the Train Operating Companies. However, a small number of stations (usually the busiest) are managed and operated by Network Rail. Of these, sixteen are listed, or part listed and are of significant historic and architectural interest. Some historic information may be available to assist those managing and developing works proposals or advising third parties about the historic importance of these buildings.

Image 2.5 Edinburgh Waverley station, a Network Rail managed station. Category A listed.


Understanding the Network Rail Estate 2.4 Upgrading the Historic Estate 2.4.1 Listing — managing change, not preventing it Listing does not mean that a building or structure should become a museum piece: its purpose is to manage change in order to protect what is significant about the place — not prevent it. It is therefore generally understood by those involved in building conservation that buildings and structures on the operational network need to adapt in order to thrive. Imaginative well-designed alterations and new interventions that respect the character of the listed structure are encouraged. 2.4.2 Underlying approach to changes and modernisation It is inevitable that the continual upgrading of train services and technology may have an impact on listed structures, whether they be track realignments requiring a cut-back of canopies or the installation of overhead electrification on viaducts, through tunnels or under bridges. These challenges need to be faced realistically. Where change is necessary, care should be taken to retain those characteristics that make the building notable or memorable (its ‘significance’).

What should be avoided are short-term solutions and cosmetic changes likely to cause long-term damage such as signage and servicing installations. Interventions should be carried out with statutory consent, be well designed, reversible and not in any way detrimental to the building’s long-term future. CCTV installations are a prime example where real physical damage can be caused to the fabric of a building as well as producing a visual eyesore, whenever crude support brackets, a range of dissimilar fixings and poorly thought-out cable routes are introduced without consideration or strategy. Section 5.5 covers the containment of services in more detail. So long as high-quality heritage and design advice is received at the beginning of each project, then unexpected costs can be minimised and the risk of lost time on controversial consultations with local planning authorities or statutory national heritage bodies can be spared. The Railway Heritage Trust (RHT) is an independent body whose purpose is to provide grants and advice for preservation and restoration of operational railway heritage that is not feasible to fund by other means or require change of use. (Refer to Appendix C)

Image 2.6 Chorley flying arches, Grade II listed being rebuilt in higher position to allow OHLE installation.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 20/130


Heritage Planning and the Legal Context

3


Image 3.1 Glasgow Central station, Category A listed


Planning and the Legal Context

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 23/130

The planning legislation related to historic infrastructure is complex and sometimes open to a degree of subjectivity. This guidance explains the national laws and related processes that apply to the buildings and other assets in Network Rail’s ownership and advises on the most appropriate way to make planning and listed building consent applications and consult with the necessary authorities and stakeholders. The railway companies have inherited a legacy of special provisions and exemptions from the laws applicable to other property or land owners and these are explained as well as the responsibilities and penalties that apply to the individual companies.

Image 3.2 Stamford railway station, 1848, Grade II* listed


Planning and the Legal Context 3.1 Ownership of the Buildings 3.1.1 Ownership Network Rail is freehold owner of all buildings and structures in its estate. Other than the ‘non-franchised’ stations (that are directly managed by Network Rail) most of the other buildings are tenanted by Train Operating Companies (TOCs) and Freight Operating Companies (FOCs) and managed by them on a daily basis. The Arch Company purchased Network Rail’s former commercial property estate in 2019 and own a portfolio of approximately 5,200 railway arches, business estates, former station buildings and other properties. 3.1.2 Repair and maintenance The relationship between Network Rail, its leaseholders and tenants is based upon a contract where Network Rail is responsible for the overall condition and long-term repair and renewals of the structures while the tenant is responsible for daily maintenance and upkeep of the premises they occupy. Some premises have further sub-tenancies of the lease where, for example, a retail or catering use has been introduced or where non-rail tenants are in occupancy.

3.1.3 Landlord’s Consent Generally, the tenant is free to decorate and possibly modify the premises to suit commercial need — in all cases having first obtained formal advice and approval from the landlord (Landlord’s Consent). The most successful developments are those where the needs of all parties are satisfied and where the brief is developed and agreed through direct and open consultation. 3.1.4 Planning consents Where works are contemplated to any listed building or structure or building in a conservation area, there should first (no later than GRIP 2) be consultation with the appropriate Network Rail Buildings Route Asset Manager, Town Planning manager and the Principal Architect’s team. The Route Town Planner will consult the Conservation Officer at the local planning authority to establish whether any application needs to be made and the extent of the work to be included.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 24/130

It is, however, important to note that consultation with Network Rail’s Town Planning and Principal Architect’s Team does not remove the need to obtain, where required, formal ‘Closure’ or ‘Change’ in respect of the Railways Act 1993, Landlord’s Approval for the works or any other legal requirements. Reference should also be made to asset information files, Health & Safety files and the Risk Register before undertaking design or construction in respect of all railway buildings. In respect of works which are deemed to require Planning Permission and/or Listed Building Consent, it is the responsibility of the proposer to obtain the consents, taking advice from the Town Planning team. Section 3 provides details of the necessary steps and requirements, which can be extensive. Contractors’ scope should include sufficient resources to prepare required drawings, visualisations and reports.

Refer to Case Study 1: Great Western Main Line Electrification


Planning and the Legal Context 3.2 Planning Law and the Railway Companies 3.2.1 Seek advice Always confirm with the Network Rail Route Town Planning Manager whether proposed works of repair, renovation, extension or demolition require planning permission from the local planning authority or whether they fall under ‘permitted development1. 3.2.2 Permitted Development Many works on railway premises are permitted development. This is covered under: → Part 8 (Class A) of Schedule 2 of the Town and Country Planning (General Permitted Development) (England) Order 2015 → Historic Environment (Wales) Act 2016 → The Town and Country Planning (General Permitted Development) (Scotland) Order 1992, Part 13 (Class 34) This include most changes of use provided they serve the travelling public. However, works where the design or appearance of a station could be said to be materially altered are specifically excluded from these permitted development rights.

Works may also be permitted development under: → Part 18 (Class A) of Schedule 2 of the 2015 Order in England → Historic Environment (Wales) Act 2016 → Part 11 (Class 29) of the Scottish 1992 Order. There are restrictions on what is covered and in all cases the works will need to have originally have been authorised under an Act of Parliament. Ultimately it is the local authority that will decide whether works are permitted development. This process is generally simpler than seeking full planning permission but can still require the submission of full planning drawings and supporting information, depending on the nature of the proposal. Note that Permitted Development does not override Listed Building legislation, or the need for Listed Building Consent. If none of the above apply, then a full planning permission will need to be obtained.

Image 3.3 Newcastle Central station, 1850, Grade I listed

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 25/130


Planning and the Legal Context 3.2 Planning Law and the Railway Companies 3.2.3 Listed buildings Different rules apply where buildings and structures are either listed as buildings of special architectural or historic interest, or located within designated conservation areas, by virtue of: → Section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 → Section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1997 (Scotland) Any works of demolition, alteration, extension involving a listed station or railway structure that would be likely to affect its special character, will need to be the subject of an application for Listed Building Consent. Such works would include practically anything of a physical nature — including repainting, the addition of fittings such as CCTV and OLE and the installation of cabling — be they external or internal works. It may also extend to works in a building attached to a listed building, or located within the curtilage. This is determined by the local planning authority and not the applicant. It is important to recognise it is a criminal offence to ‘demolish, alter or extend a listed building, or affect any fixtures or fittings therein, in any way which affects its character, without first obtaining Listed Building Consent.’ The penalties for doing this can be heavy ­— a fine and / or imprisonment.

3.2.4 Scheduled monuments In the case of scheduled monuments, scheduled monument consent is required for all works, however, minor, including repairs. Consent is obtained from the Department of Digital, Culture, Media & Sport, Cadw or Historic Environment Scotland, according to location. As with listed buildings, it is a criminal offence to carry out works to a scheduled monument, and stiff penalties can be applied. It should be noted that the control of works to a scheduled monument by the above bodies is demanding. As a general principle, only works that are demonstrated to be the minimum necessary to protect the monument are likely to be granted consent. 3.2.5 Conservation areas The demolition of a non-listed building within a Conservation Area will require planning approval from the Local Planning Authority. Where planning permission is required, the impact of proposed external alterations (not internal) to an unlisted building on the character and appearance of the conservation area are a material consideration in determining the application. Any proposed redevelopment or new building must preserve or enhance the character or appearance of a conservation area. Image 3.4

Battle station, 1852, Grade II listed

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 26/130


Planning and the Legal Context 3.2 Planning Law and the Railway Companies 3.2.6 Advertising and signage Functional advertisements and signs which are displayed on stations wholly for the purposes of announcement or direction in relation to the operation of the railway undertaking, are granted deemed consent under: → Class I of Schedule 3 of the Town and Country Planning (Control of Advertisements, England) Regulations 2007 → Town and Country Regulation 1992 in Wales (amended 2017) → Class 1 of Schedule 4 in the Scotland Town and Country Planning (Control of Advertisements) Regulations 1984 (as amended) Commercial advertisements are also permitted within stations where they are not readily visible from the outside, and this is sometimes extended to station forecourts. However, these deemed consents do not override the requirement to obtain Listed Building Consent if the station is listed. Further guidance in the context of listed buildings and

conservation areas in England and Wales respectively is given in: → PPG19 — Outdoor Advertisements and Signs guidance → Technical Advice Note 7 Outdoor Advertisement Control 3.2.7 Statutory undertaker When Railtrack plc took over the management of the railway infrastructure, British Rail’s status as a Statutory Undertaker was conferred on Railtrack plc and the Train Operating Companies. This status has, in turn, been conferred on Network Rail as Railtrack’s successor. The General Development Order (GDO) in England and Wales and the General Permitted Development Order (GPDO) in Scotland exempts the statutory undertaker from the need to comply with the process of obtaining approvals under the Building Regulations or Building Acts within operational premises in England and Wales. However, Network Rail’s policy is to comply with these regulations, providing they do not contradict any operational constraints. In Scotland, the requirement to obtain a Building Warrant for any alteration or addition to a station building still applies.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 27/130

3.2.8 Accessibility The Equalities Act 2010 requires service providers such as Network Rail and Train Operating Companies to make reasonable adjustments for disabled people in the way they deliver their services. This does not mean, however, that the Equality Act overrides other legislation such as listed building or planning legislation, and the need to obtain appropriate approvals still applies in the case of changes made to improve access. An understanding of heritage significance and dialogue with the local planning authority will be required to make reasonable physical adjustments in ways which will also satisfy the requirements of listed building consent and other planning approvals. Historic England and others provide guidance on this (see Appendix A)


Planning and the Legal Context 3.3 Listing The purpose of listing is to conserve the special historic or architectural interest of a building or structure, known as its ‘significance’. Crucially, this does not mean changes can never be made. It is accepted by local planning authorities and the Statutory National Heritage Bodies that change is inevitable for listed buildings. Listing is about managing that change to balance significance and functional needs. 3.3.1 Reasons for listing The Secretary of State for Digital Culture, Media & Sport, the Welsh Ministers and Historic Environment Scotland are required under: → Planning Act 1990 (England) → The Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 28/130

The overarching reasons for designation are: Architectural Interest: the lists are meant to include all buildings which are of importance to the nation for the interest of their architectural design, decoration and craftsmanship. Important Examples of particular building types and techniques (e.g. buildings displaying technological innovation or virtuosity) and significant plan forms; Historic Interest: this includes buildings illustrating important aspects of the nation’s history; Historical Association with nationally important people or events;

→ The Historic Environment (Wales) Act 2016

Group Value, especially where buildings form part of an important or architectural or historic unity or a fine example of planning (e.g. squares, terraces or model villages).

to compile lists of buildings of special architectural or historic interest, for the guidance of local planning authorities in the exercise of their own planning function.

A building may qualify for listing under more than one of the above criteria.

Image 3.5 Conwy railway bridge, 1848 Grade I listed

The reasons for inclusion in the statutory list are set out in the Planning (Listed Buildings and Conservation Areas) Act 1990 and further expanded in a series of helpful advice notes published by: → DDCMS (Principles of selection for listed buildings) → Historic England (Listing Selection Guide Infrastructure: Transport) → Cadw (Technical Advice Note 24: The Historic Environment) → Historic Environment Scotland (Designation Policy and Selection Guidance 2019)


Planning and the Legal Context 3.3 Listing 3.3.2 Listing grades Listed buildings are classified in England (Historic England) and Wales (Cadw) by grade to show their relative importance: → Grade I — Buildings of exceptional interest. → Grade II* — These are particularly important buildings of more than special interest. → Grade II — Buildings of special interest which warrant every effort being made to preserve them.

A similar principle of subdivision into three categories exists in Scotland (Historic Environment Scotland), with Categories A, B and C. The vast majority of listed buildings are designated at the lowest level. For example, in England less than 10% are at the higher levels of II* and I.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 29/130

3.3.3 New listings The lists are not definitive and buildings are newly listed every year. Anyone can make an application to have a building assessed for listing, at any time in the planning and development process In Wales, there is a system of Interim Protection for assets that are under consultation for possible listing. This status means the building is treated as listed. In England and Wales, local planning authorities can serve a Building Preservation Notice to prevent demolition whilst listing is being assessed, though this power is seldom exercised. 3.3.4 How to find out if a building is listed All new or amended designations are provided to the Network Rail Routes by the designating authorities and are subsequently incorporated into Network Rail’s GeoRINM database. Historic England and the other statutory heritage bodies manage online registers, which can be searched by map, address, name etc. and which are revised as new and amended entries are added. Note that some of the mapping data is erroneous and the local planning authority should be consulted if there is any doubt about whether a structure is listed or not.

Image 3.6 Wakefield Kirkgate station, 1854, Grade II Listed


Planning and the Legal Context 3.3 Listing 3.3.5 Extent of listing Once included, a building is listed in its entirety. Whatever the grade or category, the listing includes the interior as well as the main structure, all features on the interior and exterior of the building, including late additions to an old building including modern replacement doors and windows, for example, even if not specifically described. The protection is not restricted to the main street level building or external envelope.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 30/130

3.3.7 Curtilage and Setting The concept of curtilage applies listed building consent to ancillary structures within the historic curtilage of listed buildings. The setting of a listed building is a material consideration in planning and listed building consent applications. For example, the local planning authority will take into consideration the impact of a proposed kiosk or other structure on the setting of a listed station building.

In some cases, alterations already made to the original building maybe of interest and their retention may be considered as desirable. The function of most list descriptions in England and Wales is simply to identify the building. They do not describe the extent of listing or significance and if a feature is not mentioned this does not mean that it is not listed 3.3.6 Enhanced list entries There are exceptions: in England since 2013, list descriptions can explain what is significant and whether anything is excluded from listed building control. An application can be made to Historic England to revise the list entry in this way. There is a modest fee but there can be significant benefits: the new list entry for Sheffield Midland station excludes a number of platforms and their structures that were previously considered part of the listed building.

Listing entry no.1 — Grade II listed Station, including platforms, footbridge / subway, canopies and anything attached to them, but not track or track bed Curtilage to listing entry no.1 Former goods office by entrance Listing entry no.2 — Grade II* listed Former good shed

Image 3.7 Example of listed elements to a station


Planning and the Legal Context 3.4 Conservation Areas A Conservation Area typically covers whole neighbourhoods, even if the buildings are not listed. Designation of a conservation area gives broader protection than the listing of individual buildings. The purpose of designation is conserve the character and appearance of historic areas. There is no longer separate conservation area consent, but it is a material consideration in planning applications. Local planning authorities are required to review existing Conservation Areas and designate new Conservation Areas. The local Planning Authority is then required to make proposals for the preservation and enhancement of the designated area. In England and Scotland there is no national list of conservation areas: these are held locally on local authority planning websites. In Wales a map of conservation areas can be accessed through the Welsh government website. Many conservation areas have appraisals whose purpose is to describe the special character and appearance.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 31/130

Prior approval application for the demolition, reconstruction or alteration of a building or structure where its design or external appearance will be materially affected. NOTE: does not apply to internal changes Prior approval application for demolition, reconstruction or alteration of a wall over 1m high facing a public highway or footpath NOTE: local planning authorities can refuse prior approval applications on the grounds of siting or impact on the amenity of the neighbourhood. In doing so, planning authorities may consider the impact of the proposals on the character and appearance of a conservation area to be a material consideration. Permitted development for the erection, demolition or alteration of buildings and structures on the station that do not affect its external appearance

NOTE: this is indicative only. The application of permitted development rights to individual stations is a matter of fact and degree: always consult the relevant NR Town Planning team for advice on what works require what kinds of permission before undertaking the works Image 3.8 Planning approvals in a Conservation Area


Planning and the Legal Context 3.5 Tree Preservation Orders Tree Preservation Orders Network Rail exemption Care should be taken where trees are near a building, or within the site or adjacent to it. Many trees are protected by Tree Preservation Orders (TPOs) and the Local Planning Authority maintains a record of their locations. Although Network Rail is exempt from complying with TPOs on its own land, this privilege should only be applied to locations that are safety critical to the operation of the railways. In such situations, NR’s powers to ignore TPOs extend also to trees in third party ownership. It should be noted however that there is always an obligation to protect certain species of nesting birds and bats. When to contact the Local Planning Authority Where works are to be carried out and any part of a tree could be affected — including roots — the status of the tree should be checked with the Local Planning Authority and the recommended protection put in place.

Consent is required before calling in a registered tree surgeon to remove branches or trim any tree having a Tree Preservation Order, without damaging the existing or future growth. Within conservation areas, local authorities should be consulted before felling a tree over a certain size, in order to decide whether to place it under a TPO. When trees are not protected by TPOs then adequate protection should still be considered. It should also be noted that there are important differences between the English, Welsh and Scottish regimes. The Route Town Planning Team can advise in all cases.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 32/130


Planning and the Legal Context 3.6 Archaeology 3.6.1 Archaeology of the railways Railways as we recognise them today first appeared in the UK in the first quarter of the 19th century and remains of early infrastructure may remain below what is visible today. Buildings used for the manufacture of early railway locomotives, carriages and rolling stock still exist on land adjoining railway stations, such as those of Robert Stephenson & Co in Newcastle upon Tyne. More recent items of infrastructure may also be built over long-demolished warehouses and industrial areas that grew up around stations that were later demolished to allow for expansion. Remains can be found in the most unexpected places — even above ground. 3.6.2 Impact of railways on archaeology The civil engineering of railways can involve the removal of much archaeological evidence. Indeed, the construction of the railways has brought about many archaeological discoveries — from the 1840s up to HS2 today. Nevertheless, works on the railway may still have an impact on buried archaeology. Information about the potential for this should be obtained from the local planning authority’s Historic Environment Record (HER), National Heritage Bodies and often from the local museum.

3.6.3 Human remains Sites may also include places of burial and cemeteries. The finding of human remains should, in the first instance, be reported immediately to the local police authority. 3.6.4 Archaeological requirements for major works When major works are contemplated, it is vital to establish the potential archaeological interest of a site. While not always of national significance even the smallest of items, such as segments of early rail equipment may be of interest to a local museum or educational establishment. For this reason, local planning authorities and archaeological services are likely to require an initial Desk Based Assessment prepared by an appropriately qualified archaeologist. Depending on the results of this, further assessment, investigation and mitigation measures may be required, as agreed in a so-called Written Scheme of Investigation (WSI). 3.6.5 Recording, removal, storage The WSI may require that, having carefully recorded their location and taken photographs of the items in situ, they should, subject to approval, be carefully removed and safely stored until their disposal has been agreed.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 33/130

The Railway Heritage Designation Advisory Board of the Board of Trustees of the Science Museum has statutory powers of designation for artefacts and should be contacted. If it is necessary to move artefacts, all fragile items should be fully supported and carried in safe packaging and be carefully stored until a decision is given on any further relocation. 3.6.6 Treasure trove The Treasure Act 1996 is a UK Act of Parliament, defining which objects are classified as treasure, and legally obliging finders of objects which constitute treasure (as defined in the Act) to report their find to their local coroner within 14 days. Items of value may be declared as Treasure Trove and are to be reported, as the law requires. The local museum will be able to provide advice. For further guidance and a list of local archaeological agencies, reference should be made in England to National Planning Policy Framework; in Wales to Planning Policy and technical guides: in Scotland to the Historic Environment Policy Statement and technical guides.


Planning and the Legal Context 3.7 Buildings at Risk The Heritage at Risk register brings together details of Grade I and II* listed buildings and scheduled ancient monuments known to Historic England as being ‘at risk’ through neglect and decay, or vulnerable to becoming so. In Wales, the quinquennial condition survey of listed buildings gives data relating to all listed buildings, irrespective of grade. The quinquennial condition survey of all listed buildings ensures that their condition is monitored regardless of their heritage grading. The criteria for being ‘at risk’ are based on assessment of condition and, where applicable, occupancy: Very Bad means a building where there has been structural failure or where there are clear signs of structural instability; or where there has been loss of significant areas of the roof covering, leading to major deterioration of the interior; or where there has been a major fire or disaster affecting most of the building Poor structure with deteriorating masonry and / or leaking roof and / or defective rainwater goods, usually accompanied by rot within and general deterioration of most elements of the building fabric, including external joinery, or where there means a building or has been a fire or other disaster that has affected part of the building.

Fair means a building which is structurally sound, but in need of minor repair or showing signs of a lack of general maintenance. Good means structurally sound, weather-tight and with no significant repairs needed. Occupancy is noted (to the best information) as vacant, part-occupied, occupied, or (exceptionally) unknown. The priority for dealing with an ‘at risk’ building considers not only the ‘static’ attributes of condition and occupancy but also the ‘dynamic’ rate of deterioration. A building in fair condition whose roof is beginning to fail and is deteriorating rapidly thus merits a greater priority for action than one whose roof fell many years before and is subject to slow erosion of its masonry.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 34/130

Priority is graded thus: A. Immediate risk of further rapid deterioration or loss of fabric; no solution agreed. B. I mmediate risk of further rapid deterioration or loss of fabric; solution agreed but not yet implemented. C. Slow decay; no solution agreed. D. Slow decay; solution agreed but not yet implemented. E. Under repair or in fair to good repair, but no user identified or under threat of vacancy with no obvious new user (applicable only to buildings capable of beneficial use; often specialised buildings which have become functionally redundant). F. Repair scheme in progress for identified use; functionally redundant buildings with new use agreed but not yet implemented.


Planning and the Legal Context 3.7 Buildings at Risk A similar register of listed Buildings at Risk in Scotland is maintained by Historic Environment Scotland. The register is a working tool, helping to define the scale of the problem and to prioritise action by everyone who can play a part in securing the future of outstanding and irreplaceable parts of our built heritage. Should you be notified that a building in your care has been added to the ‘at risk’ register then Network Rail Route Town Planning Managers are to be informed so that a plan of action can be agreed and implemented.

Image 3.9 Battersea Park station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 35/130


Planning and the Legal Context 3.8 Urgent Works Section 54 of the Planning (Listed Buildings and Conservation Areas) Act 1990 enables a Local Authority (or Historic England in London) to carry out urgent works for the preservation of listed buildings in their area after giving notice to the owner. In Scotland, the corresponding details are to be found in Section 49 of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997. The scope of urgent works notices extends to any neglected building provided that any urgent works do not unreasonably interfere with residential use. These powers can be used only in respect of an unoccupied building, or the unused part of a partly occupied building. The legislation enables the Secretary of State / Scottish Ministers / Welsh Ministers to direct that the powers shall apply to an unlisted building in a conservation area if it appears that its preservation is important for maintaining the character or appearance of that area. Local Authorities (or Historic England in London) may recover from owners the cost of urgent works carried out under these provisions, subject to an owner’s right to make representation to the Secretary of State / Scottish Ministers / Welsh Ministers. Image 3.10 Paddington station span four was issued with an enforcement notice, it is now restored and removed from the ‘At Risk Register’. Paddington station is Grade I listed.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 36/130


Planning and the Legal Context 3.9 Repair Notices and Enforcement 3.9.1 Repair Notices If a local planning authority (or Historic England in London) considers that a listed building is not being properly looked after, it may, under Section 48 of the Planning (Listed Building and Conservation Areas) Act 1990, serve a repair notice on the owner. In Scotland, the corresponding information is given in Section 43 of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997. This notice should specify the works which the authority reasonably considers necessary for the proper preservation of the building and should explain the relevant provisions of the legislation. These powers are not confined to urgent works or to unoccupied buildings.

3.9.2 Enforcement Where it appears to a local planning authority that works have been or are being carried out to a listed building that do not have Listed Building Consent or that are failing to comply with a condition attached to a Listed Building Consent, they may issue an Enforcement Notice that will set down a time period within which precisely specified works shall be completed. If, however, the works specified in the Notice have not been completed within the set period, the local planning authority may elect to carry out the works and recover the reasonable expenses incurred in doing so. In Wales provision exists for temporary stop notices, enabling local planning authorities to put an immediate halt to unauthorised works.

In Wales, local planning authorities also have the power to issue a Repairs Notice. It should specify the works that the local planning authority considers necessary for the proper preservation of the building and should explain to the owner how this part of the legislation works. A Repairs Notice may be issued for any listed building where the local planning authority considers that there has been a protracted failure by an owner to keep the building in reasonable repair and so places the building at risk. The Welsh Ministers have the same powers, but these will only be used in exceptional circumstances.

Image 3.11 Gates in Llandudno station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 37/130


Planning and the Legal Context 3.10 Railway-specific Legislation Although this guidance refers to heritage issues, it should be noted that other Acts, provisions, and regulatory control cover works to buildings in Network Rail ownership. Safety provisions governing works and operating provisions are controlled by The Office of Rail and Road (ORR). Whilst it may be necessary to secure Listed Building Consent (or Planning in Conservation Area) when undertaking works, when applicable, it is also mandatory that formal consent for the works is obtained from the Rail Regulator should they be classified as ‘Closure’ within the provisions of the Railways Act 1993, or regarded as ‘Change’ under contractual Station or Depot Access Conditions. Removal or alteration of railway facilities without approval may lead to a requirement to reinstate and a substantial fine. The railway is the only industry that has specific legislation protecting its heritage. The Railway Heritage Act 1996 enables historically significant artefacts and records that are operational within today’s railway industry to be ‘designated’ – protected and saved for the nation so that future generations will be able to understand the history of the railway in Britain. The Railway Heritage Designation Advisory Board (RHDAB) is the body that decides which artefacts and records are historically significant enough to be designated. For all proposals to dispose of such designated artefacts and records, it is necessary to contact the Board to obtain its advice and approval to do so. If the Board approves, it will also agree where the artefacts should go. Image 3.12 Settle station, Grade II listed

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 38/130


Heritage Project Planning and Management

4


Image 4.1 Coventry station, Grade II listed


Project Planning and Management 4.1 Responsibilities and Penalties Before starting a programme of design, construction or maintenance, it will be the responsibility of all those initiating such works to ensure they are familiar with current legislation and guidance and that Network Rail policies are being followed. It is also their duty to inform others who may be involved in the project of all matters relevant to their work. It is their responsibility to assess the level of consultation required from Network Rail or the degree of assistance needed from experts or consultant. For this purpose, a checklist to assist projects through the requirements at each GRIP stage is provided in Appendix B. Finally, it will be their duty to ensure consents from the local planning authority are properly in place before starting the works to avoid the possibility of facing criminal prosecution for making alterations to a listed building without consent.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 41/130

Currently the penalty on conviction in a Magistrate’s Court in England and Wales or Sheriff Court in Scotland is a fine of up to £20,000 and / or six months imprisonment. For conviction in a Crown Court the fine is unlimited and a prison sentence of up to two years may be imposed in addition to the fine. A conviction can result in adverse publicity for the individual, Network Rail, the Train Operating Company and any tenant involved. It is worth noting that criminal offences cannot be covered by professional indemnity (PI) insurance. Penalties apply from failure to obtain and comply with listed building consent, and in relation to scheduled monument consent. More information in these penalties can be found online.

For this reason, too, it is important that works are carried out in exact accordance with the submitted drawings.

Refer to: Project Manager’s Heritage Checklist

Image 4.2 Footbridge at Worksop railway station, 1849, Grade II listed


Project Planning and Management 4.2 Project Management, Programmes and Applications

4.2.1 Understanding the special requirements and timescales of listed building consent It is essential that projects fully understand the requirements for making changes to listed buildings, and the necessary skills and timescales for achieving this. The diagram and project management checklist in Appendix B summarises these for each GRIP stage and should be employed on all projects. The critical issue is to provide enough detail of the existing site conditions and the proposal at the outset. It is quite common for an insufficient level of detail to be provided and the application registration process to be held up pending the submission of the missing detail. The level of supporting information and design detail required for listed building consent is much greater than that needed for the equivalent GRIP stage. In particular, there is no such thing as outline listed building consent: permission is only granted for detailed proposals (Form 004 or AFC equivalent, or more than RIBA stage 3) and projects should build precisely what they have consent for. Amendments will require further negotiation and possibly consent; to proceed without these leaves Network Rail and contractors exposed to possible fines or imprisonments for making alterations to listed buildings without the necessary consent

4.2.2 Programme Sufficient time should be allowed in the programme for developing appropriate designs and consulting the local planning authority prior to submitting necessary approvals and consents. Projects and routes should not underestimate how much time is required to get to the point that they can start on site: → Many months of pre-application preparation and discussion will be required → The application process itself is a minimum of 8–12 weeks → Should more detail be required or should any aspect of the application be regarded as contentious this period could be extended → Even when consent has been given, there are often conditions which need to be discharged before any work can begin → See the GRIP diagram in Appendix B

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 42/130

4.2.3 Contractor scope and specification If works are contracted, the contractor specification should include the necessary resources, including an accredited conservation architect, preparation of method statements and planning drawings. Further details are in the programme management checklist. Failure to specify these is frequently the cause of programme delay. One key aspect of making a listed building consent application is the need for the applicant to demonstrate that the appointed designers are conservation specialists.


Project Planning and Management 4.2 Project Management, Programmes and Applications

4.2.4 Consulting Town Planning Team on requirements No later than GRIP 2, the Network Rail Town Planning Team should be consulted about the possible consents that might be required and how these will be negotiated. Once it is established that a listed building consent application is required, there are key issues which need to be addressed by applicants in respect of the level of design detail required to support an application and the way these are presented. The listed building consent procedures are different and separate to the planning permission processes and it will need to be established which type of application applies to a job: in some cases, both will be necessary. All approaches to local planning authorities and all applications should be made by the Town Planning Team. The RHT can offer project advice to project teams on listed building consent procedures and process. 4.2.5 Understanding the significance of the listed buildings Before a single option selection is made, the project should understand the extent of designation and significance of the structures. It cannot rely on the list entry alone, which may be erroneous and, in most cases, does no more than identify the building. The success of the application will depend on demonstrating an understanding of the building or structure and that the impact will not adversely affect its significance.

Where there is doubt about which parts of the building can be altered it and for larger, more complex and more highly graded buildings and structures it is likely to be necessary to prepare a ‘Statement of Significance’. This should be agreed with the conservation officer (and national heritage body) before options selection starts. The Statement should be proportionate to the significance of the site and the scale of the project. It

Image 4.3 Llanfairpwll station footbridge refurbishment.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 43/130

is highly desirable to appoint a specialist conservation advisor or conservation architect to prepared this. This document will serve as an invaluable aid in objectively assessing any impact of future projects. Whilst the recommended research and assessment may appear to be onerous, it will often repay the time spent by de-risking and assisting the application’s smooth progress through the planning procedures.


Project Planning and Management 4.2 Project Management, Programmes and Applications

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 44/130

4.2.6 Options selection and initial pre-application engagement Heritage risks should be properly considered, weighted and recorded in the single option selection process, so that GRIP 4 can proceed in confidence. Prior to this, it is therefore recommended to undertake a pre-application discussion with the local planning authority (and national heritage body) at GRIP3 to agree the Statement of Significance and test their response to options.

The procedure for making a listed building consent application is similar across the UK and the applications are now mostly made through the national online planning portals for England, Wales and Scotland. In making an application, local planning authorities will seek assurance that the proposed works will:

If intrusive surveys are required, this may need to be the subject of consultation with the concerned local planning authority and/or a listed building consent application: consult the Town Planning Team for advice.

→ Be carried out in such a way that minimises any damage to the historic fabric

4.2.7 Making an application Listed building applications require a set of drawings and accompanying documents explaining and justifying the proposals against planning policy and legislation. Pre-application discussions (which may involve a fee) should be used to clarify precise requirements before the documents, because these will vary from case to case. For example, they may require detailed visualisations, which take time to produce.

→ Not adversely affect the special interest of the building or structure

→ Be undertaken by appropriately skilled craftsmen under the supervision of a suitably qualified architect or conservation adviser → Even where works are necessary for operational or safety reasons, every attempt should be made to minimise any adverse impact. Generally, the forms require that the site and the proposed works are summarised and it will be necessary to provide an appropriate description, particularly if demolitions are envisaged.

The drawings should show detail, more than required for planning applications. These are equivalent to F004 or AFC. Image 4.4 Manchester Victoria station Entrance canopy

Refer to Case Study 1: Great Western Main Line Electrification


Project Planning and Management 4.2 Project Management, Programmes and Applications

4.2.8 Supporting heritage report and other documents The proposals should be justified by an accompanying heritage report, building on the earlier Statement of Significance. This should be prepared someone appropriately experienced and qualified to do so, otherwise it may not help the case: → in England, Historic England has published an advice note on the form and content of this report, which is called a Statement of Heritage Significance → in Wales, it is called a Heritage Impact Statement, and the contents and methodology are described in Cadw’s Heritage Impact Assessment in Wales This will need to include a formal statement on access in relation to works which affect access arrangements to or within any part of a listed building this is not used as a private dwelling

4.2.9 Discharging conditions It is normal for conditions to be attached to consent, covering matters such as paint colours, material samples and archaeology. Some of these are called ‘pre-commencement conditions’ which means that the works to the building cannot be start on site until the condition or relevant part of it has been discharged. The Town Planning Team will advise on how to discharge these, but they will require design resources and this should be allowed for in the GRIP 4-5 scope and programme so that a shortage does not hold up programme.

→ HES’ Environmental Impact Assessment Handbook has some guidance on Cultural Heritage Impact Assessment in Appendix 1. This may need to be supplemented with engineering method statements to prove that the works proposed can be undertaken without risk to the historic fabric. Requirements also exist for Design and Access Statements to accompany planning applications in most cases. Image 4.5 Glasgow Central station concourse, retail units

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 45/130


Project Planning and Management 4.2 Project Management, Programmes and Applications

4.2.10 Keeping records Complete copies of applications and consents are to be sent to Network Rail for inclusion in central records. These applications will require to be submitted and determined at the same time as the Outline / Planning Permission in Principle application. 4.2.11 Points to note → If it is unclear to the applicant what the appropriate level of detail is required, it is advised that a pre-application consultation is held with the Conservation Officer (which may involve a fee). → Most application forms include a check list of material required to be submitted to form a valid application and it is important to satisfy these requirements technically. If this isn’t done the application may not be officially registered. → For complex or contentious applications, it will be necessary as part of the pre-application and application submissions to provide a detail explanation of the options selection process in order to justify the preferred option. A number of projects have experienced delay or refusal because they could not provide a robust, evidence-based explanation of the optioneering process. → For large or complex projects, the scope of the works needs to be carefully defined to ensure that all design aspects of the proposal are incorporated into the application.

→ Once it is established that a listed building consent application is required to be submitted, there are key issues which need to be addressed by applicants in respect of the level of design detail required to support an application and the way these are presented. The listed building consent procedures are different and separate to the planning permission processes and it will need to be established which type of application applies to a job: in some cases, both will be necessary. → Often overlooked, but of concern, are those works within the setting of a listed building but not necessarily impacting on it physically. The sometimes-subjective nature of the assessment of the visual impact can result in a prolonged debate. It is important that the justification and analysis of the proposals should be undertaken at the correct time. → The level of detail required to support an application and the complexity of the impacts on existing buildings may, for some projects, require a Conservation Management Plan, particularly if works are to be designed in packages or are to be phased. The structure of such a plan is described in the following section.

Image 4.6 Wemyss Bay station, pictured in 2006 prior to refurbishment. Category A listed.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 46/130


Image 4.7 Wemyss Bay station, Winner of best entry at the 2017 National Railway Heritage Award


Planning and the Legal Context 4.3 The Conservation Management Plan 4.3.1 Purpose For larger historic sites and for complex or very large projects, a Conservation Management Plan (CMP, sometimes known as a Conservation Plan or Conservation Management Strategy) is universally agreed as the most effective means of demonstrating that a robust regime is in place to determine the significance of the site, the issues pertaining to it and the management processes required to maintain and develop it. In historic building conservation, a CMP is the first step in: → Preparing management proposals → Planning any major repair or restoration scheme → Planning any new developments → Managing a programme of regular maintenance For Network Rail, the usual trigger for the preparation of a CMP is the need or desire to carry out significant redevelopment proposals to a station or a major engineering structure. The proposals may be operationally or commercially driven but the requirement to prepare such a plan is driven by the same factors.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 48/130

4.3.2 Common understanding, preparing the way A good CMP helps by demonstrating that Network Rail has an understanding of the importance of all aspects of the site and that this importance will be communicated to all those involved with its ongoing care. Properly, prepared, a CMP becomes a shared understanding between Network Rail, local planning authorities and the relevant national heritage body of the significance of a site and how this should be managed, and where change might be possible and on what terms. In this way, CMPs can be an effective first stage in negotiating change and preparing the ground for major planning proposals.

The process of preparing a CMP can be described as:

4.3.3 Process The Heritage Fund (formally the National Lottery Heritage Fund) has the standard guidance on CMPs. The RHT has previously helped fund CMPs for major listed stations. Contact details for the RHT can be found in the appendix.

→ How that significance is vulnerable or sensitive to change

Underpinning this are some universal principles, but a good CMP should be tailored to the requirements of the site. Regardless of the precise style and contents, a CMP should be easy to use (eg. through the use of drawings and illustrations) and have been developed in consultation with the local planning authorities and the national heritage body if it is to be effective. Suitably experienced heritage consultants should be employed to prepare the CMP.

→ Understanding the site (through document research and fieldwork) → Assessing the significance → Assessing how and if the significance is vulnerable → Writing policies for retaining the significance → The CMP sets out: → Why the asset is significant or has heritage merit

→ What policies are to be adopted for retaining the significance in any future use or development → The research undertaken and the material collected for such purposes will also be invaluable in the development of designs affecting building


Planning and the Legal Context 4.3 The Conservation Management Plan 4.3.4 Structure A typical structure for a Conservation Management Plan would include the following, though it should always be adapted to the demands of the site and the project: 1. Executive Summary Introduction and summary of main conclusions 2. Background Author, scope, consultation process, stakeholder adoption statement 3. Understanding the asset Analysis of site history, historical phases, important features, management and operation today

6. Conservation policies Policies for the conservation of the asset to retain significance; prioritise repair and conservation; define a conservation policy philosophy; satisfy statutory requirements; work within available resources; enhance public appreciation; maintain the asset and influence future intervention 7. Implementation and review Identify next steps (action plan) and review process 8. Appendices Supporting information

4. Assessment of significance Overall summary of significance, details, components and statutory status 5. Defining risks and opportunities Identifying risk to significance and opportunities for change and enhancement

Image 4.8 Newcastle Central station, one of the major stations with a CMP

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 49/130


Planning and the Legal Context 4.4 The Heritage Partnership Agreement 4.4.1 Purpose A Heritage Partnership Agreement (HPA) is made between in a building owner and the local planning authority (and national heritage body) with the objective of streamlining the listed building consent regime, especially for large or complex sites.

4.4.3 Form An HPA can be made up of a number of different components depending on needs of the site.

Once the agreement is in place, it can reduce the number of occasions when listed building consents are required and thereby save the owner and local authority time and resources. Typically, these is achieved by identifying works that don’t require consent or that can be carried out to an agreed specification without the need for separate applications.

→ should make provision for the parties to review its terms at intervals specified in the agreement;

4.4.2 Statutory force In England, the Enterprise and Regulatory Reform Act 2013 provides a statutory framework for this. In Wales, the Historic Environment (Wales) Act provides the framework. Scotland does not currently have HPAs.

An HPA: → should be in writing;

→ should make provision for its termination and variation; → may relate to more than one listed building or part, provided that in each case a relevant local planning authority and an owner are parties to the agreement; and → may contain incidental and consequential provisions.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 50/130

4.4.4 On the Network Rail estate HPAs are still relatively unusual because the process of preparation and agreement can be lengthy. However, in 2019 Network Rail entered into its first, for King’s Cross Station. This built on the major regeneration project completed on 2012, for which agreement had been reached and detailed drawings been prepared for all aspects of the station. Under the HPA, these are the basis for agreement on matters ranging from ticket machines to public art. The agreement took two years to prepare, but in the first 12 months of its operation, the station manager estimated it saved the need to make approximately 40 separate listed building consent applications, and it is already an indispensable management tool 4.4.5 Lessons learnt from King’s Cross: → Simplicity is important → In the absence of a comprehensive project that supplies ready-made agreement and drawings on a range of details, HPAs should be developed incrementally, starting by agreeing where and for what consent is not required, and adding categories of works as projects create the necessary agreement and groundwork

Refer to Case Study 2: King’s Cross Station


Heritage Design Considerations

5


Image 5.1 King’s Cross station, Integration of new circulation in Grade I listed King’s Cross


Design Considerations

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 53/130

The general principles in this Guide are applicable to the design of works to all listed railway structures. They represent good conservation practice for the repair and alteration of listed buildings. They also show how, when approached with care and understanding, and when presented correctly to heritage stakeholders, it is possible to balance the operational requirements of a 21st century railway with the preservation — indeed enhancement — of Network Rail’s uniquely important heritage of railway structures. Design for listed buildings is about much more than like for like repairs or additions which match the architectural style and materials of the original. There are already many examples of striking additions in contemporary style materials which have not only improved functionality but also have added a new dimension to the listed structure, itself demonstrating a new phase in the UK railway’s long history of innovation and development. The purpose of the Guide is to add to that list. In recent years, Network Rail has worked closely with local authorities, Historic England, Cadw and Historic Environment Scotland to develop and agree workable and pleasing designs, and this is a process to be encouraged. Image 5.2 Royal Border Bridge — successful integration of OLE equipment onto a grade II* structure, resolving the objections of English Heritage (Arup, 1989)


Design Considerations 5.1 Guidance 5.1.1 Conservation Guidance Advice should always be obtained before undertaking even routine works in listed buildings and this part of the Guide is to assist all those involved in the repair, maintenance and alteration of buildings and structures that are recognised as having historic and architectural interest. Authentic conservation work is more widespread than even ten years ago and many materials found in railway construction are now more readily available. This Guide represents a starting point for the type of works to be undertaken and advice should be obtained from experienced conservation architects or contractors to source specialists, supplies and materials. Early discussions with the Conservation Officer at the local planning authority, or with the Statutory National Heritage Body can also help in finding solutions. Very good guidance on design, construction and matters of historical accuracy can also be obtained from The Railway Heritage Trust.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 54/130

5.2.1 Other Published Guidance Apart from government publications covering the legislation, a wide selection of publications is now available to assist those working to conserve a ‘listed building’. These range from general guides to more specialist books that deal in depth with a particular material, type or style of architecture. Some heritage groups also publish Conservation Guides that relate to the building period in which they specialise. Conservation Areas will typically have a published character summary or appraisal. This will outline the specific attributes of each Conservation Area. A number of books have been published about railway buildings giving historical and engineering information. These publications can also be helpful in providing an overview of the history of the original railway companies and their design policies. A non-exhaustive list of useful titles can be found in Appendix A.

Image 5.3 Example of Conservation Area guidance from Fenchurch Street Station Conservation Area


Design Considerations 5.2 Design Principles 5.2.1 Introduction For many working on the railways, listed buildings are perceived primarily as a project risk and it is indeed true that — too often — issues with obtaining the necessary consents cause both programme and cost overruns. But this not need to be the case, as properly designed and constructed works to listed buildings and other railway structures bring opportunities to enhance both operational efficiency and the quality of the railway experience for all users.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 55/130

5.2.2 Maintenance It is a key principle of good heritage conservation that regular maintenance (clearing gutters, painting external woodwork, etc.) is the best way to look after a listed (or any other) building. Wherever possible, those responsible for Network Rail’s buildings and structures should ensure that they are properly looked after and kept in a good state of repair.

The purpose of this section is to set out a design approach which can be applied to all listed railway structures, from the grandest station to the most functional engineering structure. Whilst primarily aimed at listed structures, it is an approach that can and should be applied to all structures on the network.

Refer to Case Study 4: New Uses for Old Rooms

Image 5.4 The York Tap - example of a structure being brought back into use for a purpose where it can help generate revenue.


Design Considerations 5.2 Design Principles 5.2.3 Balancing benefit and harm: It is important to stress that listing (or any other heritage designation) is not about preventing change, but about managing it. The overall aim is to design works in ways that avoid any unnecessary damage (or ‘harm’ in the jargon of the National Planning Policy Framework) to what is special about the listed structure, that is, the reason why it is listed in the first place. This means that all designs should be based on a clear understanding — ideally agreed with the local planning authority — of why the listed building is special. This needs to start at an overall level, but then go down into detail, to identify which parts are of particular importance and — equally — which elements are of less importance or even detract from the overall significance. This can helpfully be shown on a coloured-up drawing. The overall aim is to concentrate the works in these areas of less importance. But it is not always possible to achieve what is required without incurring an element of harm, so it is critical to be able to demonstrate that the harm is ‘necessary’.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 56/130

On the railways, the reasons might include: → Operational requirements, such as the introduction of electrification or to increase station capacity; → Safety, such as minimising the need for working at height (e.g. GRP for replacing stations fascias); → Cost benefit, such as the use of longer-lasting or more durable materials, such as platform paving.

In general terms, the greater the level of ‘harm’ to the listed building, the more compelling the necessity for the works should be. So designers should approach projects with the aim of achieving the desired result in a way that minimises the ‘harm’ to the structure. In discussions with heritage stakeholders and in the reports accompanying the listed building consent application it is necessary to show clearly that the need for the works is genuine and that the proposed solution is the one that causes the least harm to the significance of the listed structure. In the very rare cases where total demolition is proved to be necessary, the quality of the replacement design is itself an important part of the argument.

Image 5.5 Plan of Bristol Temple Meads station


Design Considerations 5.2 Design Principles 5.2.4 Designing out heritage risk: If a listed building consent application is to go as smoothly as possible, there are a number of ways that designers can approach their work. The first is by challenging Standards where — as is often the case — they are principally intended for new structures rather than for adapting existing (listed) ones. A very good example of this is bridge parapets over electrified railways, where a challenge by the Great Western design team was able to demonstrate that a less intrusive and destructive alternative to the 1.8m solid parapet — a railing with in-built mesh — could fulfil the aim of the Standard in an acceptable way. Even if the Standard cannot be effectively challenged, heritage stakeholders will expect the designer to have tried. The second is by careful thought about the architectural idiom and materials to be used. In many cases, it is right for the work to match the existing building, but there will also be cases where it is either not possible or desirable. In this case, the designer should adopt a contemporary style which is appropriate for the purpose of the new work — a new entrance should be clearly signed as such — and which is in harmony with the listed building. The same is true of the choice of materials. Reversibility is an important concept which designers should bear in mind. With the needs of railways changing constantly, it is often the case that today’s requirements will no longer apply in the future. Where possible, therefore, it is good to design alterations so

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 57/130

that they can be removed with a minimum of residual damage to the listed structure. The OLE bridge parapet railing was designed with this in mind. It is also good to look for opportunities (in so far as budgets and programme allow) to remove clutter and other intrusive features which are damaging the significance of the listed structure. The restoration of lost features — such as finials or chimney pots — is another possibility, where the Railway Heritage Trust may be able to help with advice and grant aid. As noted above, designers need to be aware of the level of information (typically RIBA Stage 3) which is required for a successful listed building consent application. This is far higher than needed at the equivalent GRIP stage, so it is very important to make the design team and contractors aware of what they will be expected to produce and when. This is set out in the attached flow chart and table, refer to appendix B. An important related point is that listed building consent cannot be granted in outline. Designs should be fully detailed and, once consent is given, the project should be completed in exact accordance with the submitted drawings and details. Any variations are likely to need an entirely new application, with significant programme and cost implications. Among other things, this makes it all the more important that designers have a full understanding, not just of the history and significance of the structure, but of its condition and structural form, so that their solutions are soundly based and do not need to be amended when unexpected

discoveries are made post-consent. It is possible to leave certain details of the design to be developed post-consent and these will be covered by Conditions imposed on the listed building consent. This is not without challenges, since discharging consents takes time, so should be factored into the overall programme, particularly where discharge in necessary before work on site can start. All this emphasises the importance of assembling the right professional team, from the heritage specialist, through the conservation architect to a contractor with the right experience of working on listed buildings. With a good team, the process and the result will be a delight. Image 5.6 Kettering Canopy brackets prior to dismantling


Design Considerations 5.3 New Interventions There are many successful examples of confident contemporary additions to historic station fabric. These can be subtle or exuberant, like the roof structure for the new concourse at King’s Cross station. Both approaches could be applied to different elements within the same station and as part of the same station upgrade. Whichever approach is taken, the best projects draw intelligent inspiration from what surrounds them and recognise and respect history and context. The right approach for each project will be found in examining the context for any proposed development in great detail and relating the new building to its surroundings through an informed heritage assessment and character appraisal. This does not imply that any one architectural approach is, by its nature, more likely to succeed than any other. On the contrary, the application of a simple formula is more likely to fail, whether that formula consists of ‘fitting in’ or ‘contrasting the new with the old’.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 58/130

Considerations for a successful project The proposals should relate well to the geography and history of the place and the lie of the land. They should sit happily in the pattern of existing development and routes through and around it. Good development will consider and respect important views, and respect the scale of neighbouring buildings. For successful integration with existing buildings it is important to always analyse and understand what is historically, architecturally and culturally significant about the place, and how this can be reinforced. Significance could lie in exteriors, the arrangement of spaces or particular details. These in turn should provide inspiration for way the new work responds, for example in its overall form, the choice of datums or use of materials.

The hierarchy of old and new parts needs to be considered. A contemporary upgrade should enhance the station as a whole and celebrate the historic fabric, not render it subservient. This is not to say that the upgrade has to be low key. Many historic station buildings are sufficiently large and confident in their own right not to be overwhelmed by bold new architecture. High quality materials, detailing and building methods should be used with careful attention paid to junctions between the new work and the heritage fabric. Low budget materials and inelegant details can be severely detrimental to historic buildings.


Design Considerations 5.4 New Equipment 5.4.1 Ticket Machines Ticket vending machines should be in a place convenient to passengers and this generally means in ticket halls, foyers or sometimes on platforms. However, even whilst meeting the needs of passengers and Train Operating Companies, these machines should also be situated to minimise adverse visual impact on the station building. They should not obscure key architectural features such as windows and should be located so as to allow future maintenance and cleaning of adjacent structures. Service runs to the machines should be hidden or concealed. Where this is not possible the routes should be located as discreetly as possible and painted to match the background. Where floor runs are inevitable and they disturb historic fabric, that fabric should be made good authentically. Floor mounted service runs should be neatly installed and any floor finish made good. Cable trays should not be used where they will be publicly visible. 5.4.2 Ticket Gates The principles for siting the gates closely follow those applying to ticket machines although the location is further constrained by passenger flow and space requirements. Although the height of the equipment is less than that of ticket machines the overall effect on a ticket hall foyer can be detrimental due to the collective bulk of machines and associated gates and staff areas. Care should be taken to minimise the impact by a review of alternative sites and the possible design of bespoke solutions where necessary.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 59/130

Associated signage and service runs also need to be carefully sited and special care needs to be given to any historic fabric that should be respected. 5.4.3 Ticket Counters Most ticket offices usually comprise a security glass screen with speak through devices having electronic enhancements for the hard-of-hearing, electronic passenger information and a cash till read-out. Where further installations are required the sites should be thoroughly understood before design work commences. Where a traditional booking office window has been inherited and needs operational modernisation the possibility of upgrading should be investigated before renewal or replacement is considered. Where an original ticket window cannot be modified the window and attendant equipment such as queue stalls, built-in signage etc. may be relocated for preservation elsewhere either in the station or at a heritage site, provided their removal can be achieved without damage.


Design Considerations 5.4 New Equipment 5.4.4 CCTV Care needs to be given to the installation of CCTV cameras and their service runs. It possible for cameras to be smaller or concealed and these should be chosen for use in more sensitive sites. While the design of the equipment may be of good quality it is often let down by crudely manufactured support brackets and poles. The visual impact of these fittings should be minimised by careful and considerate design. 5.4.5 Signage Orientation in large, complex stations has always been difficult for passengers arrive for the first time. Signage and way-finding is an essential element in any station and the simplicity of its design should be an essential feature. Although they need to be instantly apparent, signs and way-finding boards should be consistent in design, carefully sited and not positioned in such a way that they obscure views of the building or hide architectural features. 5.4.6 Lighting Lighting in historic buildings has to respond to both the aesthetics of the building and the task for which it is installed. Where original fittings exist, and can meet current operational requirements, they should be considered for rewiring and re-lamping in a sympathetic manner. The design of light fittings needs to be individually tailored to the location. To achieve an overall scheme that works well throughout the building it is advisable to consult a lighting designer. The inclusion of new light fittings may have planning implications.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 60/130

The service routes are often not considered sufficiently at the detail design stage and should be considered with utmost care. 5.4.7 Lightning Protection Tapes fixed on a building as part of the protection system against lightning strike should not be installed in a way that disfigures the external elevations of a listed building. Often, such an installation is considered of minor importance and routes for tapes and the location of spikes are left to the installer and without consideration of the impact on the building’s heritage. It is vitally important for the entire installation to be agreed with the local planning authority, and with the Statutory National Heritage Body prior to the order being placed with a contractor. In cases where a lightning protection system has already been attached to a building but needs to be enhanced to meet current technical standards the preference is to retain existing tapes where they are fixed rather than relocate. Information about the existing system and routes of lightning tapes on drawings should always be made available for use in any discussions with the local planning authority and the Statutory National Heritage Body.

Image 5.7 Integrated platform signage, CCTV and customer information screens at King’s Cross station, Grade I listed


Design Considerations 5.5 Containment of Services CCTV, new customer information systems, ticket machines and electronic control gates are regularly installed in new locations, greater quantities or in stations that have previously had manual controls. When not full considered and integrated both the equipment and the associated service runs and supplies have a hugely detrimental impact to station buildings. Careful attention needs to be given at the earliest possible stage to the service supplies to all such equipment. In all cases, the routes should be discussed and agreed with an architectural advisor before installation. This should not be left to the installation contractor. Cable trays should not be used where they are visible to the public. All services routes should be hidden or concealed wherever possible. When this is not possible the run should be minimised and designed sympathetically to the architecture, and so as to avoid theft or unauthorised access. Care should be given to the visual and spatial impact of services that require separation distances, especially if they cannot be concealed. The drilling of surface finishes such as stone, ceramic faïence and brick is strongly discouraged and should be avoided in all instances, unless there is an exceptional reason to do so. The finishes should match or compliment the background colour. Care should be taken to ensure equipment is selected of the right size and colour for

its particular location and use. Some items, such as information monitors, are likely to be standard but the visual impact can be mitigated by careful siting, attention to the design of the fixings and careful routing of the service supplies. If new equipment is being added to existing sites that are being served by inappropriate service runs, then the existing runs should be rationalised where possible and the new runs organised to take a more appropriate route. Existing routes should not be utilised without consideration of the visual impact, simply because they are more convenient. Redundant runs should be removed when installing new runs. Even when the design of service runs is carefully considered in the design stages, the risk is that during the execution stages short cuts might be sought to deal with difficult spatial or time constraints. It is therefore important to ensure that designs are always implemented to the original plans and sufficient time is also allowed for verification and approval of the work the before contractor leaves the site statues. Where the item is temporarily exposed to such weather conditions an insulating cover or box should be placed over the statue to prevent such damage. When adding to service runs, there should be consideration of future capacity that may be required, and additional provision should be included. Image 5.8 Good example at Paddington station of cable containment without negative impact to architecture

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 61/130


Design Considerations 5.6 Items Removed during Works Many historic buildings contain artefacts of great value that are often not recognised for their importance. If the artefacts have not been photographed and recorded for size, colour, special markings etc., this should be carried out. It may be necessary to bar-code objects as part of a computerised inventory so that data on the existing location, cleaning and repairs can be regularly monitored. This information would also be useful to the police should the artefact be stolen. Although the removal of artefacts from their original location in an historic building is not generally allowed, there may be occasions when relocation is necessary, subject to the provisions of the protective legislation described in Section 3 of this Guide and always after contacting the RHDAB, Items such as clocks, fireplaces, furniture, signs, posters and early equipment should be carefully removed and fixed in a suitable new location, preferably within the same premises.

Sometimes it may not be possible to re-use original features and where this occurs the items concerned should be offered to a local Railway Preservation Society, a local museum or another bona fide organisation. Some items may indeed be rare and in this event, the National Railway Museum at York should be contacted to establish whether they could be added to the National Collection. The railway is the only industry that has specific legislation protecting its heritage. The Railway Heritage Act enables historically significant artefacts and records that are operational within today’s railway industry to be ‘designated’, protected and saved for the nation so that future generations will be able to understand the history of the railway in Britain. NR has on its website a Railway Heritage Designation page with links to lists of designated items.

Image 5.9 Zero post at York Station, located at the centre of York Station and used as the measurement point for ten of the North Eastern Railway (NER) lines.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 62/130


Heritage Existing Elements

6


Image 6.1 Knaresborough Station, Grade II listed


Existing Elements

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 65/130

This section offers general guidance on the approach to repairs and building work on the more common station building elements and where problems have been experienced.

Canopies 6.10 Rainwater Goods

6.2

Painting and Decorating

6.6

Floors and Platforms

6.9

6.11

Statues and Monuments

6.12 Damp and Fire Protection

Image 6.2 Existing Elements of a Station

6.1

Roofing Elements

6.3

External Walls

6.8

Ceilings and Cornices

6.5

Doors

6.7

Internal Walls

6.4

Windows


Design Considerations 6.1 Roofing Elements

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 66/130

For the majority of historic buildings, the roof has a natural dominance. This is particularly so with railway stations, where it can be the major visual element in a landscape. In respect of smaller stations retention of the original shape, pitch, cladding and ornamentation is of great importance. It may well incorporate dormer windows, lanterns, turrets, spires, bell-cotes and cupolas as well as ornamentation such as ironwork cresting, ornamental ridges, finials and gargoyles, all of which should be retained, restored or replaced where possible. In the larger stations with shed roofs, it is important that the design integrity of the original is respected even where a new material is introduced for structural reasons, as for example the roof claddings in Manchester Piccadilly or Paddington. Chimneys often determine the overall character of a building and original chimney pots are frequently a decorative feature in their own right. In addition, chimneys usually perform additional functions, such as providing ventilation or giving structural support, which removal or alteration could jeopardise. Chimneys should never be demolished even when considered redundant due to disrepair, unless there is a compelling reason. In some cases, there may be a good reason for a missing chimney to be rebuilt and grant assistance can be sought in such instances.

Image 6.3 Chimney breast detail and roof interface at Scunthorpe station

Insensitive alterations, renewals or poor maintenance can have a dis- proportionate impact on a building, for example the removal of chimneys or replacement of original roof coverings with finishes that have a different scale. Broken or slipped slates or tiles should be replaced as soon as noticed with matching materials fixed in the same way as the originals or, if not possible, then in a visually discreet manner. The ventilation of roof spaces is also critical in maintaining a building in good condition and all grilles and openings should be maintained or reinstated if blocked. Although most pitched roofs on listed properties are likely to be of slate or clay tile, there are many other materials in use throughout the rail network where most building styles and materials are represented. Shaped stone slates, tiles and the patterns and colours in which they are laid are often a distinguishing feature of roofs that may have geographical and regional importance.


Design Considerations 6.1 Roofing Elements In roof replacement, faithful replication should be the first option to be considered. Where not possible, due to unavailability or budget constraints, materials with similar visual characteristics and performance should be chosen. Where the appropriate material is no longer in production, it may be possible to substitute from another less visible part of the building or to source from a reputable architectural salvage company. With stone, slate or old tile roofs, all visible pitches should retain the original finish. Substitute materials should be chosen with care as modern equivalents may be heavier than the original covering. Roof structures may only have been designed to carry the weight of the original material, and major problems can be caused with the substitution, for example, of slate by concrete roofing tiles.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 67/130

Whenever undertaking works to existing buildings, earlier and inappropriate repairs should be rectified. This should include the removal of crude ‘emergency’ repairs such as ‘Turnerising’ or ‘Flashband’ where they disfigure the appearance of the building. Repairs should never be undertaken by covering existing tiles or slate with bitumen or other substances that may prevent their eventual reuse. This does not mean that temporary repairs cannot be carried out when they are essential to stop water penetration and worse damage occurring while a more permanent solution is being organised. In these circumstances, the choice of methods should be limited to those that are quickly reversible without damage the fabric of the building.

There are, however, exceptions and slates have been known to be replaced by clay pan-tiles in cases where it was confirmed that these were the original material. The priority should always be to prevent water ingress and a change of material and detailing may sometimes be the better solution.

Image 6.4 Rainwater goods — replacement lead hopper and downpipe, reproduced in style of original at Bishopstone station, Grade II listed


Design Considerations 6.2 Rainwater Goods The maintenance of a roof and its drainage systems is probably the single most important element in the long-term preservation of the building. The biggest causes of rot in buildings are poor drainage, leaking rainwater systems and rising damp. If neglected, through lack of regular maintenance, the entire building will soon begin to decay. If left to fail, the building and its inherent value will deteriorate rapidly and lead to additional and unnecessary costs in putting matters right. Generally, authentic repairs or complete replacements are the most economic and beneficial. All elements, including flashings, gutters, ridges, copers, rainwater pipes etc., should be adequately sized, well-detailed and in good condition to be effective. Where gutters and downpipes need to be replaced, they should generally be materials with similar proportions and design details, especially if they were designed to sit in recesses or on specially formed ledges. Replacement using inappropriate materials can compromise the building even by seemingly minor alteration to rainwater goods. Where cast-iron or lead was replaced by PVC products, consideration should be given to the reinstatement of the original material in particular if it is visible.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 68/130

When replacing on a like-for-like basis it is essential to check the volume of rainwater to be disposed of by using data for the worst exposure in the calculation — especially to cope with potential climatic changes. Even a small increase in the number and diameter of pipes and gutters will help to protect the historic fabric from rain water spilling over gutters and down the face of a building. Hopper heads and collecting sumps should incorporate an overflow to bring instant attention to a blockage. Key drainage points should be regularly inspected and cleared. Most traditional materials can be repaired or replaced by craftsmen having the appropriate skills. Leadwork should be replaced on a like-for-like basis where possible and should not be painted over. Fixings should be discreet and match the material or section to be fixed. Galvanised mild steel brackets should not be used as a substitute for wrought iron or cast-iron brackets if avoidable. Care should also be taken to prevent bi-metallic corrosion caused by allowing contact between different metals. Many downpipes on traditional railway buildings have been hidden in cast-iron columns or masonry structures particularly in canopies or the larger sheds. Some of these are impossible to repair and will need to be replaced by visible substitutes. Minimisation of the numbers of downpipes needs to be considered and modern methods of drainage such as syphonic drains may need to be adopted.

Where there is a danger of damage to downpipes, particularly cast-iron or lead, on external walls, provision of protection such as bollards or railings should be considered. When building works are in progress, maintaining the free flow of rainwater and other drainage systems is often overlooked. A major cause of concern is when water is being used to clean the exterior or interior of a building. Prior to such work it is essential to establish if the disposal of the additional volumes of water is achievable using the existing pipework because it may be necessary to install a parallel system to be drained off elsewhere. Whatever the outcome of calculations, existing pipework should be flushed through to ensure it is free-flowing before water cleaning begins. Because the cleaning will remove large amounts of dirt and the debris, drainage outlets should be provided with a fine mesh grating to stop the drainage pipework being blocked and flooded, a problem that may not become apparent until sometime after the cleaning is finished. The run-off from cleaning may also contain chemicals and contaminate the local water supplies. A method statement on the means of disposal may be required by the local water company.


