ENGR 209 HOMEWORK Q.1. The network shows the activities that need to be undertaken to complete a Project.
According to upward network diagram; a) Write the all possible paths. What is the completion time for each of them ? b) Without calculating floats which path is the critical path? Why? Q.2. Construct an activity on arrow network based on the activity descriptions below. Label activities in the network by their activity letters. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc.