BATHROOM RA1. Replace sink fixture RA2. Replace shower fixture RA3. Replace or sand and paint rust toilet hardware

LIGHTING AND OUTLET L1. Install kitchen droplight (1) L2. Install living room wall light (3) L3. Install foyer ceiling light(3) L4. Install foyer closet strip light L5. Install corridor pendent light(1) L6. Install bedroom pendent light(2) L7. Install kitchen recess light(2) L8. Bedroom outlet per design L9. Foyer closet outlet per design L10. Living room outlet relocation per design L11. Kitchen outlet relocation per design L12. 2 Closets switchplate to be change to toggle lighting

KT4

KT4 KT1

KT2

KT3

105 KT KT3

KT4

KITCHEN KT1. Demolition of the current kitchen KT2. Removal of existing appliances KT3. Demolition of the kitchen tiles KT4. Fix floor Tiles of demolition counter area and existing tiles KT5. Coordinate with kitchen consultant and manufacture to install cabinetry and countertop KT6. Install sink and dishwasher KT7. Install gas range or induction cook-top KT8. Install circulating range hood KT9. Install panel ready refrigerator KT10. Install backsplash (fireproof material) KT11. Install baseboard KT12. Install/cut countertop KT13. Apply 12” waterproofing on wall per drawing submitted to building management KT14. Install and cut counter top

BA2

110 BR

101 F

109 BA

BA1

F7

F7 F6

BR1

104 LR

106 CO

HC1

BEDROOM BR1. Removal of existing bookcase FLOORING FL1. Sand the floor FL2. Apply stain to floor

108 HC

107 HC

HEATING CASE C1. Build Living room radiator box per design C2. Build bedroom shelf per design CORIDOR CLOSET PAINTING P1. Painting the entire apartment per design (not including ceiling)

UTO STUDIO 154 Grand Street NEW YORK, NY 10013 T: 916-835-8241 E: info@uto-works.com

T Residence MANHATTAN, NY 10013

HC1. Opening the wall between the 2 closest into one closet HC2. Closet lights to be adjusted per design

Name:

DEMO PLAN

LIVINGROOM LR1. Install and relocate new ceiling mounted combined smoke-carbon monoxide detector (battery operated)

103 F

102 F

FOYER F1. Front main and secondary door to remain. Cover and protect as required F2. Front main lock change and operable F3. Original doorbell box to be properly fixed on the wall (currently none operable) F4. Secondary door to be inspected and make sure it is operable F5. New mirror to be installed F6. Enlarge both foyer closet opening per design measurement and adjust casing millwork F7. Remove existing closet door and replace with new doors purchased by client F8. Repair new doors (minor chipping) F9. Closet system per design F10. Closet lighting per design

SCALE:

1/4''-1'

DATE:

DATE


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Residential Construction Documentation by Han Xiao - Issuu