Design Considerations 6.3 External Walls External walls can be found in almost every architectural style and type on the Network Rail estate, on viaducts, bridges and tunnels as well as station buildings. The materials used range from timber-clad, timber-framed structures to load-bearing brick and rusticated granite. Provided water in all its forms continues to be effectively excluded from the building or structure, the walls are likely to be more damaged through misguided maintenance than through natural wear and tear. For example, cleaning of some stone using high pressure water can cause more harm than good. Maintenance of existing walls should respect the original construction method and be repaired only where necessary on a like-for-like basis. Note that brickwork sizes have changed over the years and it may be necessary to manufacture specials to match the originals. It is not just brick colour and texture that determine the appearance of brickwork. The type of mortar, its colour and style of pointing are major contributors. This is especially important to consider when repairing small areas of existing walls. Care needs to be taken in selecting the correct materials, not just for appearance but also performance. This is particularly important where lime mortars have been used with soft brickwork. However, great care should be taken when specifying a ‘like-for- like’ repair because assumptions about the earlier work may be inaccurate. A mortar analysis, at relatively low cost, can prevent some very costly mistakes. Pointing should be in a consistent style.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 69/130

Similarly, when repairing stonework, care should be taken to match the type of stone, mortar and fixings. A petrographic analysis should be made whenever there is any doubt about the origin of the existing stone. It is inadvisable to mix reconstructed stone with natural stone. The choice of mortars and renders should be carefully considered. The different movement characteristics of non-matching fixings can result in structural failure. Some stations are clad in terracotta or its glazed form, faience. These are very specialised materials and expert advice is required when specifying remedial or replacement works. The damage caused to terracotta by, for example, cleaning with acid is irreversible. Where a block or tile is badly damaged and has lost its structural integrity, it can be cut out and replaced with a new matching block or tile from a specialist manufacturer. Where ledges or mouldings are incorporated into walls they should be maintained in good condition. Where they might collect water as a result of their shape, they should be properly flashed, generally with lead. If mouldings and projections are not repaired differential wetting and staining of the wall may occur, leading to possible deterioration in the wall’s condition. In respect of surface treatments, such as waterproofing or anti-graffiti barriers, these should generally be avoided or specialist advice taken before application. Such treatments can change the appearance of materials and dampness can be sealed

in, inadvertently, worsening the rate of deterioration. In any event, removal or repair of the coating, should it fail, can be a costly item and cause more damage. Where external materials are used internally, for example in larger halls and sheds, then the same care needs to be taken as if they were being used externally. Image 6.5 Stone window details, arch entrance and snecked quoining at Stone station, Grade II listed


Design Considerations 6.4 Windows

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 70/130

Alterations to the original external windows can have a discordant impact on the exterior. Wherever possible, such elements should be repaired or reinstated to the original pattern, profiles, materials and finish. Great care should be taken in selecting the correct glazing bars and frame sections when matching existing windows. Original glass is to be retained and protected during any construction work. All replacement glass should match the original in colour, weight and appearance. The uneven surface of older types of glass adds sparkle to a façade whereas modern float glass can make a listed building look worse. Where obscured glass is used, it should be of a consistent pattern, and not piecemeal. New double-glazed aluminium or PVC units are not normally suitable additions to historic buildings. Even apparently ‘identical’ replacements may not be historically correct and will be judged as inappropriate in certain circumstances. Where double-glazing is required for sound or energy insulation, and where the original windows are in good condition, other options such as discreet secondary glazing should be explored, as should a full overhaul and draught-stripping of the original windows, for this can bring a marked improvement which might satisfy requirements. The material, detailing and fixing of the secondary frame should, however, be well thought out, as should requirements for smoke venting and ease of opening by the Fire Brigade. Image 6.6 Sash window at Snodland station

However discreet they may at first appear secondary glazing units may need to be camouflaged with carefully chosen colours. Where windows are to be extensively repaired, replaced, or simply overhauled, consideration should be given to access and safety of maintenance and cleaning. It is also important that retained sashes have the correct weights attached for smooth operation. In some situations, it will be necessary to install safety glass or to add security films. Laminates of glass / polycarbonate / glass (GPG) are available that can include old styles of glass for the exposed surfaces. These can be obtained in a thickness that may fit the depth of existing rebates.


Design Considerations 6.5 Doors 6.5.1 External Doors and Fan-lights Alterations to the original external doors and windows can have a discordant impact on the exterior. Over time many will have been damaged or inappropriately maintained or repaired. Where doors are retained, they should be restored to the original pattern, profiles, materials and finish. Great care should be taken in selecting the correct glazing bars and frame sections when matching existing work. Original glass should be preserved and protected during construction work. All replacement glass should match the original in colour and appearance. Where safety glass should be installed matching GPG laminates are available. Door-cases, foot-scrapers, pediments, columns, pilasters, cornices, etc. should not be damaged and retained even if the door way is redundant. Repairs to such elements should always be authentic. Where fanlights were part of the original design they may have been covered or altered, possibly by insertion of ventilation units. Every opportunity should be taken to reveal and restore fanlights to their original pattern and material. Often door ironmongery has been damaged or replaced. All original ironmongery, including butt hinges, locks, handles, escutcheons, decorative studs and grilles, should be retained, cleaned and secured in place. Inappropriate kicking plates, finger-plates and other applied protective elements should be replaced by new elements that are in keeping with the originals. Any additional security that is needed may be provided by additional suites of sympathetic design or in some

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 71/130

cases by substituting the hidden mechanisms. Door closers and other mechanisms should be discreet and on external doors should be fixed on the inside face. Where inappropriate signage has been applied to a door this should be removed. Self-adhesive signs may damage layers of polish or paint when removed and should not be used. If new signage is necessary it should respect the construction and design of the door and be fixed in such a way as to be removable without damaging the original. 6.5.2 Internal Doors Internal doors are more likely to have been altered or replaced over the years. The conservation policy in each location may have to be made on an individual building basis. Original doors should be retained and repaired. Generally, all new doors should be on a like-for-like basis and match those proven to be contemporary with the building. Where doors need to be upgraded, for example in connection with enhanced fire protection, this may be possible with approved surface treatments and the insertion of intumescent strips and smoke seals into both the door and frame. In panelled doors, the weakest part is usually the thinning of the panel that allows it to be held in the main frame. Sometimes it is possible to add a discreet new panel and mouldings to one side of a door over a layer of fire resisting material. Image 6.7 External door on platform with fanlight and Terracotta detailing at Nottingham station, Grade II* listed


Design Considerations 6.6 Painting and Decorating While painting and decorating is perceived as a simple operation, there are specific issues concerning paint finishes in the railway heritage context that need to be considered carefully. Equally important to the choice of colour sympathetic to the building and appropriate to the element of fabric are: matters of access, safety, application technique and long-term performance. Whilst accepting that painted finishes are ephemera by nature, a poorly chosen or badly executed colour scheme can have a disproportionately detrimental impact on a building. It should also be remembered that changing a colour scheme once applied, as opposed to repainting within the maintenance programme, could be a costly item especially where track possession can complicate access or the erection of scaffolding. Higher performance, longer lasting paints should be used in inaccessible spaces or where the repainting of adjacent buildings would disrupt train movements. In such safety critical circumstances, the use of historically correct paints and colours may be moderated. Colours are usually applied to appropriate parts of buildings that reflect the livery of the railway company in occupation. However, there are general ‘rules’ that will help to achieve a recognisably ‘branded’ building whilst respecting the historic fabric. It is usually better to use neutral or light colours on soffits, at high level and on other less accessible structures that are likely be repainted least often in the maintenance programme. More readily accessible elements offer

scope for less permanent decorative colour schemes where they can be quickly changed or refreshed. Where it is felt that an understanding of the original colour scheme would be beneficial, specialist help may be needed to establish the original colours or patterns, particularly where later materials such as panelling, wall tiles or glazing hide the painted surface. In sensitive cases, careful site analysis and paint scrapes may be needed to establish the original colours or stencil patterns where they are known to have existed. Original colours and wallpapers can be found behind light switches and other attached wallfittings and hidden behind later alterations.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 72/130

detach earlier finishes. In such circumstances, it may first be necessary to strip the original paint using a suitable removal system that has been evaluated by testing prior to use.

Most paint-work found on older railway buildings and structures will contain lead. Sometimes earlier lead paint will be hidden beneath layers of more recent lead-free coatings. Statutory guidance is available in respect of its safe removal but the scale or magnitude of the problem should not be underestimated, particularly on the larger station shed roofs. Although lead paint can no longer normally be used, there are Grade I listed buildings of high historic importance where it can be required and special permission for its use can be granted. In respect of performance, paint selection should reflect the need for any underlying historic material to perform technically — for example, expansion, contraction or permeability. It should be remembered that modern products differ from older ones and new paint films tend to dry and create tensions that can

Image 6.8 Colour schedules require research into establishing original colour — example from Manchester Piccadilly station, Grade II listed


Design Considerations 6.7 Internal Walls Traditional internal walls are mostly plastered and have been painted and redecorated at regular intervals over the years. However, many still retain original tiling, sometimes ornamental, and many retain a timber-boarded dado. Often walls have been neglected or damaged by inappropriate fixings of equipment or services. Mouldings may also have been removed or damaged by built-in furniture and fittings. Whilst not advocating wholesale reinstatement of missing elements, care should be taken to protect any historic elements that remain, particularly if decorated in such a way as to be unique to the railway, as for example the railway routes incorporated on glazed tiles in London Victoria station and across the former North Eastern Railway (NER) routes. Tiling, such as that at Worcester Shrub Hill, should be treated with great care and only repaired or maintained with specialist advice.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 73/130

Surface mounted items such as timetable boards or advertisements should respect the elements of a wall and not generally cut across items such as dados, niches, panels or mouldings. Where possible use should be made of existing disused fixing holes. Where plaster is to be repaired, matching materials should be used or ‘disruption’ may occur at junctions between old and new work. Analysis of the existing plaster can be very helpful in sorting out the mix to be used. When injected damp-proofing works have been carried out the type of plaster to be used should follow the information provided by the supplier. Where waterproofing renders have been used, fixings should not be made through them but only into specially made pockets of solid render otherwise the guarantee will not apply.

Services mounted on the wall surface should be removed when an opportunity presents itself and new runs should be either concealed if possible or managed in a way that does not clash with existing heritage.

Image 6.9 Polychrome tile map of the North Eastern Railway network at Tynemouth Metro station, Grade II* listed. This is one of 23 installed by NER. This is on an external wall, under a large glazed canopy.


Design Considerations 6.8 Ceilings and Cornices The ceiling can be the most dominant feature in a room. It is often a major element in creating the overall character of the interior space. In older premises ceilings and cornices were damaged when conduit to light-fittings and other service pipes have been introduced. In some cases, false or suspended ceilings still hide original ceilings from view with hanging systems fixed through holes penetrating the plaster in order to reach the structure above. Where possible ceilings and cornices should be restored on a like-for-like basis with later fittings or attachments, including suspended ceilings removed or relocated. Where thick layers of paint obscure cornices. Where chemical stripping is required, caution should be exercised as they may not be made of plaster and chemicals can dissolve the moulded decoration. Feature lighting should be considered to compliment the ceiling and to illuminate it beneficially. The choice of functional lighting should follow the standards recommended for the use to which the room will be put.

Image 6.10 Cornice detail at Manchester Victoria station, Grade II listed.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 74/130

The choice of illumination should be in a colour to complement and highlight the colouring in the building, whether it is in brickwork, tiling or a painted finish; the fitting itself should be unobtrusive. When contemplating running new services through a void in the ceiling of a room or space that has a ceiling that may be restored at a future date, an appropriate route should be identified that respects the original space to avoid the need to reroute the services at a later date.


Design Considerations 6.9 Floors and Platforms 6.9.1 Floors Most ground level floors in stations have been either rebuilt or re-laid during their lifetimes. Original flooring materials, such as encaustic tiles and wood blocks, do, however, exist in some buildings. Where these remain in an operationally acceptable condition, they should be authentically repaired and retained. It should be noted that in some wood block floors the bitumen bedding also acts as the damp-proof membrane and may be difficult to repair or replace. When selecting a new flooring material or considering the extended use of an existing surface, thought should be given to both durability and slip resistance. Tests may be required to determine whether a slip-resistant treatment needs to be applied to an existing floor.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 75/130

6.9.2 Platforms Platform support walls and structures such as trestles or cross walls, whether they are being rebuilt to meet current standards or repaired, should be in traditional materials, where possible, and in sympathy with the platform buildings. Where historic surface materials survive and are in good condition meeting current safety requirements they should be retained, with complementary material used for any new work. These materials should generally be used in combination with traditional detailing and compatible modern techniques. Selection of new materials in an historic context should take into account the scale, colour, texture, composition and weathering properties of the proposed materials against the originals they will be adjacent to.

Skirtings and mouldings are often an important element in preserving the original character and should be retained if possible. Victorian skirtings are generally of larger proportions than readily available replacements and will require specialist manufacture. Some tall skirtings may be in hard plaster rather than timber. These can be replaced or repaired by specialist sub-contractors.

Image 6.11 Encaustic tiles at Lancaster station, Grade II listed

Existing platform copers should be retained if they are of significant architectural or historic value to the station, providing they are compliant with current standards in respect of gauging and construction. It may also be possible to reposition copers of historic value to meet gauging requirements and thus avoid their loss. The quality and material of the tactile strip should respect the fabric of the adjacent building in terms of colour and texture. Tactile strips are available in engineering brick, stone, concrete, ceramic and as applied finishes. In all cases, however, the tactile strip should fit the design and choice of platform finishes and comply with current safety and access standards.


Design Considerations 6.10 Canopies

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 76/130

Platform canopies, whether attached to buildings or free-standing, are usually one of the major characteristics of a station. Whilst station buildings on a particular route may vary according to locally available materials, the canopies on the same route within a former railway company may very well have a common pattern, whether that be the valance design, cast-iron supporting structure or glazing styles. Most are of simple, elegant, structural design. Frequently the opportunity was taken to embellish the structure, particularly cast-iron work, with company identification. This makes them of great value when contemplating renovation or alteration works. Cast-iron foundries do exist and replicas can usually be obtained if necessary. Some foundries have also re-opened and are utilising traditional moulds and patterns. Repair work should be authentic and advice taken to source the appropriate products. Where necessary new moulds can be taken from examples on site or from acknowledged identical or similar patterns.

Image 6.12 Platform canopy at Bury St Edmunds station, Grade II listed.

When re-glazing is required, the traditional methods should be the starting point. Whilst original materials may not be available or acceptable for use, frames should be of the same appearance, cross section and scale of the original, if Health and Safety requirements allow it. Glass should be used where structural considerations and security arrangements permit.

The Glass & Glazing Federation may be consulted over the type and supplier of appropriate materials. Sheets with a similar scale and profile to those originally used should be selected if possible. Where polycarbonate alternatives are unavoidable they should be fire-performing and self-cleaning. When adjacent lines are being modernised to meet current electrification standards, it may be necessary to cut back the canopies from the platform edge. This may result in the need to alter the support brackets and reposition the valance and gutter system. This should be done discreetly and as much of the original material re-used as possible. Where valances are being replaced, they should be of the same patterns are the originals and normally in the same materials, but the RHT has produced a report on Station Canopy Fascia Daggerboards that examines when FRP might be acceptable instead, because of its reduced maintenance burden. Services, or fixtures and fittings that are to be found beneath canopies have often been crudely attached to these structures. Frequently the routes to items such as CCTV cameras and passenger information monitors has often been along a cable tray, laid, fully visible, on the bottom truss of canopy brackets. This is to be avoided wherever possible and the opportunity taken, in any refurbishment or renovation, to relocate service runs out of sight.


Design Considerations 6.10 Canopies

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 77/130

Where this is not possible the service routes should be as visually discreet as is practical, being located sympathetically to the architecture and not competing with original design features. They should also be painted to match the background colour. Before installation is begun all runs and routes should be discussed and agreed with a conservation expert or architect. Drainage within canopies, where downpipes are concealed in cast-iron columns, can often be problematic. Blocked drains can freeze and cause fracturing of the cast-iron. Sometimes canopy drainage runs back into concealed downpipes within the masonry of supporting structures. Regular maintenance and cleaning is essential, as repairs to damaged systems in these circumstances can be difficult. As a last resort, it may be necessary to devise new methods of draining the canopy. Where any new system is visible it should be sympathetic in terms of materials and scale to the original or existing structures. Where the expansion of ice may crack concealed pipework the use of trace heating tape should be considered Canopies have often been subject to elaborate colour schemes, usually to display ‘branding’ or company identity. It is generally preferable to keep ornamental ironwork and canopy brackets painted relatively simple in light colours and allow branding to be applied only to elements that can easily be repainted upon change of occupant. In all cases where branding is implemented, care needs to be taken to ensure that it is applied in a way sympathetic to the design.

Image 6.13 Grange-over-Sands station, Grade II listed


Design Considerations 6.11 Statues and Monuments Railway stations are home to a number of valuable statues, sculptures and monuments. Such items should be fully protected in a robust wooden enclosure during building operations. Specialist advice should always be obtained prior to an item being cleaned or before attempting to remove paint or mortar splashes from the surface. If it is necessary to move an item to facilitate building works, specialists should be brought in as they will have the experience and equipment necessary to carry out the task. Ice and frost can easily damage stone and marble statues. Where the item is temporarily exposed to such weather conditions an insulating cover or box should be placed over the statue to prevent such damage. The RHT maintains a database of railway war memorials, and should be consulted on any proposed changes.

Image 6.14 Sir Nigel Gresley Statue at King’s Cross station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 78/130


Design Considerations 6.12 Damp and Fire Protection 6.12.1 Damp It is acknowledged that dampness is among the prime causes of decay in a building. If it is established that the damp is definitely originating from the ground, a range of methods to create damp-proof courses in walls are now available, with varied benefits. It should not be forgotten that some methods of chemical injection have a limited design life of about twenty years and will need to be renewed. By considering the factors associated with the works being carried out, alternative methods may prove to be a better choice over the long term.

Dampness in buildings also helps create conditions for a wide range of fungal decay mechanisms to thrive. It is vital, if a building is to remain in sound condition, that checks are made of places offering the potential for fungal outbreaks before they become a serious problem. Disused basements or unoccupied buildings on the other side of a party wall should be regularly inspected, their condition recorded and any sign of an outbreak reported so remedial action can be taken quickly. It is essential that the cause of damp is identified so that the cause can be addressed, rather than the symptom.

There are other simple actions that will help mitigate damp problems. Regular checks should be made to ensure that any outside ground works are kept well below the internal floor levels. Where a damp course is installed, the ground should be kept a minimum of 150 mm below the damp proofing. Surrounding pavements should be laid to slope away from buildings and provision made to get the water away by drainage. In some cases, it may be necessary to install runs of land-drain in the perimeter of a building

6.12.2 Fire Protection Where it is necessary to achieve fire protection to structures and other elements using specialist coatings it is advisable to check with the manufacturer as to the thickness required to meet the necessary fire rating before specifying their use. The thickness may well be excessive and when applied destroy the detail of the surface being coated.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 79/130


Image 6.1 Refurbishment of pilaster and brickwork at York station


Heritage Maintenance & End of Life

7


Image 7.1 Care and maintenance of bridge and columns at Bermondsey Spa Road


Maintenance & End of Life 7.1 Maintenance-related Design Considerations Good maintenance is an essential feature of any successful building management. It is especially so in respect of historic buildings where the materials used in their construction may have different characteristics to those used today. Knowledge of building history and construction techniques can help in forecasting maintenance tasks, particularly in hidden areas such as cavities and voids where poor ventilation may cause rot problems. Maintenance or improvement of ventilation levels is nearly always essential to keep an historic building healthy. Checks should also be made to ensure airways are kept free where insulation is used in roof spaces and especially after works have been carried out. Great attention should always be paid to the dispersal of water and the maintenance of rainwater goods. Poor or faulty drainage in and around buildings is a major risk that can lead to numerous negative consequences. Damage to interiors, fittings and finishes can also occur, even from relatively small faults. It is essential that roofs, parapets, gutters, downpipes and sub-surface drainage are all functioning without fault and that any preventative measures put in place are doing their job. Snow and ice can exacerbate the problems caused by poor drainage and ventilation and may cause pipes to split or masonry to spall.

Should water not drain or evaporate from a building adequately, the remaining damp may encourage algae, fungus, mould, moss and lichen growth, particularly on the more porous masonry materials such as stone and brickwork. Moss should not be allowed to take hold on roofs, particularly those shaded from the sun, as this will eventually fall into gutters blocking them and may promote self-seeding plant growth such a Buddleia or Ash that in turn could dislodge parapets and coping stones. Inappropriate repairs, however well intentioned, can also often cause damage. For instance, the use of cement-based mortars to repair brickwork bedded n lime mortar can lead to structural damage through differential permeability or retention of moisture. Of particular concern is the temporary overpainting of surfaces for purposes of branding or refreshing the appearance of tired looking finishes. Construction or repair needs to consider the likely level of exposure and ensure that new material will be placed and secured accordingly. Strong winds, for example, can cause problems for dry-fixed tiles and slates. Dislodged roofing or wall tiles and slates will allow the ingress of water. Materials and fixings need to be appropriate for the predicted exposure.

Image 7.2 Maintenance on the Forth bridge, taking place near the live railway without disrupting train services

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 83/130


Maintenance & End of Life 7.1 Maintenance-related Design Considerations The importance of regular inspection and timely maintenance cannot be over-emphasised. In all properties, a single person should be nominated with the responsibility for carrying out or arranging regular inspections. Such inspections are especially important both before and after winter rain, snow and wind. The inspection should be followed closely by any identified remedial measures.

A further, but often-overlooked aspect of maintenance is to keep up-to-date Maintenance Manuals and ‘As-installed’ Drawings in a single filing system where they can be kept up-to-date. In much the same way as original drawings and photographs are an invaluable aid to the restoration of an historic building, updated information can save a great deal of time when planning maintenance schedules and coping with emergencies.

The main requirements for successful maintenance are: → Planning — ad-hoc reactive maintenance can be costly as well as ineffective. → Regular Inspections — continual vigilance to identify any damaging activity such as leaking pipes, etc. → Informed Forecasting — considering the nature of the building and experience with similar construction. → Quick Response — to any problem found and emergency repairs → Access Routes — planned, constructed and readily available to allow safe access to all areas requiring regular and essential maintenance. → Maintenance Sheets — to ensure the correct cleaning methods and materials are used. → Training — to ensure staff are aware of conservation aspects of the building and report damage as soon as they are observed.

Image 7.3 Footbridge before repair at Settle station, Grade II listed

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 84/130


Maintenance & End of Life 7.2 Planned Maintenance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 85/130

There are two aspects to current Network Rail maintenance policy: → the safe management of railway structures → the long-term care and maintenance of the asset. In respect of the first, all Network Rail standards in respect of Asset Management apply and this requires visual examination once a year and a detailed examination of certain classes of structure at intervals between 6 and 12 years as determined by risk assessment. Structures that cross tracks, including rafts, footbridges and shed roofs require detailed structural assessments.

Image 7.4 Carlisle station, Grade II* listed pictured in 2012 prior to roof refurbishment

Image 7.5 Carlisle station, roof refurbishment in progress in 2016


Image 7.6 Carlisle station, after refurbishment


Maintenance & End of Life 7.3 Redundancy and Alternative Use 7.3.1 The need for disposal or replacement There are occasions when historic structures are no longer operationally required, or cannot meet operational or safety standards, and a viable alternative use cannot be found. In other instances, historic infrastructure may stand in the way of vital upgrades and enhancements. Very occasionally, a structure may be beyond reasonable economic repair, even with support from the Railway Heritage Trust and others. There are also instances where a building (such as a signal box or goods shed) may no longer be required, where a collection of properties need to be rationalised or where structures no longer meet operational or safety standards. 7.3.2 Legislative and policy requirements If such a structure is listed or in a conservation area, legislation and planning policy expect Network Rail or its tenants to find the appropriate financial resources or a new use, and to demonstrate in detail why this is necessary. Permission for the demolition of listed buildings is only given in exceptional circumstances. 7.3.3 Disposal advice Should a property be considered for disposal it will be necessary in the first instance to seek advice from Network Rail Property to understand what special conditions or covenants may apply. Network Rail will also advise on the need to bring in consultants to assist in the sale. Refer to Case Study 4: New Uses for Old Rooms

7.3.4 Protecting vacant buildings When construction work is delayed on a property that is designated for re-use, the individual buildings should be regularly inspected and maintained in a secure, safe and stable condition. This will help to retain their value and minimise the risk of incurring the cost of unnecessary repairs. In isolated properties, valuable items such as fireplaces or decorative elements are a target for thieves and should be secured. In extreme circumstances where the risk of damage is high, removal to secure storage for reinstatement later may be considered. Listed Building Consent may be required and this should be clarified with the planning authority and the relevant statutory national heritage body. Where a building is less isolated, fireplaces and other items should be fully enclosed within timber boxing with inspection panels through which the item can be verified it is still in place. In all cases an intruder alarm should be considered. The terms and conditions of insurance policies should be checked for exclusions that may jeopardise a claim for the replacement cost of items stolen from an unoccupied building. Image 7.7 Wroxham Signal box. Members of the Barton House Railway set up the Wroxham Signalbox Trust to preserve and restore the signal box Image 7.8 Victorian columns at old Blackfriars station were reused by Pontypool and Blaenavon heritage railway

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 87/130


Maintenance & End of Life 7.4 Demolition and Dismantling 7.4.1 Exceptional circumstances An application for the demolition of a listed building should be made in exceptional circumstances and only as an option of last resort. The presumption in law and policy is that a listed building shall not be demolished unless it can be shown that there is no reasonable alternative. In only a few instances can it be agreed that partial or wholesale demolition of a building or structure is the only solution to a problem. Such events are exceptionally rare and planning policy sets demanding tests before consent will be granted. In such cases a detailed study is essential to justify applications. These studies will need to include vigorous and exhaustive investigation of alternative uses. Note that in law and policy, relocation is considered demolition — and the same exacting tests apply.

7.4.2 Recording In the event of consent being given to demolish all or part of a listed building or structure (or a historic structure in a conservation area), there will normally be a condition to record it with a survey and photographic record carried out by a specialist. In England, the specification for this will be agreed with the local archaeological service and Historic England, and the results should be deposited at the local Historic Environment Record. For buildings in Scotland the local authority will require the applicant to notify Historic Environment Scotland’s Threatened Buildings Survey to provide an opportunity of recording the building prior to its demolition. In Wales, the Royal Commission on Ancient and Historic Monuments in Wales should be notified for the same reason.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 88/130

7.4.3 Reclaiming and reusing materials Opportunities for saving and reusing elements of a building for which demolition is consented may be a condition of the consent. Regardless, they should be explored. Reclaimed materials and fittings can often be used to replace elements missing elsewhere in the Network Rail estate. In some cases, where there is no option but to remove a building from the site, total relocation within Network Rail’s estate or in a heritage railway or museum setting may be appropriate. Where materials are badly damaged, it may not be practicable to reuse or recycle them.


Document References

Heritage Definitions Legislation and Guidance Image Credits

A


Appendix A Definitions Heritage Definitions https://historicengland.org.uk/advice/hpg/hpr-definitions/

Abbreviated Terms CIS CMP DDCMS DfT FOC GDO GPDO GRIP HER HPA LBC ORR PTE RAM RHDAB TfL TOC TPO RHT WSI

Customer Information Screens Conservation Management Plan Department for Digital, Culture, Media and Sport Department for Transport Freight Operating Company General Development Order (applies in England and Wales) General Permitted Development Order (applies in Scotland) Governance of Railway Investment Projects Historic Environment Record Heritage Partnership Agreement Listed Building Consent Office of Rail and Road Passenger Transport Executives Route Asset Manager The Railway Heritage Designation Advisory Board Transport for London Train Operating Company Tree Preservation Order Rail Heritage Trust Written Scheme of Investigation

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 90/130


Appendix A Legislation and Guidance Technical and Regulatory Guidance: Railway Group Standard GI/RT7016 Issue 2 ‘Interface between Station Platforms, Tracks and Trains’ Rail Industry Standard RIS-7700-INS ‘Rail Industry Design Standard for Station Infrastructure’ Railway Group Standard GC/RT5212 ‘Requirements for Defining and Maintaining Clearances’ DfT — Accessible Train Station Design for Disabled People Code of Practice 2015 DETR — Guidance on the use of Tactile Paving Surfaces (under review 2015) A Guide to Overhead Electrification, Network Rail / Alan Baxter Associates, 2015 (can be requested from NR Principal Architect) Examination of the use of FRP for Station Canopy Fascia Daggerboards, Railway Heritage Trust/ Alan Baxter Associates, 2018 Rail Heritage Designation Network Rail Guide to: The principles of the conservation of historic buildings BS7913:2013 Network Rail Guidance Suite: Station Design Guidance, NR/GN/CIV/100/02, 2020 Redundant Signal Box Strategy NR/GN/CIV/400/06, 2020

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 91/130


Appendix A Legislation and Guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 92/130

English Legislation, Policy and Guidance: Planning (Listed Buildings and Conservation Areas) Act 1990

Building Regulations 2010

National Heritage Acts 1980, 1983, 1997 and 2002

Health and Safety at Work etc. Act 1974

Planning Act 2008

Public Health Act 1961

Enterprise and Regulatory Reform Act 2013

The Regulatory Reform (Fire Safety) Order 2005

Historic Buildings and Ancient Monuments Act 1953

Construction (Design and Management) Regulations 2015

Planning (Listed Buildings and Conservation Areas) Regulations 1990

VAT Notice 708: buildings and construction

Town & Country Planning Act 1990

National Planning Policy Framework 2019

Town & Country Planning (Development Plans) Regulations 1991

Planning Practice Guidance 2019

Town Country Planning (Control of Advertisements) (England) Regulations 2007

The National Heritage List for England

Transport and Works Applications (Listed Buildings, Conservation Areas and Scheduled Monuments Procedure) Regulations 1992

Historic Environment Records Historic England (HE), Protocol for the Care of the Government Historic Estate 2017

Town and Country Planning (General Permitted Development) (England) Order 2015 HE, Easy Access to Historic Buildings (2015) Town & Country Planning (Development Management Procedure) (England) Order 2015

HE, Understanding Historic Buildings: A Guide to Good Recording Practice 2016

Planning and Compulsory Purchase Act 2004

HE, Infrastructure: Transport Listing Selection Guide 2017

Ancient Monuments and Archaeological Areas Act 1979

HE, Managing Significance in Decision-Taking in the Historic Environment: Listed Buildings and Curtilage

Ancient Monuments (Class Consents) Order 1994


Appendix A Legislation and Guidance

Environment Good Practice Advice in Planning 2 2015 HE, Listed Buildings and Curtilage: Advice Note 10 2018 HE, The Setting of Heritage Assets: Historic Environment Good Practice Advice in Planning Note 3 (Second Edition) 2017 HE, Energy Efficiency and Historic Buildings: Draught-proofing windows and doors 2016 HE, Energy Efficiency and Historic Buildings: How to Improve Energy Efficiency 2018 HE, Conservation Principles, Policies and Guidance 2008 HE, Scheduled Monuments: a Guide for Owners and Occupiers 2013 HE, Making Changes to Heritage Assets: Advice Note 2 2016 English Heritage, Investigative Work on Historic Buildings 1994 (available to NBS subscribers) English Heritage, Scaffolding and Temporary Works for Historic Buildings 1995 (available to NBS subscribers) The Historic England website including: Heritage Protection Guides Heritage Definitions Building Regulations Compliance: Listed Buildings and Other Heritage Assets

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 93/130


Appendix A Legislation and Guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 94/130

Cadw publications and Welsh Legislation, Policy and Guidance: The Historic Environment (Wales) Act 2016

Town Country Planning (Control of Advertisements) Regulations 1992 with amendments

Planning (Wales) Act 2015 Planning (Listed Buildings and Conservation Areas) Act 1990 Planning (Listed Buildings and Conservation Areas) Regulations 1990

Transport and Works Applications (Listed Buildings, Conservation Areas and Scheduled Monuments Procedure) Regulations 1992 Town and Country Planning (General Permitted Development) Order 1995 with amendments

Planning Act 2008 Town and Country Planning Act 1990 The Town and Country Planning (Development Management Procedure) (Wales) (Amendment) Order 2016

Town & Country Planning (Development Management Procedure) Order 1995 with amendments Planning and Compulsory Purchase Act 2004 Planning Policy Wales Edition 10 2018

National Heritage Acts 1980, 1983, 1997 and 2002 National Development Framework 2019 Ancient Monuments and Archaeological Areas Act 1979 Enterprise and Regulatory Reform Act 2013 Historic Buildings and Ancient Monuments Act 1953 Environmental Protection Act 1990 Ancient Monuments (Class Consents) Order 1994 Building Regulations 2010 Health and Safety at Work etc. Act 1974 Public Health (Wales) Act 2017

Welsh Government Planning Policy Technical Advice Notes including: Technical Advice Note (TAN) 24: The Historic Environment 2017 Cadw, Heritage Impact Assessment in Wales 2017 Cadw, Managing Change to Listed Buildings in Wales 2017 Cadw, Managing Listed Buildings at Risk in Wales 2017 Cadw, Managing Conservation Areas in Wales 2017 Cadw, Managing Scheduled Monuments in Wales 2018 Cadw, Setting of Historic Assets in Wales 2017 Cof Cymru — National Historic Assets of Wales website The Cadw Historic Environment of Wales website


Appendix A Legislation and Guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 95/130

Scottish Legislation, Policy and Guidance: Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997

Historic Buildings and Ancient Monuments Act 1953

Historic Environment Scotland Act 2014

Building (Scotland) Amendment Regulations 2010

Planning (Scotland) Act 2019

Health and Safety at Work etc. Act 1974

Town and Country Planning (Scotland) Act 1997

Public Health etc. (Scotland) Act 2008

Town and Country Planning (Development Planning) (Scotland) Regulations 2008

Scottish Planning Policy 2014

Town and Country Planning (Control of Advertisements) (Scotland) Regulations 1984

Scottish Historic Environment Policy Statement 2016

The Town and Country Planning (General Permitted Development) (Scotland) Order 1992 (with amendments 2014)

Scottish Government Planning Advice Notes (PANs) including: Note 2/2011: Planning and archaeology

The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 Ancient Monuments (Class Consents) (Scotland) Order 1996

Historic Scotland INFORM: Information for Historic Building Owners notes Historic Environment Scotland (previously Historic Scotland) Managing Change in the Historic Environment guidance notes including:

Fire (Scotland) Act 2005 Guidance on Conservation Areas 2019 National Heritage (Scotland) Act 1985 Guidance on the Principles of Listed Building Consent 2019 Natural Heritage (Scotland) Act 1991 Asset Management 2019 Ancient Monuments and Archaeological Areas Act 1979 Engineering Structures 2010 Building (Scotland) Acts 1959, 1970 and 2003 Use and Adaptation of Listed Buildings 2019 Enterprise and Regulatory Reform Act 2013 Setting 2016


Appendix A Legislation and Guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 96/130

Works on Scheduled Monuments 2016

Other Published Works:

