OUTLINE SPECIFICATIONS:
1. basement-mechanic room foundation: 1'x 2' grade beam running flush with top of pile caps with 4 -#5 reinforcement bars bottom and 3 -#5 reinforcement bars top connecting pile caps RETAINING WALL: 10" thick cast in place concrete wall with -2 #5 vertical reinforcement bars 12" o.c. hot rubberized asphalt membrane at exterior drainage mat r10 rigid insulation footing drainage pipe FLOOR: granular fill to b.o vapor retarder sheeting 2 feet r-10 insulation on perimeter 6 1/2 inch sturcture concrete slab on grade INTERIOR WALL: 5/8 inch gypsum board 4 inch metal stud 5/8 inch gypsum board
2. EXTERIOR BICYCLE PARKING GARAGE FLOOR: 4 inch concrete topping slab r-21 rigid insulation (sloped to drain) protection sheet hot rubberized asphalt membrane with fabric reinforcement 5 1/2 inch site cast concrete slab on composite metal deck w10x45 steel column
3. MAIN LEVEL-OFFICE ROOM FLOOR: floor finishing-carpet 5 1/2 site cast concrete slab on 3 inch composite metal deck w12x16 steel beam EXTERIOR WALL: alluminum wall metal siding breathable wall membrane 1/2 inch plywood sheathing 6 inch metal stud (8 inch at braced frame) at 16 inch o.c. r13 batt insulation fillin 5/8 inch gypsum board mechanic louver CEILING: hanging acoustic ceiling tiles
4. UPPER LEVEL-STUDY ROOM FLOOR: floor finishing-carpet 5 1/2 site cast concrete slab on 3 inch composite metal deck w16x36 steel structure beam r13 batt insulation 5/8 inch steel furring channel EXTERIOR WALL: alluminum wall metal siding breathable wall membrane 1inch z channel 3/8 inch r3.8 insulation sheathing 8 inch metal stud at 16 inch o.c. r13 batt insulation fillin 5/8 inch gypsum board vapor retarding primer inverse chevron diagnal bracing WINDOW
5. lower roof assembly single ply pvc membrane 1/4 inch overlayment board r21 rigid insulation vapor barrier 1 1/2 inch corrugated metal deck slopped w12x26 steel beam
6. upper roof assembly single ply pvc membrane 1/4 inch overlayment board r21 rigid insulation vapor barrier 1/4 inch underlayment board 1 1/2 inch perforated metal deck w10x15 steel beam
CONIBEAR SHELL HOUSE M I L L E R H U L L A R C H I T E C T S N.ST.JOHN E.LORTZ
N
6"
1'
2'
4'
SCALE: 3/4" = 1'-0"
J.COSTELLO Y.MENG
P.JACOBITTI
8'
GROUND FLOOR: 4 inch crushed stone 1 inch rigid board insulation vapor barrier 4 inch site cast concrete slab on grade with steel wire meshed reinforcement INTERIOR WALL: 8 inch x 8 inch x 16 inch cmu block CHIMNEY: Foundation at fireplace: 5 feet 8 inch x 5 feet 8 inch x 12 inch thickness site cast concrete footing with 8 #5 reinforcing bars(bottom) e/w and 10 #5 reinforcing bars(bottom) n/s 8inch x 8inch x 16inch cmu block walls below grade CHIMNEY WALLS AT LOWER LEVEL: 8 inch x 8 inch x 16 inch cmu block outer wythe 2 inch x 4 inch x 8 inch fire brick 8inch reinforced concrete lintel parge smooth smoke chamber w/ concrete infill clay flue lining CHIMNEY WALLS AT UPPER LEVEL: 4 inch x 8 inch x 8 inch cmu block Clay flue lining FIRST FLOOR: 1/2 inch gypsum board ceiling 2 inch x 10 inch plywood web i-joist framing at 16 inch o.c sound insulation 1and 1/2 inch tongue and groove wood floor decking 8inch reinforced site cast concrete slab at hearth with 7 #4 reinforcing bars(horizontal) and 4 #5 reinforcing bars at each face(vertical) GLASS: insulating glass 3 inch steel framing site cast concrete sill LOFT FLOOR: 3 inch x 10 inch beam wood framing at 16inch o.c 1and 1/2 inch tongue and groove wood floor decking CLERESTORY WINDOW: site cast concrete lintel with 4 #5 reinforcing bars steel framed safety window flitch beam composed of 4 2 x10 inch beams and 1 3/8 inch thickness steel plate on center ROOF assembly: 3/4 inch battens flitch beam 2inch x 10inch laminated veneer lumber beam at 16inch o.c 1/2inch plywood roof sheathing 2 inch x 4 inch rafters vapor barrier R30 batt insulation slip sheet metal roofing
Menefee Cabin Clark & Menefee Architects nathan st.John yan meng Georine Pierre John Costello
0 1/2
1
2
4