Project Report: Mumbai Metro

Page 1

MUMBAI METRO RAIL CORPORATION (MMRC)

PROJECT TRAINING 2020

FINAL COMPREHENSIVEREPORT (FCR)

MUMBAIMETROLINE-03,UNDERGROUND CONSTRUCTION PACKAGE-02

COLABA-BANDRA-SEEPZ

SUBMITTED BY : BHUMIKA RAJ (UC5316)

GUIDED BY: PROF.: RESHMA SHAH

TEACHING ASSISTANT : MAYURIKA

BACHELORS IN CONSTRUCTION TECHNOLOGY

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075

Certificate of Approval

This is to certify that Miss Bhumika Raj, Code No. UC5316, undertaking Project Training course offered in Spring Semester, academic year 2019-20 has satisfactorily completed training on site Mumbai Metro Line 3 UGC02, Mumbai and submitted final comprehensive report that broadly satisfies the training requirements.

Signature of Faculty:

Name of Faculty Incharge: Prof. Reshma Shah

Date:

T +91 7926302470

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI,
GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
F +91 7926302075

DECLARATION

I hereby declare that the project training report submitted to the Faculty of Technology, CEPT University is a record of an original work carried out by me on project training site Mumbai Metro Line-03, UGC 02 at Mumbai Maharashra. further declare that the material obtained from other sources has been duly acknowledged in the Report. I shall be solely responsible for any plagiarism or other irregularities, if found in the report.

Signature of student:-

T +91 7926302470

F +91 7926302075

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

ACKNOWLEDGEMENT

I would like to express my deepest gratitude to my reporting officer, Mr. Abhijeet Chaudhary (Asst. General Manager, MMRC), whose contribution in stimulating suggestions and encouragement, helped me to coordinate my project especially in curating this report.

Also I would like to extend my thanks to Mr. Mukul Borah (R.E. MAPLE) who helped me to complete my report as well as took their precious time to explain and guide me. A special thanks goes to Mr. Avinash who patiently provided with all the information. Finally, many thanks go to the Chief Project Manager, Mr. Ravi Ranjan Kumar; Deputy General Manager, Mr. S. G. Dalvi; and Deputy Engineers, Mr. Rohan Shiral and Mr. Ranjit Deore whose have invested their full effort in guiding me in achieving the goal.

I appreciate the guidance given by my faculty Prof. Reshma Shah as well as the our Teaching assistant Mayurika as their continuous monitoring and feedbacks during the internship period helped me in overcoming my setbacks.

CEPT University, Ahemdabad

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
380009,
+91 7926302470
+91 7926302075
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat T
F

This subject called Project Training Report has been made in requirement of BCT [Bachelor’s in Construction technology] in Civil-Construction from Faculty of Technology, CEPT University, Ahmedabad; in the 8th Semester of this course. It is a 10 semester course in which along with theoretical study, equal emphasis is laid on practical study and experience.

Project Training was a 16 week long intensive training program where emphasis was laid on study of Construction Technology, including method of construction, use of equipmentplants, productivity and related management aspects. The structure of training was for me to take up major constructions activity unique to the project and study them in detail, dedicating minimum three weeks of time to each report. It has total 5 reports ( 1 Preliminary Site Report (PSR) + 4 Construction Activity Report (CAR). Effort has been made to cover all the major aspect of construction, including planning and management for each of the construction activity studied which is Part one.

Also due to Covid-19 few days were left for training so 4 tasks were allotted to us including a sketch up model to work from hom which is Part two.

This Project Training has been a great learning experience towards understanding the functioning of such a huge Project with involvement of multiple agencies and the challenges in coordination, planning and execution.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS :
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
CST, KALBADEVI, GIRGAUM, GRANT ROAD.
PREFACE .

Time Sheet

Project Training | Faculty Of Technology |Spring 20

Bhumika Raj (UC5316) Semester-08 PROJECT TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Name:BHUMIKA RAJ CODE: UC5316 Address:AZAD MAIDAN GATE NO 2, FORT MUMBAI JOINING DATE : 26 DEC 2019 -LAST WORKING DATE: 19 MARCH'20 Project name:UGC-02 MUMBAI METRO LINE 3 Code Name T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12 T13 TOTAL PERCENT % 1 Drawing/Specs Study 7 4 4 2 11 7 3 2 7 3 7 9 3 69 11.94 2 Lineout/Surveying 2 4 4 2 6 6 4 5 6 7 6 5 4 61 10.55 3 Earthwork 1 0 5 6 4 4 4 6 4 5 2 0 4 45 7.79 4 Embankment/Rock Filling 0 0 0 1 0 0 0 0 0 0 0 0 0 1 0.17 5 Foundation/Piling/Sub Base 0 7 7 0 0 0 7 0 0 0 0 0 7 28 4.84 6 Concerting/Precast 0 7 4 0 0 0 4 0 0 0 0 4 4 23 3.98 7 Formwork,Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 8 Reinforcement 5 3 11 0 18 13 11 14 3 5 4 3 11 101 17.47 9 Structural Steel Works 0 0 0 15 0 0 0 0 0 0 0 0 0 15 2.60 10 Prestressing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 11 Enabling Structures 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 12 Launching/Erection 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 13 Brick/Block Work 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 14 Wall finish:Plaster/print/other 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 15 Floor finish,water proofing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 16 Plumbing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 17 Door/Window/Ventilators 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 18 Finishing(Other) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 19 Roads & Infrastructure 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 20 Tools/Equipment/Plants 3 7 3 0 0 0 4 5 0 2 1 3 4 32 5.54 21 Quantity Surveying,Billing 5 2 3 2 3 5 3 3 2 5 6 2 3 44 7.61 22 Quality/Testing 0 0 0 7 0 0 0 0 0 0 0 0 0 7 1.21 23 Planning/management 8 0 2 8 2 6 2 2 2 8 4 0 2 46 7.96 24 Other(NATM , DRILL BLASTING ) 17 5 5 2 4 7 4 4 15 17 18 4 4 106 18.34 Total(MIN 48 HRS) 48 39 48 45 48 48 46 41 39 52 48 30 46 578 100.00
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 1 Contents 2 Metro Project In A Nutshell 1 2.1 Automated Metro 2 2.2 Benefits Of The Project ..............................................................................................................2 2.3 Organisation Chart .....................................................................................................................3 2.4 Roles And Responsibilities 3 2.5 Details Of The Project 4 2.6 Cost Break Up 5 2.7 Project Location 6 Work Breakdown 7 2.8 Organisation...............................................................................................................................9 2.9 Client Organisation Chart 10 2.9.1 Cst Statiion Plans 11 2.9.4 Kalbadevi Station Plans 12 2.9.5 Kalbadevi 13 2.10 Construction Methodology Adopted For The Project 15 Temporary Structures 15 2.11 Stations..................................................................................................................................15 2.12 Tunnels – 16 2.13 Why Natm: 16 2.14 Contract Conditions 17 2.15 Miscallaneous Facilities 18 2.16 Wages 18 Chapter 2: .......................................................................................................................................19 Construction And Methodology.......................................................................................................19 3 Project Scehdule.......................................................................................................................20 3.1.1 Time Distnace Graph 22 3.2 Job Layout At Cst Station..........................................................................................................23 3.2.1 Job Layyout At Wadala 24 3.3 Method Statement: 26
GRANT ROAD.
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 3.4 4. Degree Of Mechanisation Justification: 26 4 Secant Piling 28 4.1 Scope Of Work: 28 4.2 Observed Activity Flow Chart 28 Tender Document Specification( 29 4.3 Organisation Chart 30 4.4 Procedure For Piling 32 4.5 Procedure Sketch For Piling 33 4.6 Bbs For Pile( S1467) 34 4.7 Material Consumption: 35 4.8 Data Entry Done For Pile- P1489 36 4.9 Time Cycle 37 4.11 As Per Observation................................................................................................................39 4.12 Abstract Shee 44 4.13 Activity Analysis 45 4.17 Equipment Detail 46 4.18 Hira 47 5 Roof Slab 48 5.1 Scope Of Work 48 5.2 Observed Activity Flow Chart ...................................................................................................48 5.3 Organisation Chart ...................................................................................................................49 5.4 Joblayout 51 5.6 Methodology 52 5.7 Scaffolding Detail 53 5.7.1 Reinforcement Details Pedestal 54 5.9 Pour Plan Of Roof Slab 55 5.10 Material Testing Details.........................................................................................................56 5.11 Activity Wise Cost Break Up ..................................................................................................57 5.12 Labour Productivity ( Pour 6) 57 5.13 Time Cycle Analysis 58 5.14 Analysis Of Roof Slab For Entire Station Length 59 5.15 Alternative Suggestion 60
GRANT ROAD.
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 5.16 Activity Over View 61 5.17 Construction Of Adit And Central Cavern By Natm Methodology 61 5.18 Natm Procedure 61 5.19 Alignment Plan 62 5.20 Adits And Central Covern Plan...............................................................................................63 5.21 Organisation Chart 64 5.22 Stratigraphy Of Soil Condition At Kalbadevi Station According To The Geological Investigation Report 65 5.23 Geological Profile Details (Kalbadevi ) 66 5.24 Design Methodolgy 68 5.25 Analytical Approach...............................................................................................................68 5.26 Instrumentation And Monitoring 69 5.27 They Are Located At The Periphery Of The Face Of Excavation, One On 69 5.28 Natm At Kaldadevi In A Glance 70 5.29 Procedure For Construction Of Adit At Kbd Station 71 5.30 Procedure Sketch For Adit Construction 72 5.32 Blast Details For Adit .............................................................................................................74 5.33 Quantity Estimation Of Explosives For Adit ..........................................................................75 5.34 Procedure For Central Cavern 78 5.35 Rocedur For Blasting With Explosives 78 5.36 Observed Qauntity For Blasting Central Cavern Through Adit 3 79 5.37 Time Cycle Analysis For Adit 3 81 5.38 Time Cycle Annalysis For Cavern 82 5.39 Table 29: Timecycle For Central Cavern.................................................................................82 5.41 Analysis Of The Activity 90 6 Cross Passage Construction 91 6.1 Reason For Providing Cross Passage 91 6.2 Organisation Chart 92 6.3 Oserved Activity Location 93 6.5 Cross Passage Details 95 6.6 Lattice Girder Details 96 6.7 Procedure For Construction Of Cross Passage .........................................................................97
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 6.8 Instrumentation And Monitoring 98 6.9 98 6.10 Quantity Estimation For Lattice Girder 99 6.11 Labour Analysis For Cross Passage 7 At Grant Road Station 100 6.11.2 Buy And Lease Options:...............................................................................................104 6.11.3 Bills 105 6.11.4 Managemnet Aspects Of Site. 106 6.12 Feasaibiliyy 106 Feasibility Study 107 7 Introdcution To Project Delay 109 7.1 Reasons Of Delays In Developed Vs Developing Countries. 110 7.2 Task Overview 111 7.3 Time Line Of Delays................................................................................................................112 7.4 Quantification For Delay Of Work ,Time And Costoverun. 114 7.5 Impact Of Tbm Hault: 114 7.5.1 Impact Due To Geogology 115 7.5.2 The Rate Of Mining Will Be Affected In Closed Mode From 7 To 3 Rings Per Day Additional 2 Weeks For Interchanging The Tbm Mode 115 7.5.3 Land Acquisition Issue At Kalbadevi ............................................................................115 7.5.4 Impact Due To Delayed Natm Works 116 7.5.5 Impact Due To Encountered Uncharted Utilties 116 Impact Due To Covid -19 116 7.6 Project Key Dates And Delays 117 7.7 Comparison With Research Paper Number 118 7.8 Conclusion:.............................................................................................................................121 8 Designing A Labour Colony: 123 Idealogy Used: 124 8.1 ...................................................................................................................................................126 8.2 127 8.3 128 8.7 Methodology 132 Alternative Activity 139
GRANT ROAD.
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 9.1 Method Statement For Construction Of Tunnel By Adecco-Rs 140 9.2 Methodology Introduction(Adecco-Rs) 140 9.3 Definition Of Cases 143 Case Type-1 143 Case Type-2.................................................................................................................................143 Case Type - 3 143 9.4 Stability Measures 144 9.5 Stepwise Procedure 144 9.5.1 Methodology : 145 9.6 Quantity Analysis 147 Quantity Estimation By Addeco Rs Method By Adecco-Rs............................................................147 9.7 Timecycle For Adecco –Rs Methodlogy 148 9.8 Cost Analysis For Addeco-Rs...................................................................................................149 9.10 Pipe Jacking 151 9.11 Details Of Cross Passage : 151 Jacking Method 151 9.12 Methodology 152 9.13 Schematic Diagram For Pipe Jacking System 153 Machinery Selection Criteria : 153 9.15 Rate Analysis........................................................................................................................156 9.16 Diaphragm Walls .................................................................................................................158 9.17 Method Statement 158 Timecycle For Diaphragm Walls Timecycle For Diaphragm Walls 160 9.18 Outcome: 161 10 3d Model Of Natm Works At Kalbadevi Station 163 3d Model Images 165
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 Table Index Table 2: Contract Conditions 17 Table 3: Miscallaneous Details 18 Table 4: Labour Details 18 Table 5: Project Key Dates 20 Table 6: Bbs For Pile 34 Table 7: Material Consumption 35 Table 8:Data Entry For Piles..................................................................................................................36 Table 9: Time Cycle Analysis For Primary Piles .....................................................................................37 Table 10: Timecycle For Secondry Piles ................................................................................................37 Table 11: Time Cycle Analysis As Per Observation ( Primary Piles) .....................................................38 Table 12:Time Cycle Analysis As Per Observation ( Secondary Piles)...................................................38 Table 13: Ra For Excavation Of Pile.......................................................................................................40 Table 14: Ra For Reinforcement Of Pile(Secondary) 41 Table 16; Ra For Concrete 43 Table 17: Hira For Secant Piling 47 Table 18: Material Testing Details 56 Table 19: Labour Productivity Roof Slab 57 Table 20: Time Cycle Analysis Roof Slab 58 Table 21: Time Cycle Break Up.(Pour Wise) 58 Table 22: Analysis For Entire Station Length 59 Table 23:Rate For Couplers...................................................................................................................60 Table 24: Provided Alternatives............................................................................................................60 Table 25: Geological Details At Kalbadevi.............................................................................................66 Table 26: Rmr Table ..............................................................................................................................68 Table 27: Quantity For Blasting At Caven Round 1...............................................................................79 Table 28:Quantity For Blasting At Central Cavern Round 3..................................................................80 Table 29: Time Cycle Analyis For Adit 81 Table 30: Timecycle For Central Cavern 82 Table 31: Labour Productivity 83
GIRGAUM, GRANT ROAD.
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 Table 32: Ra For Excavation Of Adit 84 Table 33: Ra For Shotcrete 85 Table 34: Ra For Wiremesh...................................................................................................................86 Table 35: Ra For Rock Bolting ...............................................................................................................87 Table 36: Ra For Rock Bolting ...............................................................................................................88 Table 37: Quantity Of Lattice Girder.....................................................................................................99 Table 38: Labour Analysis ...................................................................................................................100 Table 39: Ra For Lattice Girder ...........................................................................................................101 Table 40; Abstract Sheet 102 Table 41: Comparison Between Developed And Developing Countries 110 Table 42: Working Time Calculation 114 Table 43: Proceedings 115 Table 44: Building Demolition Status 116 Table 45: Project Key Delays 117 Table 46: Labour Colony Details 123 Table 48: Cost Analysis Addeco-Rs Method........................................................................................149 Table 49:Cost Analysis For Cross Passage By Pipe ..............................................................................156 Table 50: Timecycle For D-Walls.........................................................................................................160 Table 51: Comparison Table ...............................................................................................................162 Figure Index Figure 1: Map Showing All Stations 15 Figure 2: Automated Metro Details 2 Figure 4: Map Showing All The Stations 6 Figure 5: Map Of India 6 Figure 6: Alignment Plan 6 Figure 7: Process Of Natm Is Shown In Above Image. 16 Figure 8: Project Scheduling For Kalbadevi Station 21 Figure 9: Time Distance Graph 22 Figure 10: Geological Profile At Kalbadevi Station................................................................................65
GIRGAUM, GRANT ROAD.
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 Figure 11: Dimensions For Adits 66 Figure 12: Instrumentation And Monitoring 69 Figure 13: Set Out Points For Adit.........................................................................................................74 Figure 14: Blast Details For Adit............................................................................................................74 Figure 15: Set Out Points At Central Cavern.........................................................................................78 Figure 16: Blast Details For Central Cavern ..........................................................................................77 Figure 17: Shotcrete Strength Graph....................................................................................................90 Figure 27: Excaavtion For Soft Rock....................................................................................................143 Figure 28: Pipe Jacking Method 153 Figure 29: Concrete Pipe 154 Figure 30: Cutter Head 154 Figure 31:Plan View Of Cross Passage Indicating The Orientation Of Concrete Pipes To Be Installed 155 Figure 32: Methodology For D-Walls 159 Figure 34: 3d Model 164 Figure 35: Adit Plan At Kalbadevi Station ...........................................................................................164 Figure 33: Alignment Plan...................................................................................................................164
GRANT ROAD.

PART 1 CHAPTER 1: INTRODUCTION TO PROJECT

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
T
F

2 METRO PROJECT IN A NUTSHELL

The Aqua Line of the Mumbai Metro, also known as Line 3 or the Colaba–Bandra-SEEPZ line, is a part of the metro system for the city of Mumbai, India of which construction has been initiated. When completed, the 33.5-km long line will be the first underground metro line in Mumbai

Though 2,150 trains hurtle through the city, carrying millions of Mumbaikars to their destinations but for the 75 lakh odd commuters, every day brings with it the challenge of searching for foot-space in a train that cannot hold a pebble more. Time has truly come for ‘the lifeline’ of Mumbai to now change to Metro –a grade separated rail based Mass Rapid Transit System

Mumbai Metro Line - 3 (MML - 3) is one of such key projects to improve the transportation scenario in the financial capital of India i.e. Mumbai. MML-3 project - a 33.5Km. long corridor running along Colaba-Bandra-SEEPZ, envisages to decongest the traffic situation in Greater Mumbai. Mumbai Metro Rail Corporation Limited (MMRC) is the nodal agency responsible for the implementation of Mumbai Metro Line–3(MML-3) project. It has been constituted as a JV of the Govt. of India(GOI) and the Government of Maharashtra(GOM) on 50:50 sharing basis.

AIM : CONNECTING THE UNCONNECTED

1 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS
+91 7926302470
+91 7926302075
: CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T
F
Parade 0(CHAINAGE M) Vidhan Bhavan 1438 Churchgate 2216 Hutatma chowk 3087 CST Metro 3902 Kalabadevi 4754 Girgaon 5452 Grant Road 7035 Mumbai Central Metro 7951 Mahalaxmi 9047 Science Museum 10208 Acharya Atre Chowk 11256 Worli 12723 Siddhivinayak 14286 Dadar 15683 Sitaladevi 17364 Dharavi 19095 BKC 20925 Vidyanagari 22138 Santacruz 23155 Domestic Airport 25510 Sahar Road 27220 International Airport 28202 Marol Naka 29200 MIDC 30380 SEEPZ 31697 AAREY 33000
Cuffe
FIGURE 1: MAP SHOWING ALL STATIONS

METRO

Since the beginning of rapid transit systems 154 years ago in London’s Metro Railway, metro rail systems have advanced to most recent and updated technologies that took place in past 30 years. Almost a quarter of world’s 150 metro cities have at least one line operating in fully automated mode. Automation in metro is significantly seen in Europe, Middle East and China

2.2 BENEFITS OF THE PROJECT

Environmental benefits :There is expected to be reduction in air pollution, and improvement in air quality. MML-3 is committed to preserve the environment. As commuters would start to prefer the comforts of metro over other conventional transport options.

Travel with comfort: Today suburban trains are overcrowded, carrying 5000 passengers against design capacity of 1750. Metro 3 is expected to reduce the load by nearly 15%. Since the entire train will be air-conditioned, commuters will be saved from noise/dust pollution and will be able travel with better comfort

Revisiting History : The present travel time of 100 minutes from Cuffe Parade to Airport will come down to only 50 minutes due to MML-3

Economic Benefits: MML- would be uniquely positioned to attract more business investments and is also expected to result in employment generation during and after constructiom

2 MUMBAI
LINE 3 – PACKAGE 2 UGC02
T
F +91
METRO
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
7926302075
2.1 AUTOMATED (reference Mumbai metro magazine vol. 3) FIGURE 2: AUTOMATED METRO DETAILS

MUMBAI METRO LINE 3 –

PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.3 ORGANISATION CHART

MMRC ( EMPLOYER)

MAPLE (GENERAL CONSULTANTS)

PACKAGE 1&7 (L&T) ANS SHANGHAI TUNNEL ENGINEERING CO.

PACKAGE 2 HCC AND MOSCOW MOSMETROSTROY

PACKAGE 3 DOGUS AND SOMA

PACKAGE 4 CONTINENTAL ENGCORP.,ITD CEMENTATION AND TATA PROJECTS

PACKAGE5 &6

J KUMAR INDRA PROJECTS AND CHINA RAILWAY RUNNEL GROUP

CST STATION CHATTRAPATI SHIVAJI TERMINUS

KALBADEVI STATION

GIRGAON STATION

GRANT ROAD STATION

Note MAPLE is a consortium of 4 different companies :AECOM-LEAD, PAEDCO,LOUIS BERGER,EGIS FURTHER DIVIDED INTO :L1-FOREIGNER HIGHEST DIVISION L2-FOREIGNER L3-IDIANS AND FOREIGNERS L4-L5-INDIANS

2.4 Roles and responsibilities

AUTHORITY NAME

MUMBAI METRO RAIL CORPORATION

RESPONSIBILITY

Over all supervision of metro station works and tunnel Dealing with different departments like traffic,BMC for completion of project

GENERAL CONSULTANTS

CONTRACTORS

Supervision of over all metro construction ,providing drawing and weekly progress report to client

Excecuting the metro work as per terms and conditions of client

Kasturbhai Lalbhai Campus University Road, Navrangpura

Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

3

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.5 DETAILS OF THE PROJECT

NAME – Package 2, Line 3 (underground), Mumbai Metro

OBJECTIVE – To construct two parallel underground tunnels by using TBM (Tunnel Boring Machine) for Mumbai metro line 3 including four stations – CST Metro, Kalbadevi, Girgaum and Grant Road.

SITE OFFICE ADDRESS – Gate 3, Azad Maidan, Nr. Metro Cinema, Mumbai – 400001, Maharashtra

SCOPE OF WORK – Design and construction of Underground Stations namely CST Metro, Kalbadevi, Girgaum and Grant Road and Twin Tunnel between CST and Mumbai Central – Up Line (from Ch. 3770.58 m to Ch. 7842.62 m) and Down Line (from Ch. 3801.05 to Ch. 7860.22 m) by TBM including Scope of works comprising of Civil, Architectural, E&M works as defined in agreements.

PROJECT TYPE – EPC (Engineering, procurement and construction) Contact. EPC Contractor is responsible for all activities engineering, procurement and construction and hand – overs the project to the owner.

LENGTH OF PROJECT:CST METRO STATION – 255 m ,KALBADEVI STATION – 208 m,GIRGAUM STATION – 292 m,GRANT ROAD STATION – 202 m.NORTH BOUND (Downline) TUNNEL LENGTH – 3115 m SOUTH BOUND (Upline) TUNNEL LENGTH – 3102 m TOTAL LENGTH OF TUNNELS – 6217 m

CLIENT – MMRC (Mumbai Metro Rail Corporation Limited)

CONTRACTOR – HCC – MMS JV ( Joint Venturebetween Hindustan Construction Company and Mosmetrostroy). (HCC – 74% and MMS 26%)

 Start date – 18th july, 2016

 Project completion date – 10th january, 2021

 Duration of project (as per contract) – 1638 days

 Tender project cost – rs. 2115.3 crores

 Muck disposal site – mhape midc and ambernath

 Mean sea level -25

 Track gauge- Standard Gauge (1435 m)

 Design speed- 80 kmph,

 Scheduled speed- 30 kmph

 Capacity of 8 coach unit- 2406 passenger

T +91 7926302470

F +91 7926302075

4
UGC02
MUMBAI METRO LINE 3 – PACKAGE 2
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

CONSULTANTS

GENERAL – MAPLE (Joint Venture - AECOM, PADECO, LBJ Inc. & Egis Rail)

DDC (Detail Design Consultant) - Ayesha

LDC (Lead Design Checker) – Amber

Detail DesignConsultant (AYESHA). They design the project

Lead DesignConsultants

If there are any mistakes, the Checker designs are again sent back to DDC (AMBERG)If everything is right, issues a Design Certificate

2.6 COST BREAK UP

HCC-MMS

They also have a design team that checks the designs

COST BREAK UP

GeneralConsultants(MA PLE) also check the designs and issues NONO (Notice of no ection) if design is right

EXECUTION

GRANT ROAD-MMCT

Girgaon Station to Grant Road Station

Kalbadevi Station to Girgaon Station

CST Station to Kalbadevi Station

grant road

Girgaon Station

PIE CHART 1: DEPICTING COST BREAK UP OF TUNNELS IN ALL STATIONS.

Kasturbhai Lalbhai Campus University Road, Navrangpura

Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

5
GRANT ROAD-MMCT 8% Girgaon Station to Grant Road Station 14% KALBADEVI TO GIRGAUM 6% CST TO KALBADEVI 8% grant road 19% Girgaon Station 14% Kalbadevi Station 12% cst metro 19%

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.7 PROJECT LOCATION

LENGTH OF PROJECT

CST METRO STATION – 255 m

KALBADEVI STATION – 208 m

GIRGAUM STATION – 292 m

GRANT ROAD STATION – 202 m

Seismology: As per India times data, Mumbai lies in Seismic Zone-3, which is Moderate seismic zone. It can withstand up to 6.5 Richter scale earthquake intensity.

 All the four stations under package 2 are completely different

NORTH BOUND (Downline) TUNNEL LENGTH – 3115 m

SOUTH BOUND (Upline) TUNNEL LENGTH – 3102 m

TOTAL LENGTH OF TUNNELS – 6217 m

 The type of geological strata of all four stations is completely different.

 Cst has hard rock so its depth is less compared to other stations

 The neighbouring locality also varies,example kalbadevi is a densely populated with many heritage structures like parsi temple and many more while girgaum is located near beach and is one of the high end localities of Mumbai,CST Chattrapatati Shivaji terminus

 The depth of each station varies with quite a difference.

 With so much variation in each station, much more learning can be carried out

6
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
Landmarks NEAREST TO SITE NEAREST TO RESIDENCE NAME DISTANCE (Km) NAME DISTANCE (Km) Railway Station Mumbai Central 5.5 Mumbai Central 2.1 Airport Chhatrapati Shivaji 22.4 Chhatrapati Shivaji 18.3 Hospital Bombay Hospital 1.2 Jaslok Hospital 0.22 CST • CHATTRAPATI SHIVAJI TERMINUS KALBADEVI • ONE OF MOST DENSEY POPULATED AREA AND HAS HERITAGE STRUCTURES GIRGAUM • IT IS SITUATED NEAR NEACH GRANT ROAD
FIGURE 4: MAP OF INDIA
FIGURE 3: MAP SHOWING ALL THE STATIONS FIGURE 5: ALIGNMENT PLAN

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

7
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT
BREAKDOWN
Bhumika Raj (UC5316) Semester-08
TRAINING 2019-2020 WORK
8
CST, KALBADEVI,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS :
GIRGAUM, GRANT ROAD.
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
9 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020 2.8 ORGANISATION CHART
GRANT
Bhumika Raj (UC5316) Semester-08

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.9

MMRC ORGANISATION CHART Director of Project

Mr. Subodh Gupta Mr. Ravi (Package - 2)Ranjan

Kumar

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
10
F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470
CLIENT ORGANISATION CHART Deputy General Mr. S. G Dalvi. Assistant General Mr. Abhijeet Chaudhary Deputy Engineer Mr. Ranjit Deore Deputy Engineer Mr. Rohan Shiral BHUMIKA RAJ (INTERN)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

11
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
CST STATIION PLANS
Bhumika Raj (UC5316) Semester-08
2.9.1

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

12
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
CST STATION SECTION
Bhumika Raj (UC5316)
2.9.2

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

13
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
KALBADEVI STATION PLANS
Bhumika Raj (UC5316)
2.9.5
14 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
: CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
KALBADEVI STATION SECTIONS
STATIONS
Bhumika Raj (UC5316) Semester-08
2.9.6

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.10 CONSTRUCTION METHODOLOGY ADOPTED FOR THE PROJECT TEMPORARY STRUCTURES

SECONDARY PILE SHOWING REINFORCEMENT

PRIMARY PILE

OVERLAPPING IS DONE TO STOP THE WATER INGRESS

Secant piles act as retaining structures and are used to support weaker strata and to stop the water ingress. Also guide walls are not used at CST station because of the hard rock strata requires different machinery and is does not turn out to be economical.While at other metros across the country diaphragm walls are used because of the soft soil conditions.(Refer piling report pg 28)

2.11 STATIONS

Secant piling is done on the periphery of the station and construction work is carried out

Traffic decking is done and supported by king post on one side and utility diversions are provided

Cst Station :bottom up approach , off road

Kalbadevi Station : natm on the road

Girgaon Station: on the road , bottom up

Grant road Station : on the road. Bottom up

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
15
F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470
STATION TYPE OFF THE ROAD ON THE ROAD

2.12 TUNNELS –

Two tunnels are being dug by using Tunnel Boring Machine (TBM). TBMs are named after Vaitarna river (Vaitarna 1 and 2).

Cost -60 croresThe first of these was a 6.68m diameter dual-mode hard rock TBM (T58) that will be one of two new machines deployed by the Hindustan Construction Company – Moscow Metrostroy JV to build the twin tunnels on the line’s 4.049km UGC-02 contract (Chhatrapati Shivaji Terminal Station – Mumbai Central Station), which was awarded by the Mumbai Metro Rail Corporation Ltd (MMRCL) in July 2016.

Procurement

Dual Modesingle shield (hard rock)

2.13 WHY NATM:

After design and production, TBM will be assembled and tested for factory acceptancetest before shipment from China to Mumbai

Also called (New Australian Tunelling Method)Used to widen the tunnel using explosives, used when there is space constraint or In case of widening the tunnel.NATM requires high expertise as it include drilling and blasting using explosives.(refer natm report pg no.61)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 16
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
BRAND –terratec
Figure 6: process of natm is shown in above image.

2.14 Contract conditions

At package 2 –HCC –MMS (CJV) total 12 volumes are available for contracts, each cobering differnet aspects of contracts management.

TABLE 1: CONTRACT CONDITIONS

5

6

7

8

Arbitration :If both the parties don’t resolve the issue mutually it is referred to indian arbitration and reconciliation act , 1996.Total 3 arbitrators are appointed .One from each party and both one presiding arbitrator shall be appointed by both arbitrators and the decision of the arbitrator shall be final

Repayment amortisation of advance payment:The recovery of mobilisation and plant and machinery advances will be completed by the time 85% of the accepted contract amount has been paid or by the time of original completion date, which ever is earlier. The recovery of advances shall be 10% of monthly bill

Payment of materials in site:Limited to 80% of the actual value or assessed value of cement and steel.The total advance on account at a time shall be limited to 1% of contract price or average consumption of such material for 3 months or less. At any time the total outstanding advance against such materials atshite shall not exceed 1.5% of conract price

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 17
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
NO. ATTRIBUTE DETAIL
Type of contract EPC
Design Life for project 130
Estimated cost of work package 2252
Specific Technology Tbm and natm
1
2
3
4
Time for completetion of works ; 1638 days days to achieve issuance of taking over certificate
Defects notification period 1 YEAR
Amount of Performance Guarantee 10% of total contract price
Maximum limit of delay damages foe dealy 10% of contract price
Mobilisation advance payment 5% accepted contract amount
Advance against plant and machinery 5 accepted contract amount
Amount of third party insurance 0.50 million for any one incident,heritage building-1 million for one incident,upto many incidents 12 Bonus for early completion 1 million
9
10
11

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

2.15 Miscallaneous facilities

TABLE 2: MISCALLANEOUS DETAILS

INFRASTRUCTURE FACILITIES

1 Facility: Casting Yard and then transported to all the 4 stations.

• Food is available on paid basis to all the members at site, such as Civil engineers, QC staff, GC staff, SHE staff, Sub-contractor staff and all the labourers.

2 Medical Facility: Medical tool box kit is available on every station and also at the casting yard, along with OHC (Occupational Health Center) department.

• There are hospitals nearby all stations and casting yard, in vicinity of around 1-2 kilometres.

3 Health & Hygiene condition of place:

2.16 WAGES

BMC organisation people come and make a random visit, to check the hygiene of the place, as per Govt. of Maharashtra norms

Wages of labourers (For 11 hours shift)

Skilled: ₹ 650 Semi- Skilled: ₹ 600 Unskilled: ₹ 540

Labour colony is at Byculla

TABLE 3: LABOUR DETAILS

LABOUR DETAILS (AS ON JAN ‘20)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
18
T +91
F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
7926302470
SR. NO. STATION SKILLED UNSKILLED TOTAL 1 CST 83 140 223 2 KALBADEVI 64 123 187 3 GIRGAON 78 160 238 4 GRANT ROAD 59 114 173

CHAPTER 2: CONSTRUCTION AND METHODOLOGY

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 19
– 380009, Gujarat T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad

3 PROJECT SCEHDULE

Achieve substantial completion of station public Concourse/Mezzanine (wherever applicable) Level areas including entrances (all stations) finished to Degree 2 completion and provide access to all Interfacing Contractors

Achieve substantial completion of all bored tunnels (including cross passages and temporary TBM shaft in tunnel areas, if any) finished to Degree 1 completion and provide access to Track work and other Interfacing Contractors on entire bored tunnels ( all bored tunnel lengths)

Achieve substantial completion of all bored tunnels (including cross passages and temporary TBM shaft in tunnel areas, if any) finished to Degree 1 completion and provide access to Track work and other Interfacing Contractors on entire bored tunnels ( all bored tunnel lengths)

Achieve substantial completion of all E&M works to permit permanent power on to all stations and tunnels

all architectural finishing and signage works in all respects 1522

issuance of Taking Over Certificate (all completed to degree 4 completion)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS
20
: CST, KALBADEVI, GIRGAUM, GRANT ROAD.
T +91 7926302470 F +91 7926302075 TABLE 4: PROJECT KEY DATES
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
Description Number of days from commencement Status as per EOT2submitted remarks day dated diff date Start of Initial drive for TBM-1 462 22-Oct-17 -179 19-Apr-18 KD achieved On 4-Dec-17 Start of Initial drive for TBM-2 518 19-Nov-17 -175 13-May-18 KD achieved On 21-Feb18
1204 03-Nov-19 -1039 7-Sep-22
1064 16-Jun-19 16-Jun19 -929 31-Dec-21
1260 29-Dec-19 -1059 22-Nov-22
1498 23-Aug-20 -962 12-Apr-23
1522 16-Sep-20 -1054 06-Aug-23
1638 10-Jan-21 -1041 17-Nov-23 Achieve
of
Certificate 2003 10-Jan-22 -1041 16-Nov-24
Complete
Achieve
issuance
Performance

Above image shows how planning is done for kalbadevi station box in microsoft project, it starts with temporary structures proceeding to north box and south box construction . activity id is assigned to each of the activity which shows the start date and end date of project. For comparison baseline start and finish dates are also shown.Float shows the days by which the activityis leading or lagging. Negative float shows activity is lagging by the no of days and positive float shows the days by which activity is leading.

LIST OF ACTIVITIES

21
METRO LINE 3 – PACKAGE 2 UGC02
MUMBAI
+91
STATIONS : CST, KALBADEVI, GIRGAUM,
GRANT
ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F
7926302075
1. Secant Piling 2. Production of Tunnel Segments at Casting Yard 3. RCC Strut and Waler Beam construction at Level- 4. set up of Tunnel boring machine 5. Secant Piling 6. Reinforcement, formwork and concreting . 7. Steel Strut Design, Fabrication and Installation 8. shotcrete for cross passage, adits and cavern 9. Instrumentation and Monitoring 10. Rock Bolting 11. Shotcreting with Dry Mix 12. Utility Diversion and support 13. Traffic Decking FIGURE 7: PROJECT SCHEDULING FOR KALBADEVI STATION
22
METRO LINE 3 – PACKAGE 2 UGC02
: CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
MUMBAI
STATIONS
PROJECT TRAINING 2019-2020 3.1.1 TIME DISTNACE GRAPH FIGURE 8: TIME DISTANCE GRAPH
Bhumika Raj (UC5316) Semester-08
23 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Raj
Semester-08 PROJECT TRAINING 2019-2020 3.2 JOB LAYOUT AT CST STATION
Bhumika
(UC5316)
24 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Raj (UC5316) Semester-08 PROJECT TRAINING 2019-2020
JOB LAYYOUT AT WADALA
Bhumika
3.2.1

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

25
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020 LIST OF EQUIPMENTS S.NO DESCRIPTION MAKE MODEL CAPACITY NOS OWN LOCATION 1 DG Set Cummins CS1010D10P 1010 kva 1 Own CST Station 2 DG Set Cummins 500 kva 1 Own CST Station 3 DG Set Cummins C15 15 kva 1 Own CST Station 4 Front Loader cum Back hoe JCB 4DX 1 cubic m 1 Own Grant Road Station 5 Lathe Machine AtlasTools Shimoga 2 m 1 Own CST Station 6 Drill Rig Atlas Copco ROC 203PC 3 m 2 Own CST 7 Backhoe Loader JCB 4DX - 1 Own Grant Road 8 Crawler Pilling Rig Mait HR 130 5 ton 1 Hired CST 9 Backhoe Loader JCB 4DX - 2 Own Girgaon 10 Diesel Welding Machine ESAB EDW 200 CU - 1 Own CST 11 Hydra ACE F - 15 15 ton 1 Hired Girgaon 12 Backhoe Loader JCB 4DX - 1 Own Girgaon 13 Trailer TATA 3581 - 1 Hired CST 14 Truck EICHER 709 - 1 Hired CST 15 Excavator L & T PC200 1.2 Cub m. 8 Subcon CST 16 Gantry Crane Electromech Goliath Crane 35 ton 2 Own CST 17 Chilling Plant EU Industries TR 50 50 TR 1 Own CST 18 Crawler crane Fushun QUY80 80 ton 1 Own CST 19 Crawler Crane Zoomlion - 70 ton 1 Hired CST 20 Mobile Crane TIL RT740 B 40 ton 1 Hired Girgaon 21 Piling Rig Mait HR 180 - 2 Subcon Grant Road Station 22 Piling Rig Mait HR 130 - 1 Subcon CST 23 Piling Rig XUZHOU XR 180 D - 1 Hired Grant Road 24 Mini Excavator Genius V1020 - 3 - 1 Hired Grant Road S.NO DESCRIPTION MAKE MODEL CAPACITY NOS OWN LOCATION 25 Skid Steer Loader Bob Cat S450 - 1 Hired Grant Road 26 Dumper TATA Hyva 10 ton 2 Hired Grant Road 27 Hydra ACE F - 160 16 ton 1 Hired Grant Road 28 Trailer TATA 3518 20 ton 1 Hired CST 29 Tyre mounted shotcrete kit Palfinger PC3300 - 1 Hired CST 30 Truck EICHER 709 8 ton 1 Hired Girgaon 31 Piling Rig Mait HR 130 - 2 Subcon Girgaon 32 Grout Plant IREX - - 1 Own CST 33 Secondary Grout Pump GERTEX 1 Own CST 34 Tunnel Boring Machine Terratec T58 - 2 Own CST TUNNEL 35 Tower Crane Commansa 11CM160 8 ton 1 Own CST 36 Forklift GODREJ G800D 8 Ton 1 Own CST 37 Locomotive Atlas Copco DHD 25 25 Ton 6 Own CST Tunnel 38 Micro Pile Boring Machine Soil Mech - 10 meter 1 Own CST 39 Batching Plant Schwing Stetter M1.25 60 m3/hr Own Wadala, CST 40 DG Set Cummins - 500 Kva 1 Own Wadala 41 Gantry Crane Electromech Goliath Crane 15 Ton 2 Own Wadala 42 Gantry Crane Electromech Goliath Crane 10 Ton 2 Own Wadala 43 E.O.T. Crane Electromech - 20 Ton Wadala 44 Forklift Godrej GX150 D 1.5 Ton 1 Own Wadala 45 Trailer Mahindra & Ashok Leyland - 40 Feet 6 Hired Wadala 46 Weigh Bridge Citizen - 40 Ton 2 Own Wadala, CST
Bhumika Raj (UC5316)

3.3 METHOD STATEMENT:

There are certain documents available at site, which indicates the sequence of construction to be followed based on certain guidelines and standards. This document is called “Method Statement”.At CJV, method statements are prepared for each activity, which is to be executed at site, station wise. This is because each station has different geological strata, and hence, different type of methodology to be adopted.

 These documents are prepared by design/ Geotech engineers, which are then reviewed by managers for the respective field and approved by project manager.

 QA manager, QC manager, construction managers (Civil and Tunnel), safety manager, project manager and deputy project manager will have its controlled copies.

 They include mechanisation of machinery, required manpower, HIRA, inspection and test plan, some standard tests to be conducted, etc. items in the method statement.It also indicates contingency plan for any risk hazard, if occurred at site, then whom to contact and which person to be notified.

 It has to followed in general terms. It has to approved from MAPLE (i.e. General Consultant) staff also, before executing the work. So, for this, RFI [Request for inspection] has to be prepared by contractor representative and submitted to GC. After getting approval, the activity can be started.

 Also, method statements get reviewed by GC and MMRC staff. After certain comments, the method statement gets revised.

3.4 4. DEGREE OF MECHANISATION JUSTIFICATION:

 As the package-02 has 4 stations and a casting yard under its scope of work, the Plants and machineries required for mechanisation of work needs to be planned and for the same, the work needs to be executed at a targeted time frame, within restricted cost budget.

 So, the plant and machinery department maintain a record in excel regarding the equipments owned or hired (from subcontractor agency) by the company.

Example, refer (Table of equipments) As there is more scope of excavation in Grant road station, greater number of back hoe loaders are available at grant road station , as compared to other stations. Also, at present time, piling going is on at Girgaon station. Hence, to carry out piling we require piling rigs Hence, greater number of piling rigs are required to carry out the activity, compared to other stations and according to the demand the mechanization is carried out at different station.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
26
GRANT ROAD.
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

CHAPTER 3: CONSTRUCTION ACTIVITY REPORT

CAR 1 SECANT PILING

CAR 2 ROOF SLAB

CAR 3 CONSTRUCTION OF ADITS AND CENTRAL CAVERN

CAR 4 CONSTRUCTION OF CROSS PASSAGE

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
27
T +91 7926302470 F +91 7926302075
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

4 SECANT PILING

4.1 Scope of work:

 Setting out survey reference points for excavation.

 Preparing of polymer slurry

 Excavation of Secant pile wall

 Boring of piles

 Preparation and installation of reinforcement cage

 Constructing alternate soft piles and hard piles

 Finishing the topmost surfaces

4.2 OBSERVED ACTIVITY FLOW CHART

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 28 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Activity • SECANT PILING Location •CST STATION ANCILLARY BUILDING CROSS OVER PASSAGE NO OF PILES OBSERVED •9 (4secondary 5 and primary) SECANT PILING EXACAVATION KING POST STRUT ADN WALER MAPPING ROCK BOLTING SHOTCRETE BASE SLAB CONCOURSE SLAB ROOF SLAB ANCILLIARY BUILDING DRILLING AND BLASTING CROSS PASSAGE SUMP PASSAGE ERRECTION OF RAILS MUMBAI METRO UGC 02 STATION TEMPORARY WORKS STATIO PERMANENT WORKS TUNELLING/NATM UTILITY SHIFTING SEWAGE TREATMENT PLANT CST STATION Legend: Ongoing activities Observed activities Activities finished

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

Construction Methodology:

Bottom-Up construction (Decided based on soil strata-page 15) (Refer Drawing )

Construction methodology )( refer GIR report page 1)

No of Piles for CST station: piles [Boring, Drilling, Concreting] 10

Piles studied: SP 1489 [Total = 9 piles], No of soft piles = 6, No of hard piles= 4

Pile type: end bearing piles, cast in situ.

Reinforcement :Fe500 neo steel

Concrete:M20 for primary piles ,M40 for secondary piles

TENDER DOCUMENT SPECIFICATION(Tender Documents, Part- 2, Section-VII)

Before starting excavation, the ground water table is to be lowered inside the excavation area to at least 1.0m below the excavation level for all stages of construction and shall be maintained until the backfilling is done, or station construction is completed. The secant pile wall is made of 1000mm diameter Primary Piles (to be drilled first) in M20 grade and 1000mm diameter Secondary Piles (to be drilled overlapping with constructed primary piles) in M40 grade

Major points in BS8004

The design of foundations subject to cyclic loading should consider the following:

• Degradation of ground strength (leading to ultimate limit states being exceeded at loads below those expected from verifications based on static strength) degradation of ground stiffness, leading to an accumulation of permanent foundation displacement (“ratcheting” effects); and amplification of loads or movements owing to resonance.

Non-engineered fill, such as industrial, chemical, and domestic wastes,should not be placed beneath foundations.All materials intended to be placed behind foundations should be properly investigated and classified.

The resistance of a pile foundation in rock depends markedly on the method of pile construction and the roughness of the rock socket in which the pile is located.

As observed on site:

Sr.no Description

Non-engineered fill, such as industrial, chemical, and domestic wastes,should not be placed beneath foundations

All materials intended to be placed behind foundations should be properly investigated and classified

Followed yes or no

YES

It is disposed in BMC Sewer

YES,all the quality check on materials was done

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
29
T +91
F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
7926302470

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

4.3 Organisation chart

•The approval of method statement,over all scope of work co-ordination of personnel and equipment to ensure continuous program of work,receiving daily progress report and giving to client HCC-MMS JV management and enusring prompt action to any matter highlighted

•implementation of method statement,ensuring all personnel are aware of their duties and responsibilities.

SITE ENGINEER

•emsuring in accordance with the appproved method statement and specification ,all required as built data are recorded

SITE SUPERVISOR

•ensuring that the construction is done as per method of statement and responsible for managing all machiney tools and laboursused in driving of bores for secant piles

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
30
T
F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
exceution
station manager site engineer site supervisor support
hse QA/QC SUrVEY Station
project manager
department
department
manager
: PROJET MANAGER : STATION MANAGER :

T +91 7926302470

F +91 7926302075

Location where pile is observed

P1468,S1467,P1467,S14

66,P1466,S1465,P1465, S1464,P1464

Overlapping:130mm

From gl. 0.00 to -13m

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
31
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura
Ahmedabad – 380009, Gujarat

4.4 PROCEDURE FOR PILING

No flushing is required if polymer is used as it ensures that the soil doesn’t collapse, Polymer slurry to be poured continously

Surveyor shall set out the centre of each pile as per location and approved drawing setting out trial pit for utility identification

Trial pit of 1.5 m depth shall be done to identify presence of utility line

polymer slurry preparation

1000mm dia shall be drilled, casing the casing should be inserted inside of 1000mm dia shall be inserted inside with the hammering effect of rotary drilling.verticality to be checked with Bore hole casing with plumb

reinforceme nt for secondary pile

Reinforcement bars should be cut as per BBS ,Lap joints and lifting hook of the reinforcement cage shall be welded.

installation of casing

bore holes for soft piles

Bore holes to be drilled within the casing by cutting and removing of soil by drilling equipment auger bucket attached. horizontal tolerane-25mm vertical tolerance1 in 200

Muck generated is shifted to the designated place,its initially dumped near working area then shifted.

Tremie pipe of 250 mm dia shall be lowered in pieces and connected while lowering leaving 0.3 m above bottom level with help of rig,Concrete funnel shall be filled completely and process is carried out

Reinforcement cage to be lowered by rig /hydra.Cage shall be lowered upto required levelLifing plan is followed at site.

concreteing

muck removal

flusing concreting bore for secondary piles

No flushing is required if polymer is used as it ensures that the soil doesn’t collapse

980mm dia shall be drilled, casing the casing should be inserted inside with the hammering effect of rotary drilling.verticalit y to be checked with Bore hole casing with plumb

reinforcement

Tremie pipe of 250 mm dia shall be lowered in pieces and connected while lowering leaving 0.3 m above bottom level with help of rig,Concrete funnel shall be filled completely and process is carried out

 When reinforcement cage is ready, it shall be lifted by hydra and kept on the trailer for shifting near the piling location , also the cage should be kept on wooden runners to avoid contact with soil

 Fabricated cage should be covered in plastic when not in use for longer period

 The verticality of the casing shall be checked during the installation by plumb from two perpendicular directions .

 SOUNDING CHAIN METHOD: it used to check the measurement of depth of pile , the chain in inserted inside the pile and then removed out and its length is measured by a measure tape .

 TOLERANCE LEVEL FOR VERTICALITY : HORIZONTAL 25MM ,VERTICAL : 1 IN 200

 Reinforcement cage is prepared at WTC then brought to the site of execution.

32 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS
Kasturbhai
T +91 7926302470 F +91 7926302075
: CST, KALBADEVI, GIRGAUM, GRANT ROAD.
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
PROJECT
Bhumika Raj (UC5316) Semester-08
TRAINING 2019-2020

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

4.5 PROCEDURE SKETCH FOR PILING

CASING IS INSERTED

1 Drilling is done through auger and inserting case

2 Casing is inserted and polymer slurry is poured down

3 Auger is lifted up when hard rock is obtained.

4 Assembly of tremie and hopper is arranged for concrete works

5 Finishing works and drilling is started for secondary piles

F

T

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. Kasturbhai

MAIT 130 HR 130

M40-GRADE DRILLING IS CARRIED OUT BY AUGER

6 Drilling carried out through auger for secondary piles

7 Reinforcement cage is lowered by the rig

8 Concrete work is done in same way as done for primary piles

9 Finishing work is carried out

CASING IS REMOVED AND FINISHED IS DONE

33
380009, Gujarat
Lalbhai Campus University Road, Navrangpura Ahmedabad –
+91 7926302470
+91 7926302075
Bhumika Raj (UC5316) Semester-08
PROJECT TRAINING 2019-2020
1 2 3 4 5
6

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

4.6 BBS FOR PILE( S1467)

T

5: BBS FOR PILE

34
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316)
ABLE
COVER 40 SR. NO. DESCRIPTION Shape DIA. DIA. OF BAR CUT LENGTH SPACING NO. OF RINGS SIM NO. TOTAL LENGTH 8mm 10mm 12mm 16mm 20mm 32mm L = 13.5 1000 MAIN RINGS 1 UPTO 2M(BUNDLED RINGS 920 16 6833.6 95 23 1 157.17 157.17 2 >2M 920 12 3384.8 115 101 1 341.8648 341.86 3 VERTICAL BARS 32 13.5 20 1 270 270 4 MASTER RING 824 16 2987.36 1600 9 1 26.88624 26.88624 TOTAL LENGTH 341.86 184.059 270 WEIGHT(Kg/m) 303.8798 290.8587 0 1706.667 2301.405 BBS FOR PILE( S1465) SR. NO. DESCRIPTION Shape DIA. DIA. OF BAR CUT LENGTH SPACING NO. OF RINGS SIM NO. TOTAL LENGTH 8mm 10mm 12mm 16mm 20mm 32mm L = 13.5 1000 MAIN RINGS 1 UPTO 2M(BUNDLED RINGS 920 16 6833.6 95 23 1 157.17 157.17 2 >2M 920 12 3384.8 115 101 1 341.8648 341.86 3 VERTICAL BARS 32 13.5 20 1 270 270 4 MASTER RING 824 16 2987.36 1600 9 1 26.88624 26.88624 TOTAL LENGTH 341.86 184.059 270 WEIGHT(Kg/m) 303.8798 290.8587 0 1706.667 2301.405

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

4.7

Inference: cement used is in the maximum quantity while flyash is used in least quantity in construction of pile

Highest depth observed is 13.5

Minimum depth obtained is 9.3

35
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
M20 M40 MATERIALS MIXDESIGN FOR7.8 m3 WASTAGE MIX DESIGN FOR 9m3 WASTAGE CEMENT 240 1872 1909.44 350 3150 3213 FLYASH 140 1092 1113.84 120 1080 1101.6 20MM AGGREGATE 167 1302.6 1432.86 667 6003 6603.3 10MM AGGREGATE 446 3478.8 3826.68 443 3987 4385.7 SAND 750 5850 6435 686 6174 6791.4 WATER 178 1388.4 175 1575 1732.5 SIKA VISCOCRE 0 5.64 50.76 55.836 SIKA PLAST 5.13 40.014 FOR CEMENT WASTAGE : 2% , AGGREGATES AND SAND WASTAGE : 10% TABLE 6: MATERIAL CONSUMPTION PILE NUMBER HEIGHT SOIL ROCK CONCRETE (����2��) P1468 9.3 9 0.3 7.3 S1467 13.5 13 0.5 10.59 P1467 9.3 9 0.3 7.3 S1466 10.5 10 0.5 8.24 P1466 11 10.5 0.5 9.46 S1465 13.5 13 0.5 10.59 P1465 11 10.7 0.3 9.46 S1464 10.5 10 0.5 8.24 P1464 11 10.5 0.5 9.46 PRIMARY PILE SECONDARY PILE DEPTH( AVERAGE) 9.94 11.5 CONCRETE REQUIRED 7.8 9.0
MATERIAL CONSUMPTION:

4.8 Data entry done for pile- P1489

Table 7:data entry for piles

After grade 4 is obtained , penetration is continue for more 50-60 mins to ensure the pile is embedded in the hard rock.

WEIGHT OF ONE CAGE _1.8 Metric ton( as shown in machine)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
36
ROAD.
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
Duration Depth From to from to Total drilling min Total depth ROP (m/min) Strata description 9:30 9:45 00 2.5 15 2.5 0.16 9:45 10:00 2.5 4 15 1.5 0.1 10:00 10:15 4 5 15 1 0.06 10:15 10:30 - 15 -10:30 10:45 5 5.8 15 0.8 0.05 10:45 11:00 5.8 6.6 15 0.8 0.05 11:00 11:15 6.6 7.2 15 0.6 0.04 11:15 11:30 7.2 7.8 15 0.6 0.04 11:30 11:45 7.8 8.1 15 0.3 0.02 GRADE 4 11:45 12:00 8.1 8.4 15 0.3 0.02 12:00 12:15 8.4 8.7 15 0.3 0.01 12:15 12:30 8.7 8.9 15 0.2 0.01 12:30 12:45 8.9 9.1 15 0.2 0.01 12:45 13:00 9.1 9.2 15 0.1 0.01 13:00 13:15 9.2 9.3 15 0.1 0.01 REMARKS : Depth of the pile (P 1489) is 9.3 m.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

4.9 TIME CYCLE

Table 8: time cycle analysis for primary piles

4.10

TABLE 9: TIMECYCLE FOR SECONDRY PILES

AS PER OBSERVATION: TIME CYCLE

37
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
Kasturbhai
T
F
TIMECYCLE FOR SECANT PILE PRIMARY AT CST STATION description quantity unit Rate of production Time required for othrt activities Time for piling rig Time required for crane total 1 Survey and setting out works 1 0.50 0.50 2 Positioning of piling rig 1 nos 0.50 0.50 3 Boring 4 In soft rock 10 M 4m/hr 2.50 2.50 5 In rock 2 M 1m/hr 2 2 6 Shifting of rig 0.50 0.50 1 7 Placing of tremie pipe 1 No 7cum/hr 0.14 0.14 8 Placing of concrete 11 Cum 7cum/hr 1.55 1.55 9 Extractiong of casing ring 0.25 0.25 10 Total time required for continuous piling @ 10 % contigency 6.05 11 Total piles required@20hrs/day 3.64 No of piles per day per rig 3
TIME CYCLE FOR SECANT PILE SECONDARY AT CST STATION description quantity unit Rate of production Time required for othrt activities Time for piling rig Time required for crane total 1 Survey and setting out works 1 0.50 0.50 2 Posiyioh of piling rig 1 nos 0.50 0.50 3 Boring 4 In soft rock 10 M 4m/hr 2.50 2.50 5 In rock 2 M 1m/hr 2 2 6 Shifting of rig 0.50 0.50 1 7 Placing of reinforcement cage 11 Cum 7cum/hr 1.55 1.55 8 Placing of tremie 1 NO 7cum/hr 0.50 1.55 9 Placing of concrete RCC 0.25 0.25 10 Total time required for continuous piling @ 10% contigency 6.05 3.08 9.13 Total piles required@20hrs/day 3.64 No of piles per day per rig 3

TABLE 10: TIME CYCLE ANALYSIS AS PER OBSERVATION ( PRIMARY PILES)

Note : GREY part shows the variation observed on

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 38 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
T
F
STATION(P1489) Description quantity unit Rate of production Time required for othrt activities Time for piling rig Time required for crane total 1 Survey and setting out works 1 0.50 0.50 2 Positioning of piling rig 1 nos 0.50 0.50 3 Boring 4 In soft rock 10 M 4m/hr 2.50 2.50 5 In rock 2 M 1m/hr 2.5 2.5 6 Shifting of rig 1 1 2 7 Placing of tremie pipe 1 No 7cum/hr 0.30 0.30 8 Placing of concrete 11 Cum 7cum/hr 1.55 1.55 9 Extractiong of casing ring 0.25 0.25 10 Total time required for continuous piling @ 10 % contigency 6.05 11 Total piles required@20hrs/day 2 No of piles per day per rig 2
11:TIME CYCLE ANALYSIS
PER OBSERVATION ( SECONDARY PILES) TIME CYCLE FOR SECANT PILE SECONDARY AT CST STATION(S1466) description quantity unit Rate of production Time required for othrt activities Time for piling rig Time required for crane total 1 Survey and setting out works 1 0.50 0.50 2 Positioning of piling rig 1 nos 1 1 3 Boring 4 In soft rock 10 M 3 3 5 In rock 2 M 2.5 2.5 6 Shifting of rig 0.50 0.50 1 7 Placing of reinforcement cage 11 Cum 0.30 2 2.30 8 Placing of tremie 1 NO 2 2 9 Placing of concrete RCC 0.50 0.50 10 Total time required for continuous piling @ 10% contigency 8.30 5 13.30 Total piles required@20hrs/day 1.5 No of piles per day per rig 1
TIMECYCLE FOR SECANT PILE PRIMARY AT CST
TABLE
AS
site.