Scottish Government Planning Circular 2/2015: Consolidated Circular on Non-Domestic Permitted Development Rights 2015

Conservation, RIBA Plan of Work 2013 Guide, Hugh Feilden Understanding Historic Conservation, Michael Forsyth 2007

SG NPPG 5: Archaeology and Planning 1994 Historic Scotland, Conservation of Architectural Ancient Monuments in Scotland 2001

Living Buildings, Architectural Conservation: Philosophy, Principles and Practice by Donald Insall 2018 New design for Old Buildings, Roger Hunt & Iain Boyd SPAB 2017

National Records of Scotland Research Guides: Buildings The SPAB Approach to the Conservation and Care of Buildings, Matthew Slocombe National Records of Scotland Research Guides: Railway Records The Historic Environment Scotland website including: Grants and Funding Guides for Practitioners & Technical Advice Notes

English Heritage Practical Building Conservation Series 2013 The Heritage Fund Conservation Planning Guidance Conservation of Georgian Houses by A Davey, R Heath, D Hodges, R Milne, M Palmer, 4th edition, 1995 Informed Conservation - Understanding historic buildings and their landscapes for conservation by Kate Clark 2001 Practical Building Conservation (5 Vols) by J Ashurst and N Ashurst 1988/2011 Emergency Repairs for Historic Buildings by Eleanor Michell 1988 The Repair of Historic Buildings: Advice on Principles and Methods by Christopher Brereton 1991 Conservation of Historic Buildings by Bernard M Feilden 2003 Historical Structural Steelwork Handbook by W Bates 1984 (available for .pdf download from www.steelconstruction.org)


Appendix A Legislation and Guidance

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 97/130

National Trust Manual of Housekeeping 2011

Conservation of Timber Buildings by F W B Charles and Mary Charles 1995

Modern Practical Masonry by E G Warland 2006

Practical stone masonry by P R Hill and J C E David 1995

Looking after antiques by Frances Halahan and Anna Plowden 1999

Repair of Ancient Buildings by A R Powys (1929) SPAB Third Edition 1995

Tree Roots and Buildings by D F Cutler and I B K Richardson 1989

Building Pathology: Principles and Practice, David Watt 2007

Heritage under Fire: A Guide to the Protection of Historic Buildings (Fire Protection Association) 1995 Conservation of Building and Decorative Stone by John Ashurst and Frances G Dimes 1998 Mechanical and Electrical Systems for Historic Buildings by Gersil Newmark Kay 1992 Timber Decay in Buildings: Decay, Treatment and Conservation: The Conservation Approach to Treatment by Brian Ridout 2000 Conservation repair and treatment of timbers in historic buildings – Paper 6 of the 1992 British Wood Preservation and Damp-proofing Convention by C J D George and A D Mountford 1992 Conservation of Clay and Chalk Buildings by Gordon T Pearson 1992 Fire protection measures for the Royal Palaces, Report by Sir Alan Bailey 1993 Management Guidelines for World Cultural Heritage Sites by Bernard M Feilden and Jukka Jokilehto 1993 Cleaning Historic Buildings (2 Vols) by Nicola Ashurst 1994


Appendix A Legislation and Guidance

Publications about Railway Buildings: London Termini by Alan A Jackson 1985

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 98/130

Further Information: Further information is to be found in publications by the British Standards Institution, the Building Research Establishment, the Lead Development Association and the Stone Federation.

The Railway Heritage of Britain by Gordon Biddle and O S Nock 1983

The Oxford Companion to British Railway History edited by Jack Simmons and Gordon Biddle 1999

Conservation Guides are also available from Historic England, Historic Environment Scotland, Cadw, The Georgian Group, The Victorian Society and The Society for the Protection of Ancient Buildings. Some Railway Heritage Groups also publish guides to certain building types such as signal boxes, bridges and stations related to particular railway companies or geographical areas.

Railways as World Heritage Sites by Anthony Coulls (contributions by Colin Divall and Robert Lee) 1999 (available as a .pdf file to download from www.icomos.org)

Many local authority planning departments also produce their own free guides to the management, repair and alteration of listed buildings; the relevant guide should be consulted in each case.

Civil Engineering Heritage: various authors for the Institution of Civil Engineers from 1981

For more detailed research see:

The Directory of Railway Stations by R J V Butt 1995

Britain’s Historic Railway Buildings, Gordon Biddle, 2011

→ http://www.buildingconservation.com/

21 Years of the Railway Heritage Trust, Railway Heritage Trust, 2007

→ Institute of Building Conservation

Glasgow Central Station Through Time, Michael Meighan, 2013

→ Institute of Conservation (for objects, not buildings)

Station Colours, Peter Smith, 2016

→ The Heritage Alliance

British Rail Architecture 1948-97, David Lawrence, 2018 Britain’s 100 Best Railway Stations, Simon Jenkins, 2017 Britain’s Historic Railway Buildings — a gazetteer of Structures and Sites’, Ian Allan and RHT, 2011


Appendix A Image Credits

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 99/130

Page Image:

Section 3

Page

Image:

0.1 © Paul Childs, Railway Heritage Trust

Section 1

06

Page

Image: 1.1 © Paul Childs, Railway Heritage Trust 1.2 © Weston Williamson + Partners, Max Breese 1.3 © Paul Childs, Railway Heritage Trust

Section 2

08 09 12

3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12

© Network Rail Media Centre, Adam Parker © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Noel Walley / Wikimedia Commons / CC BY-SA 3.0 © Paul Childs, Railway Heritage Trust © Weston Williamson + Partners © Weston Williamson + Partners © Paul Childs, Railway Heritage Trust © Robert Thornton © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust

22 23 25 26 28 29 30 31 35 36 37 38

19 20

5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9

© Network Rail Media Centre, Adam Parker © Historic England Archive © City of London © Tim Green / flickr / CC BY 2.0 © Weston Williamson + Partners © Alan Baxter Ltd. © Network Rail Media Centre, Adam Parker © Network Rail, Boaz Yariv © Robert Thornton

Section 6

52 53 54 55 56 57 60 61 62

Page

Image:

Page

14 15 16 17 18

Page

Image:

Section 4

Page

Image: 2.1 © SR Photies / flickr / CC BY-SA 2.0 2.2 © Paul Childs, Railway Heritage Trust © Weston Williamson + Partners 2.3 © Paul Childs, Railway Heritage Trust 2.4 © Ellievking1 / Wikimedia Commons / CC BY-SA 4.0 2.5 © Network Rail Media Centre 2.6 © Network Rail Media Centre

Section 5

Image: 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8

© Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Network Rail Media Centre © Paul Childs, Railway Heritage Trust © Network Rail Media Centre, Adam Parker © mike138 / flickr / CC BY-ND 2.0 © Colin / Wikimedia Commons / CC BY-SA 4.0 © Alan Baxter Ltd.

40 41 43 44 45 46 47 49

6.1 © Paul Childs, Railway Heritage Trust © Weston Williamson + Partners, Max Breese 6.2– 6.14 6.15 © Paul Childs, Railway Heritage Trust

64 65 –78 80


Appendix A Image Credits

Section 7

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 100/130

Page

Image: 7.1 © Paul Childs, Railway Heritage Trust 7.2 © Network Rail Media Centre, Kieran Dodds 7.3 © Weston Williamson + Partners, Max Breese 7.4 © Ed Webster / flickr / CC BY 2.0 7.5 © Network Rail Media Centre 7.6 © Paul Childs, Railway Heritage Trust 7.7 © Paul Childs, Railway Heritage Trust 7.8 © Network Rail Media Centre

Appendices

82 83 84 85 85 86 87 87

Page

D.21 D.22 D.23 D.24 D.25 D.26 D.27

© Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust

127 128 128 129 129 130 130

Inside Cover Images Front

King’s Cross station, Eastern Range detail © Network Rail Media Centre, Adam Parker

Back

King’s Cross station, platform clock © Network Rail Media Centre, Adam Parker

Image: C.1 C.2 D.1 D.2– D.7 D.8 D.9 D.10

© Paul Childs, Railway Heritage Trust © Paul Childs, Railway Heritage Trust © Network Rail Media Centre © Alan Baxter Ltd.

© Railway Heritage Trust © Network Rail Media Centre, Adam Parker © DAVID ILIFF / Wikimedia Commons / CC BY-SA 3.0 D.11 © Network Rail Media Centre, Adam Parker D.12 © Network Rail Media Centre, Adam Parker D.13 © Network Rail Media Centre, Adam Parker D.14 © Railway Heritage Trust D.15 © 2012 SilverTiger D.16– © Weston Williamson+Partners, Max Breese D.19 D.20 © Railway Heritage Trust

106 110 112 113 –118 119 119 120 121 122 122 123 123 124 –126 127

This document was produced on behalf of Network Rail by Weston Williamson + Partners in partnership with Alan Baxter.


Processes

Heritage GRIP Process Diagram Project Manager’s Heritage Checklist

B


Appendix B GRIP Process Diagram

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 102/130

Engineer/architect led

Contractor shadowing

GRIP 2 FEASIBILITY

GRIP 3 OPTIONS SELECTION

GRIP 4 SINGLE OPTION DEVELOPMENT

GRIP 5 DETAILED DESIGN

CAT 2/3 Check

PRE-APP CONSULTATION STAGE 2

PRE-APP CONSULTATION STAGE 1

LISTED BUILDING CONSENT APPLICATION

3 months

DISCHARGE CONDITIONS

Stage 2: Construction Issue

Stage 1: Design Basis

HERITAGE ASSESSMENT

GRIP 1 DEFINE OUTPUTS

Contractor led (GRIP 4 designer retained)

2 months

GRIP 6 CONSTRUCTION, TEST COMMISSION

GRIP 7 HAND BACK

GRIP 8 PROJECT CLOSE


Appendix B Project Manager’s Heritage Checklist

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 103/130

GRIP STAGE 1. Output Definition

Have you done an Initial Baseline Review of history and heritage/landscape significance of the route or place?

Have you procured all the necessary survey information and decided on key parameters (such as wire heights and track levels)?

Is visual quality included as a design criterion in the Project Specification?

Have you had Pre-application discussions with the LPA and HE/Cadw/HES? Have they agreed to the selected option?

Have you documented your thought process and decisions? 2. Feasibility

Have you reviewed and liaised with HE/Cadw/HES about updating heritage designations? Have you done an initial heritage risk assessment? Have you consulted the Railway Heritage Trust? Have you documented your thought process and decisions?

3. Option Selection

Does the design contractor CRT clearly and in detail specify necessary heritage / planning outputs (reports, drawings and visualisations, attendance at pre-app, etc.)? Does the option selection provide the right comparative information on rejected options to allow heritage stakeholders to sign up to the preferred option?

Have you documented your thought process and decisions? 4. S ingle Option Development

Does the design contractor CRT clearly and in detail specify necessary heritage / planning outputs (reports, drawings and visualisations, attendance meetings, etc.)? Are they properly briefed? Does the designer have the right heritage and/ or architectural resource? Have you co-ordinated the design interfaces? Have you allowed enough time for the design and consents process, including the discharge of any conditions? Have you got RAM and ToC sign-off for your proposals? Have you consulted key heritage stakeholders, national and local, including the Railway Heritage Trust? Do they support your proposals?


Appendix B Project Manager’s Heritage Checklist

GRIP STAGE 4. Single Option Development

Have you checked that the designs comply with relevant standards, loadings, etc.? Have you budgeted for/sourced any necessary materials, such as stone? Have you documented your thought process and decisions?

5. Detailed Design

Does the detailed design follow exactly what you have got consent for? Have you discharged all the precommencement consent conditions, e.g. providing samples of materials or making a record of the structure? Have you documented your thought process and decisions?

6. Construction Test and Commission

Does the contractor have the necessary conservation skills in their workforce? Does the contractor understand the requirement to build in exact compliance with the listed building consent? Has the work been carried out to the required standard and in exact compliance with the listed building consent? Have all planning conditions been discharged?

8. Project Close Out

Are you ready to run another heritage-related project?

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 104/130


Contacts and Awards

Heritage Network Rail Contacts and Useful Addresses National Records Centre The Railway Heritage Trust Awards

C


Image C.1 Ramsgate station, Grade II listed


Appendix C Network Rail Contacts and Useful Addresses

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 107/130

Network Rail — York Audax National Records Centre:

Network Rail Architectural and Town Planning advice can be obtained from: Network Rail Technical Authority — Architecture and Design Advice

AskTheArchivist@networkrail.co.uk

Name

Title

Contact

Frank Anatole Boaz Yariv Trevor Wilson Kaine Osakwe

Principal Architect Senior Architect Senior Architect Architectural Assistant

@networkrail.co.uk @networkrail.co.uk @networkrail.co.uk @networkrail.co.uk Useful Addresses: Historic England https://historicengland.org.uk

Network Rail — Town Planning Legislation Guidance Name

Department or Role

Contact

Tom Higginson Colin Field Sandra Hebenton Tony Rivero Jill Stephenson Steven Taylor

Head of Town Planning Senior Town Planner — Western & Wales Senior Town Planner — Scotland Senior Town Planner — LNE Senior Town Planner — LNW Senior Town Planner — Southern, Anglia & Wessex

@networkrail.co.uk @networkrail.co.uk @networkrail.co.uk @networkrail.co.uk @networkrail.co.uk @networkrail.co.uk

Historic Environment Scotland https://www.historicenvironment.scot Cadw, Welsh Government https://cadw.gov.wales The Georgian Group https://georgiangroup.org.uk The Victorian Society https://www.victoriansociety.org.uk

Network Rail — Land Information (Property) Name

Department or Role

Contact

The Twentieth Century Society https://c20society.org.uk

Jim Stewart Rebaz Salar

Geospatial Data Manager Geospatial Surveyor

@networkrail.co.uk @networkrail.co.uk

Society for the Protection of Ancient Buildings https://www.spab.org.uk


Appendix C National Records Centre What is the National Records Centre Network Rail’s National Records Centre is the organisation’s central repository for millions of engineering drawings, from the very earliest days of the railway to today’s renewal and development schemes. We also hold land and property deeds and agreements that may also be useful in researching historic stations and structures. How to access it For research you can request information through the Ask the Archivist service: → in your initial enquiry please give us as much information about your project as possible → Our catalogues are vast and there may be tens of thousands of records relating to a structure, with varying degrees of cataloguing descriptions, so please also be as specific as you can → ELR references and structure numbers always help → We will search our catalogues and let you know what drawings and documents we have. If there are items of interest, we will send you electronic copies for information in the first instance The Ask the Archivist service can be contacted via: askthearchivist@networkrail.co.uk and on My Connect: https://networkrail.sharepoint.com/sites/myconnect/routeservices/Pages/ CorporateArchive.aspx For access to current records relating to railway infrastructure please follow the National Record Group’s standard processes. Please contact: NRGenquiries@networkrail.co.uk or via My Connect: https://networkrail.sharepoint.com/sites/myconnect/routeservices/Pages/NRG. aspx

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 108/130

Be aware Be aware that the historical railway record is widely dispersed, and collections are often split between different repositories. For example, Network Rail may hold the original engineering drawings for a structure while the contract, accounts and business administration forming the context to those drawings may well be held elsewhere. Network Rail may also only have access to microfilm copies of drawings because the originals are held elsewhere or sometimes have not survived. Other sources of drawings Additional and related information can be found in repositories such as The National Archives, the National Records of Scotland, local county record offices, the National Railway Museum as well as railway history societies. We will give you pointers as to where other relevant archives might be held.


Appendix C The Railway Heritage Trust The Railway Heritage Trust is a company limited by guarantee and owned by its directors. It was formed in 1985, and is sponsored by Network Rail and Highways England’s Historical Railways Estate, which is the successor to BRB (Residuary) Ltd. However, the RHT is independent of both bodies. The RHT’s scope of activity is → nationally listed buildings and structures, or buildings and structures in a conservation area, → that are owned by Network Rail or Highways England (Historical Railway Estate). The RHT has two objectives, to give grants to: 1.

improve the heritage features of buildings and structures that are in its scope, and to

2. help find new uses for such buildings and structures when they no longer have operational use on the railway. In addition to awarding grants, the RHT also achieves its objectives by giving advice or comment when required. The RHT has awarded 1,825 grants, to a total value of almost £60 million, in its 35 years of existence. It has a current turnover of some £2.7 million a year, 90% of which is awarded as grants. You can find more details of the RHT, how it works, and past projects it has supported, at www.railwayheritagetrust.co.uk or you can contact by email at rht@railwayheritagetrust.co.uk

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 109/130


Appendix C Awards Several awards recognise and publicise good design and care for the architectural heritage. They include annual awards from the Civic Trust, Royal Institute of British Architects, Royal Incorporation of Architects in Scotland, RICS Building Preservation Awards and Europa Nostra. Specific awards that relate to railways include National Railway Heritage Awards, the Brunel Awards and the Best Station Award. Network Rail Architects may be contacted for further advice on submitting suitable projects.

Image C.2 Awards are not only for large scale projects. This faithful restoration of railings at Newcastle Central station achieved a National Railway Heritage Award in 2011

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 110/130


Case Studies

Heritage Great Western Main Line Electrification King’s Cross Station High Level Bridge New Uses for Old Rooms

D


Image D.1 High Level Bridge, Newcastle upon Tyne


Appendix D — Case Study 1 Great Western Main Line Electrification

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 113/130

The electrification of the Great Western from London to Cardiff required obtaining dozens of listed building consents for works to stations, overbridges, tunnels and viaducts, many designed by Brunel. Throughout the project, the design team worked hard to challenge Standards and to develop new designs to satisfy operational and safety requirements while meeting the criteria for successful listed building consent applications. The extensive use of specialist heritage advice and early and continued dialogue with local authorities, Historic England and Cadw was essential to containing planning risk.

Image D.2 Guide to Overhead Electrification

Image D.3 Statement of History and Significance of the Great Western Main Line


GLOUCEST LOUCESTER OU GLOUCESTER

Keynsham Hams Underbridge (II) [11403]

Pixash Lane Overbridge (II) [11263]

Middle Hill Tunnel Middle Hill Tunnel West Portal (II*) East Portal (II*) [10148] [10139]

Green Overbridge Overbridge (II) [9304] Culvert (II) [11428]

Saltford Tunnel West Portal (II) [11168]

Stony Lane Overbridge (II) [10934]

Sydney Gardens Overbridge (II*) [10610]

World Heritige Site Boundary

St. James’s Viaduct (II*) [10678 - 10704]

Bath Spa Station (II*) [10671 ]

CHIPPENHA M

Box Tunnel East Portal (II) [9912]

Hampton Mill Lane Overbridge (II) [10456]

Box Tunnel West Portal (II*) [10078]

Sydney Gardens Footbridge (II*) [10614]

Highnams Underbridge (II) [11115] Underbridge near Box Road (II) [10364]

Sydney Wharf (Raby Villas) Overbridge (II) [10622]

Clay Overbridge (II) [11226] St James’s Railway Bridge (II) [10661]

Swindon Road Overbridge (II) [8137]

Potley Lane Overbridge (II) [9850]

BATH

By Brook Underbridge (II) [10162]

Bathwick Covered Way (Raby Villas and Bathwick Terrace Tunnels) (II) [10624]

Skew Bridge (II) [10675] Bellotts Road Overbridge (II) [10810]

Avon Mill Lane Underbridge (II) [11350]

Stone Wharf Underbridge (II) [11042]

Beckford Road Overbridge (II) [10605]

Brook Road Overbridge (II) [10776]

Swindon Railway Village: 63 listed buildings

Former Moulsford Station, hotel and cottages Hotel (2 x II)

DIDCOT PARK WAY

Moulsford Viaduct (II*) [4727]

G Viad

Swindon Station Stone Building (Platform 2&3) (II) [7723]

Pangbourne St Underbridge

Meadow Lane Overbridge (II) [10515]

Retaining Wall between railway and canal (II) [10565 - 10605]

Sydney Road Overbridge (II) [10618]

Twerton Viaduct (II) [10829 - 10854]

Twerton (Short) Tunnel West Portals (II*) [10873] Twerton (Short) Tunnel East Portal (II*) [10870]

Listed Structure

Sydney Gardens Retaining Wall (II*) [10605 - 10618] Sydney Gardens Dwarf Balustrade Wall (II*) [10605 - 10618]

Steventon Overbridge (II) [5638]

Railway Works entrance subway (II) [7751]

London Road Overbridge (II) [10116]

St Anne’s Park No.2 Tunnel East Portal (II*) [11641]

Appleford Road Bridge (II) [DCL 5518]

SWINDON

Huntsmill Road Overbridge (II) [8333]

Bristol TempleMeads (I) [11831]

River Chew Underbridge (II) [11354]

Twerton Wood Tunnel East Portal (II*) [10903]

Former GWR Locomotive & Carriage Works: 16 listed buildings

Chipping Sodbury Vent Shafts x 6 (II)

BRIS TOL TEMPLE MEADS

St Anne’s Park No. 2 Tunnel West Portal (II*) [11648]

Overbridge near Dauntsey Overbridge (II) [8830]

Bath Road (A4) Underbridge (II) [9504]

Chipping Sodbury Tunnel East Portal (II) [SWB 10348]

BRIS TOL PARK WAY

Steventon Railway Cottages (2 x II)

Roman Road Overbridge (II) [7508]

River Avon Bridge (I) [11725]

Bristol & Exeter House Bristol Temple (II*) Meads Old Station (I)

Twerton Wood Tunnel West Portal (II*) [10915]

Dauntsey Road Overbridge (II) [8849]

Chipping Sodbury Tunnel East Portal (II) [SWB 10106]

Severn Tunnel English Portal (II*) [BSW 1208]

Culham Station (II*) [DCL 5618] Bourton Church Overbridge (II) [7169]

New Road Viaduct (II*) [9409]

Newport Old Tunnel (II) [SWM2 15871]

CARDIFF

Culham Station Overbridge (II) [DCL 5616]

Bourton Overbridge (II) [7215]

Saltford Tunnel East Portal (II) [11157]

Fox’s Wood Tunnel West Portal (II*) [11624]

II) [SWM2 17027]

Th Ov [DC

Chippenham Station (2 x II) [9376] River Avon Viaduct (II) [9077]

Durley Lane Underbridge (II) [11439]

NEWPOR T

OXFORD

STROUD STROU ST TROUD OUD UD

Bath Road Overbridge (II) [10175]

Bathford Road Underbridge (II) [10403]

NEWBUR Y Rockingham Road Overbridge (II) [BHL 5333]


Key Listed Structure Gatehampton Viaduct (II) [4402]

Structure Name Listing Grade For operational railway structures, the structure number (if MLN1, number only, otherwise preceded by ELR)

hame Lane verbridge (II) CL 5654]

Transfer Shed (II)

Y

Engine Shed (II)

Coaling Stage (II) Maidenhead Railway Bridge (I) [2327]

Silly Bridge Overbridge (II) [4779]

Westbourne Bridge (II) [0033]

Dumb Bell Underbridge (II) [2263]

Southbury Lane Overbridge (II) [3035]

PADDINGT ON

Reading Station (II) [3574]

Gatehampton duct (II) [4402]

Hanwell Station (II) [0727] Leigh Road Overbridge (II) [1974]

READING

Paddington Station (I) [0000] also: Mint Wing Stables (II); Station Hotel (II)

tation Road e (II) [4137] London Road Overbridge (II) [3346]

Viaduct (I) [0742] St Mary’s Road Overbridge (II) [1668] Slough Station (II) [1832]

Bath Road Bridge (II) [BKE 3729]

River Kennet Bridge II[3479]

Tilehurst Road Overbridge (II) [BKE 3709]

GWML

GWML Listed Structures 1515/614 February 2013

Image D.4 Listed Structures Route Map

NTS

Alan Baxter ©COPYRIGHT


Appendix D — Case Study 1 Great Western Main Line Electrification

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 116/130

Images D.5 Maidenhead bridge before and after

A special CHS OLE portal was designed to minimise the visual impact of electrification on Brunel’s famous Grade I bridge over the Thames at Maidenhead. Variations on the design were used at Gatehampton and other bridges and viaducts. Consent was granted on time because of a willingness to adopt a non-standard design and the employment of a heritage specialist to lead extensive negotiation with the local authorities and English Heritage.


Appendix D — Case Study 1 Great Western Main Line Electrification

Overbridges were the most common type of listed structure affected by electrification. By challenging the accepted Standard for overbridge parapets on electrified railways, NR’s design team developed a railing with inbuilt mesh which could be modified to suit the many individual overbridges along the route. A number of mock ups were created for the benefit of planning authorities. Problems were initially encountered because contractors did not at first have the resources, experience or expertise to prepare listed building consent applications — requiring a level of detail at an earlier GRIP stage and the production of drawings, reports and visualisations not normally required for bridge works.

Images D.6 GWEP bridge before and after

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 117/130


Appendix D — Case Study 1 Great Western Main Line Electrification Images D.7 Cardiff station before and after

The canopies at Grade II listed Cardiff Central Station was carefully cut back and remodelled so that the change is imperceptible. Standard OLE Series 1 masts were used, but care was taken to minimise the number of different types of structure and to position them regularly in order to minimise their visual impact on the station. The process was assisted by the quality of drawings and visualisations provided by the contractor. Cardiff (and other stations such as Stirling) demonstrate that standard NR designs and products may be acceptable at listed stations, if they are employed flexibly and intelligently with specialist advice about the significance of the station and how to respond to it.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 118/130


Appendix D — Case Study 2 King’s Cross Station King’s Cross Station is one of only 6 grade I listed operational stations in England. Designed by Lewis Cubitt and opened in 1852 as the flagship of the Great Northern Railway, it has a strikingly powerful and lean design that creates a fascinating contrast to the full-blown Gothic of neighbouring St Pancras. By the late 1990s, however, the purity of Cubitt’s concept had been lost under 150 years of accretive change, most infamously the temporary concourse built across the front that lasted for 40 years, not 5.

Images D.8 and D.9 King’s Cross station with temporary concourse in front (below) and with new public space following 2012 redevelopment (right)

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 119/130


Appendix D — Case Study 2 King’s Cross Station

The acclaimed transformation of the station completed in 2012 to the plans of John McAslan + Partners has won numerous awards. Dramatic improvements to passenger facilities and the capacity of the concourse and the creation of a new public open space has been achieved by restoring and celebrating the 1850s design. Working with the right architect Choice of architect — and crucially, their scope — is essential to achieving quality and a smooth consents process. In this instance John McAslan + Partners had the combination of the necessary understanding of complex stations and their planning and the technical conservation skills to restore the grade I fabric. Perhaps more importantly, they were retained beyond GRIP 3 to work with the contractor and ensure — at the insistence of English Heritage — that the detail of the consented scheme was carried through into construction. All too often, the quality of an architectural idea is lost in the process of value engineering under a design and build contract. King’s Cross demonstrates what the success that can be achieved by retaining the concept architect.

Image D.10 View of trainshed from Platform 8, prior to refurbishment

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 120/130


Appendix D — Case Study 2 King’s Cross Station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 121/130

Working with the Railway Heritage Trust Time and again the RHT is able to bridge a funding gap and realise the finishing touches that make a big impact on the overall presentation and reception of projects but are otherwise outside project scope. At Kings Cross the RHT funded a number of individual projects including a new war memorial and restored station clock. But perhaps its greatest achievement 40% matching funding to replace the 1970s OLE portals with headspans, which effectively makes the OLE disappear, so that the superb restoration of the trainsheds can be enjoyed without interference.

Image D.11 View of trainshed from Platform 8, prior to refurbishment


Appendix D — Case Study 2 King’s Cross Station

Working with ‘the grain’ of the building For historic structures, the best results — and the easiest to secure consent for — are achieved by understanding and working with the original design concept. Here, restoring the historic operating diagram — passenger arrivals on the west side and departures out of the southern end — was key to unlocking the scheme, enabling the existing concourse to be removed, the station façade to be restored and a new square created in front.

Images D.12 and D.13 New concourse at west side of station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 122/130


Appendix D — Case Study 2 King’s Cross Station

Image D.14 Booking Hall prior to 1970s ‘temporary’ concourse

Working in partnership with planning stakeholders A lesson from stakeholders was the close and constant collaboration between the project and the planning authority (the Borough of Camden) and English Heritage was vital to the effective delivery of what was a highly complex planning and consents situation. Regular meetings throughout the project built trust and solved problems, so there were fewer surprises, and less planning risk.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 123/130

Image D.15 Ticket office returned to prior location

The culmination of this approach was the signing of the network’s first Heritage Partnership Agreement after the completion of the project. The station manager reported this agreement saved the need to apply for around 40 listed building consent applications in the first year of its operation alone (see section 4.4 for more detail).


Appendix D — Case Study 3 High Level Bridge Robert Stephenson’s High Level Bridge is one of the most imposing and original creations of the railway age. Imposing, because of its height and span a cross the Tyne gorge. Original, because it is a double decker, with a road deck suspended beneath the rail deck, between tied iron arches. It is little surprise that the 1840s structure is listed at Grade I. By the turn of the millennium the structure was 150 years old and in need of significant repair. Following a £42m project with Network Rail, Mott MacDonald and May Gurney, the bridge emerged in 2008 repaired and strengthened for decades of further use. Central to the success of the multi award-wining project was a commitment to research and development. The bridge was subject to a visual condition inspection and non-destructive testing of 57,000m2 of cast and wrought iron. Full-scale fatigue testing of structural components was also undertaken in conjunction with the University of Manchester, to understand the performance of the cast iron.

Image D.16 View of the Tyne river and High Level Bridge

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 124/130


Appendix D — Case Study 3 High Level Bridge

The importance of properly analysing the nature of a historic structure in order to understand the underlying causes of the defects is all the more important than with more modern structures because of the lack of technical information and the vagaries of Victorian manufacturing and construction techniques. Modern standards and codes will mostly not apply. In this instance, this approach alleviated the need for extensive strengthening of the rail deck that might otherwise have been required by a more conventional design process - a demonstration that a recognition that historic structures should be evaluated differently can lead to savings in both budget and programme. Research was not limited to structural performance but combined with restoration of lighting and paint schemes, with the result that the bridge’s appearance was greatly improved. All of this was achieved by close collaboration with the local authorities, England Heritage and the Railway Heritage Trust.

Image D.17 Road deck on the High Level Bridge

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 125/130


Appendix D — Case Study 3 High Level Bridge

Image D.18 Pedestrian walkway next to the road carriageway

Image D.19 View of the rail deck from the Gateshead side of the High Level Bridge

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 126/130


Appendix D — Case Study 4 New Uses for Old Rooms

Image D.20 Disused former first class dining room and Sheffield Midland station

Over the past half century, significant changes to the way that stations are managed, manned and operated have left rooms and buildings across the network underused, neglected or abandoned. This presents both a risk — that condition will deteriorate to a point where expensive repairs to listed buildings are required — and an opportunity — to put redundant spaces to beneficial new uses.

Image D.21 Sheffield Tap, located in the former first class dining room and Sheffield Midland station

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 127/130


Appendix D — Case Study 4 New Uses for Old Rooms

Image D.22 Gallery space created at Middlesbrough station, external view

For the last twenty years, the Railway Heritage Trust has recognised these issues and in partnership with Network Rail, TOCs, local authorities, charities, businesses and community groups it has funded many dozens of successful schemes to restore and transform abandoned space across the country into a wide range of new uses. As this small sample illustrates, the results create value in many different ways: improving passenger facilities, generating new revenue and providing much-needed facilities for Network Rail’s partners and the communities it serves.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 128/130

Image D.23 Gallery space at Middlesbrough station, internal view

One of the most successful concepts is the ‘station tap’ pubs created in a series of stations, often exploiting the splendid architecture of former refreshment rooms to create highly successful businesses that also provide improved passenger facilities. The previous page shows the opulent former first class dining rooms at Sheffield Midland Station.

The RHT has frequently supported stations over multiple projects, where the needs are great. An example is Middlesbrough, where in addition to fabric repairs and passenger facilities grant aid has supported the creation of studios and galleries for Platform Arts Ltd. Artists space has been created at a number of stations with RHT investment.


Appendix D — Case Study 4 New Uses for Old Rooms

Image D.24 Leamington Spa waiting room before refurbishment

Waiting rooms are another frequent beneficiary: either refurbished with improved facilities in historically sympathetic ways, such as Leamington Spa, or brought back into use as here at Inverurie by conversion to a café and coffee bar.

Image D.25 Leamington Spa waiting room after refurbishment

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 129/130


Appendix D — Case Study 4 New Uses for Old Rooms

Image D.26 Converted rooms the local Historical and Archaeological Society at Littleborough station

Many schemes are architecturally modest, but provide vital support to charities and communities. Two examples from Lancashire are Bamber Bridge, where parts of the 1840s station building were converted for use by the local Pensioners’ Association and, Littleborough, where the redundant interiors were restored to house the collections and meeting space of the local Historical and Archaeological Society.

Heritage: Care and Development Strategic Planning NR/GN/CIV/100/05 July 2020 130/130

Image D.27 Rooms converted into a training facility at Harwich Town station

The RHT can help find uses for whole station buildings. Harwich Town Station building and goods shed were both empty and unused until the RHT funded their refurbishment and conversion into offices, training facilities and workshops for the Harwich Mayflower Project.



100/

05


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.