4.11 AS PER OBSERVATION

CHART TITLE

primary pile TIME TAKEN (Hrs)secondary pile

Placing of tremie

Placing of reinforcement cage

Shifting of rig

In rock

In soft rock

Inference:

Posiyioh of piling rig

Survey and setting out works

Placing of concrete RCC time taken(hours)

 P1489, DATE :16 january 2020 , P1466 DATE 20 january 2020

 Placing of Tremie in took longer time because appropriate size of tremie was not available on time.

 Placing of concrete took longer time because concrete mixer was not available at site on time

 Due to unfavourable conditions on site i.e. mud disposal positioning of rig became difficult.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
39
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
Kasturbhai
T +91 7926302470 F +91 7926302075
0 0.5 1 1.5 2 2.5 3
activity description

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJ CODE NO:-UC5316

PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02)

Measurement Sheet

Providing boring for rcc cast in situ piles including withdrawl of shell, cleaning removal of earth to a distance upto 50m of dia 1000mm at CST station etc complete as directed by general consultants

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
CST, KALBADEVI,
ROAD. 40
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075 TABLE 12: RATE ANALAYSIS FOR EXCAVATION OF PILE
STATIONS :
GIRGAUM, GRANT
Kasturbhai
T
F
Item No Item Description Unit Qty Rate Amount
Rmt A. Material B Labour Skilled no 3 60 ₹180 Unskilled no 6 50 ₹300 C Piling rig no 4 2010 ₹8040 Dumoper no 2 600 ₹1200 Back hoe loader no 2 664 ₹1328 D water and electricity cost(1% of A+B) ₹110.48 E Miscallaneous(2% of A+B) ₹223.1696 0 F Overhead charges and profit 0 ptofit 10% of A+B+C+D ₹1138.165 total 12m ₹12519.81 Z for 1 m ₹/m ₹1043.318

TABLE 13: RATE ANALYSIS FOR REINFORCEMENT OF PILE(SECONDARY)

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

BHUMIKA RAJ

PROJECT TRAINING 2019-2020

Measurement Sheet

Providing and laying reinforcement bars of fe500 grade for secant piles as per drawings including cutting ,welding tieing with binding wires ,assembling etc and providing 40 mm cover as engineer in charge and General consultants authority etc( for 3 piles of length 13.5 m)

CODE NO:-UC5316

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
CST, KALBADEVI,
41
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470 F +91 7926302075
STATIONS :
GIRGAUM, GRANT ROAD.
Kasturbhai
T
Item No Item Description Unit Qty Rate Amount Remarks
kg A. Material steel (2% wastage) JSE NEO STEEL kg 49263 40 1970520 binding wire 18 gauge(9KG is used per tonne) kg 46.44 50 2322 1tonne=1000kg cover block (4% wastage) pieces 192 4 768 B Labour operator man/day 3 1200 ₹3600 skilled man/day 5 660 ₹3300 unskilled man/day 6 540 ₹3240 ₹1983750 C Machines and equipments piling rig hours 1 6200 ₹6200 oxygen cutting/welding hours 2 625 ₹1250 D water and electricity cost(1% of A+B) ₹198375 E miscallaneous(2% of A+B) ₹243.28 Total ₹2189818.28 Cost per kg Kg/₹ ₹44.45

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

RAJ CODE NO:-UC5316

PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02)

Providing and laying CONCRETE OF M40 grade for secondary piles of secant piles for specified depth inlcuding transportation, pouring, casing with tremie pipe finishing etc as per the direction of engineer incharge. For 9 m3 cum A. Material

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 42
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
TABLE 14: RATE ANALYSIS FOR CONRETE
BHUMIKA
NAME:-
Sheet Item No Item Description Unit Qty Rate Amount Remarks
Measurement
M40 GRADE concrete (5% wastage) cum CEMENT opc 53 kg 3213 7 ₹22491 FLYASH (class c) kg 1101.6 1 ₹1101.6 20mm aggregate kg 6603.3 0.82 ₹5414.706 10mm aggregate kg 4385.7 0.82 ₹3596.274 SAND( crushed) kg 6791.4 0.9 ₹6112.26 Sika viscocre kg 55.836 93 ₹5192.748 ₹43908.59 B Labour operator man/day 2 1150 ₹2300 unskilled man/day 4 350 ₹1400 ₹3700 C Machines and equipments transit mixer rs /hr 2 623 ₹1246 Pile rig 1 6200 ₹6200 D water and electricity cost(1% of A+B) ₹476.0859 E miscallaneous(2% of A+B) ₹952.1718 F Overhead charges and profit (10% of A+B+C+D+E) ₹4903.685 for 7.8 ₹53940.53 for 1m3 ₹/m3 ₹6915.453

PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02)

Providing and laying CONCRETE OF M20 grade for primary piles of secant piles for specified depth inlcuding transportation, pouring, casing with tremie pipe finishing etc as per the direction of engineer incharge.(7.8m3)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
43
T +91 7926302470 F +91 7926302075 TABLE 15:RATE ANALYSIS FOR CONCRETE
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
NAME:- BHUMIKA
CODE NO:-UC5316
SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY
RAJ
Item No Item Description Unit Qty Rate Amount Remarks
Measurement Sheet
cum A. Material M40 GRADE concrete (5% wastage) cum CEMENT kg 1909.44 7 ₹13366.08 FLYASH(tata) kg 1113.84 1 ₹1113.84 20MM AGGREGATE kg 1432.86 0.82 ₹1174.945 10MM AGGREGATE kg 3826.68 0.82 ₹3137.878 SAND kg 6435 0.9 ₹5791.5 SIKA PLAST kg 44.0154 93 ₹4093.432 B Labour 0 operator man/day 2 2000 ₹4000 skilled man/day 2 600 ₹1200 unskilled man/day 6 420 2₹520 ₹36397.68 C Machines and equipments 0 transit mixer rs/hour 2 626 ₹1252 rig rs/hour 1 6200 ₹6200 D water and electricity cost(1% of A+B) ₹363.9768 E miscallaneous(2% of A+B) ₹727.9535 F Overhead charges and profit ptofit 10% of A+B+C+D+E ₹4494.161 for 9m3 49435.77 for 1m3 ₹/M3 ₹₹5492.863

4.12 ABSTRACT SHEE

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020

ABSTRACT SHEET

Providing empty boring rcc cast in situ piles including withdrawl of shell, removal of earth to a distance upto 50m of dia 1000mm etc com plete as directed by engineer in charge( refer pg no.40)

Providing and laying CONCRETE OF M20 grade for primary piles of secant piles for specified depth inlcuding transportation, pouring, casing with tremie pipe finishing etc as per the direction of engineer incharge.(7.8m3)( refer pg no.41)

providing and laying reinforcement bars of fe500 grade for secant piles as per drawings including cutting ,welding tieing with binding wires ,assembling etc and providing 40 mm cover as engineer in charge and General consultants authority etc( for 3 piles of length 13.5 m)( refer pg

Providing and laying CONCRETE OF M40 grade for secondary piles of secant piles for specified depth inlcuding transportation, pouring, casing with tremie pipe finishing etc as per the direction of engineer incharge. For 9 m3( refer pg no.43)

INFERENCE : maximum cost is observed for reinforcement as the cage made for piling is dense, while concreting is also done for entire volume of pile and excavation consumes less cost as only no resources are used except rotary driller

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 44
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
Kasturbhai
T
F
Item No Item Description Unit Qty Rate Amount
1
Rmt 12 1043 ₹12519.81 2
Cum. 9 5492.863 ₹49435.77 3
no
Kg 49263 44.45 ₹2189818.28 4
42 )
Cum. 7.8 6915.453 ₹53940.53 EXACAVATION 4% CONCRETE 33% REINFORCEME NT 63% COST BREAKDOWN EXACAVATION CONCRETE REINFORCEMENT

LABOUR PRODUCTIVITY

LABOUR PRODUCTIVITY*LABOUR PRODUCTIVITY FOR 1 PILE

4.13 ACTIVITY ANALYSIS

For one primary pile

for excavation– rs1043

Cost of concreting – rs. 10709 Total cost – rs. 11752

depth of pile – 9.94• Average volume of concreting – 7.8m3

4.14

4.15

TOTAL NO OF PILES IN ANCILLARY BUILDING AREA AT CST AREA WHERE BUILDING IS OBSERVED IS:

4.16

52 PRIMARY

TOTAL COST OF EXCAVATION =54236

TOTAL COST OF CONCRETING -556868

TOTAL COST OF REINFORCEMENT –

TOTAL COST Rs. 611104

50 SECONDARY

TOTAL COST OF EXCAVATION =52150

TOTAL COST OF CONCRETING -777937

TOTAL COST OF REINFORCEMENT –rs 4821150

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 45
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470 F +91 7926302075
TOTAL HOURS LABOURS TOTAL MAN HOURS(REFER TIMECYCLE QTY PRODUCTIVITY EXACAVATION SKILLED 6 2 12 12 1 UNSKILLED 6 3 18 12 0.67 REINFORCEMENT SKILLED 2.3 3 6.9 2301 333.48 UNSKILLED 2.3 6 13.8 2301 166.74 CONCRETE(SP) SKILLED 2.5 2 5 7.8 1.56 UNSKILLED 2.5 4 10 7.8 0.78 CONCRETE(PP) SKILLED 2 2 4 9 2.25 UNSKILLED 2 4 8 9 1.125
Cost
Average
For one secondary pile cost of reinforcement – rs.96423 Cost of concreting – rs. 15558.75 Total cost – rs. 1,13243 Average depth of pile – 11.5 Average volume of concreting – 9m3

4.17 EQUIPMENT DETAIL

 Koden is an ultrasonic device used for measuring the depth,it’s a highy expensive machine used in large scale projects.

 It is placed above the hole from where the sensor unit is lowered down and the winch unit is placed above the hole with the help of support

 Its highly accurate so it used.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS
46
: CST, KALBADEVI, GIRGAUM, GRANT
ROAD.
PROJECT TRAINING
Bhumika Raj (UC5316) Semester-08
2019-2020
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
1300 1500 1200 500 1500
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 47 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
HAZARD RISK LEGAL SEVERITY PROBABILITY S*P RISK LEVEL Control measures Boring Activity by using rotary machine and driving of cassion Presence of underground services such as electrical lines and gas pipe lines or water pipe line Electrocution and explosion or personal injury yes 5 3 15 High risk Drawing of utility services should be studied and always available with site person Uncovered bore holes Fall of person yes 5 3 15 High risk All piling bore hole should be covered Fall of cassion Hit by the object no 5 1 5 High risk Cassion should be secure and fixed during driving Only authorized operator /trigger should be allowed. Unauthorized enty prohibited. Shifting of reinforcement cage to piling site from reinforcement yard Exposed reinforcement or extended reinforcement from vehicle Personal injury of property damage yes 5 3 15 High risk Long vehicle should be used for lifting the reinforcement. Reinforcement should be made near topiling site. For Lowering of reinforcement cage in to bore hole with the help of crane Working at congested area Toppling of crane Yes 5 3 15 High risk Working space for crane should not have obstruction. Wprking area should levelled and compacted. Uncontrolled swing Personal injury of property damage no 4 2 8 Medium risk Tag lineshould be used for controlling his swing Swinging area should be barricaded. Pouring concrete with hopper tremie pipe Improper placement of hopper Personal injury no 3 2 6 Medium ridk During concreting it is assured that hopper tremie pipe is properly placed Exacavation Exposure to dust Lung disease /eye irritation no 4 2 8 Medium risk Use dust mask and goggles House keeping Improper house keeping Slip and trip causing injury yes 4 4 16 High risk Daily cleaning work place and maintain good housekeeping Working at night Insufficient illumination May cause discomfort for working at night no 3 3 9 Medium risk Lights should be planned prior to start of activity and placed at every corner of the work Location to avoid shadow
4.18 HIRA Table 16: HIRA

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5 ROOF SLAB

•slab : reinforcement ,concrete , formwork and water proofing

5.1 SCOPE OF WORK

FORMWORK AREA:1108m2 (including bottom and sides)

CONCRETE AREA:913 m3

REINFORCEMENT: 82000kg

5.2 OBSERVED ACTIVITY FLOW CHART

MUMBAI

covered area _ grid 6 to grid 8

SECANT PILING

EXACAVATION

KING POST

STRUT ADN WALER

MAPPING

ROCK BOLTING

SHOTCRETE

CONCOURSE SLAB

ANCILLIARY

DRILLING AND BLASTING

CROSS PASSAGE

SUMP

Legend:

Ongoing activities

Observed activities Activities finished Activities yet to be started

METRO LINE 3 – PACKAGE 2 UGC02
MUMBAI
48
F +91 7926302075
Kasturbhai
Lalbhai Campus
University Road,
Navrangpura
Ahmedabad – 380009, Gujarat T +91 7926302470
BASE SLAB
ROOF SLAB
BUILDING STATION WALLS
PASSAGE ERRECTION OF RAILS
METRO UGC 02 STATION TEMPORARY WORKS STATIO PERMANENT WORKS TUNELLING/NATM UTILITY SHIFTING SEWAGE TREATMENT PLANT CST STATION Activity
Location
CST STATION
ROOF SLAB LEVEL: -4.91

5.3

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
49
ROAD.
380009,
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat
ORGANISATION CHART project manager exceution department station manager site engineer site supervisor support department hse QA/QC SUrVEY Station manager
MUMBAI
LINE 3 – PACKAGE 2 UGC02
KALBADEVI,
50
METRO
STATIONS : CST,
GIRGAUM, GRANT ROAD.
PROJECT TRAINING
Bhumika Raj (UC5316) Semester-08
2019-2020
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

ENTRY POINT 1

ENTRY POINT 3

ANCILLARY BUILDING

MUCK DISPOSAL AREA

PORTION LEFT TO BE CASTED DURING LAUNCHING SHAFT

CONSTRUCTED PORTION UPTO ROOF SLAB

OBSERVED PART

PORTION LEFT TO BE CASTED

GANTRYS ARE PLACED IN THAT SECTION TUNNEL DOWNLINE AND UPLINE 22.8

ENTRY POINT 2

– PACKAGE 2 UGC02
51
MUMBAI METRO LINE 3
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
PROJECT TRAINING
Bhumika Raj (UC5316) Semester-08
2019-2020
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat 5.4 JOBLAYOUT 5.5
250M

5.6 METHODOLOGY

Wooden ply of 12 mm thickness of sizes are laid they are further given support by props and U jacks and wooden planks so all the sizes are joined together.

Wooden shuttering ply should be in alignment and sizes used is 1.22*2.44 for one ply sealed with tape

And foam sheets shall be provided at joint gaps to prevent leakage of slurry

Concrete of m50 grade is provided

According to pour plan the concrete pimp set up is done by using gi pipes,All the pipes are laid and concreteing is started .Prior to concrete about 0.5 to 1 cum of cement slurry shall be pumped to lubricate pipe

Needle vibrator of 3 different types were used , 40,60,80 mm are used

Aluminiumn hollow box is used curing

PRE-REQUISITE

• Surface should be clean

• Panels surface (ply) to be oiled before placement

STAGING SHUTTERING REINFORCEMENT CONCRETE CURING

Staging should be carried out as per the drawings .

Cup lock system is used .

Deshuttering is done after 24-48 hours

First base jack , verticals and u jack is errected, above that I section and RHS are errected

Wooden planks of size are laid and on the top rests wooden ply of 12 mm thickness( refer pg no 53 )

Prior to reinforcement shuttering oil should be applied

All staging should be checked

Rebar construction shall be done done at construction depot

Rebars shall be lowered to required level with help of crawler crane as per bar marking

Bottom bars are first place and after that top bars are placed

18 gauge wire is used to tie the bars and cover blocks

After completion of bottom mat chairs bars of size are provided over bottom reinforcement

Joint check to be done by gc after tying activity

Foam sheet shall be packed at joint gaps to prevent leakage of slurry(( refer pg no.54)

Hessian clotshall be placed and covered with polytehen sheet

It should be kept damp and after 24 hours area shold be pounded of water for 7 days

POST-REQUISITE

• Curing

• Surface should be clean

• Waterproofing

Moist Curing is carried out by using hessian cloth and then after 24 hours cloth and polythene sheet are removed and area shall be pounded with bund for 7 days

Clause 13.5 is code

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 52
PROJECT TRAINING
Bhumika Raj (UC5316) Semester-08
2019-2020
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat F IGURE 9: REINFORCEMENT YARD LOCATION
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
ROAD. 53
GRANT
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
T +91 7926302470 F +91 7926302075
SCAFFOLDING DETAIL
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
380009, Gujarat
5.7
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
ROAD. 54
GRANT
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
T +91 7926302470 F +91 7926302075 5.7.1 REINFORCEMENT DETAILS PEDESTAL NAME SPACING SHAPE 445 DIA 40 @125 C/C 368 DIA 40@125C/C 368A DIA 40 125C/C
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
380009, Gujarat
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 55 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
T
F
PLAN
5.9 POUR
OF ROOF SLAB

5.10 MATERIAL TESTING DETAILS

MATERIAL TESTING DETAILS SR

HENCE

SOUNDESS

TABLE 17: MATERIAL TESTING DETAILS

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 56
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
Kasturbhai
T
F
. NO TEST SPECIFICATIONS ACCORDING TO IS RESULT OBTAINED ON SITE FINESS OF CEMENT TEST AS PER IS 4031-1968 1.30 LESS THEN 10 CONSISTENCY AS PER IS 4031-1968 NEEDLE PENETRATION (5-7 mm) 6mm FINAL AND INITIAL SETTING TIME Initial setting time-min 30 minutes Final setting time-max 600 minutes Initial setting time-160 Final setting time-28
OF CEMENT AS PER IS 4031-1968 Le chatelier apparatus Difference in indicator-< 10mm Observed-0.933mm CEMENT COMPRESISIVE STREGTH 9 cubes casted at 3, 7, 21 daysstrength not less than 22 Mpa – 3 DAY 33 Mpa- 7 DAY 43 Mpa- 21 DAY 34.27 Mpa – 3 DAY 46.33 Mpa- 7 DAY 63.30 Mpa- 21 DAY
FINESNESS OF FLYASH
THE TESTS CARRIED OUT ON CEMENT WERE PASSED

COST BREAK UP

5.11 ACTIVITY WISE COST BREAK UP

Inference:Char4 :In item wise cost break up , the highest cost is found in material followed by labour as they Constitute a major role in progress of activity.

Char 2: in total cost beak up, concrete holds 47% as the depth of slab was 1m and reinforcement holds 43 % percentage as heavy Reinforcement was used for roof slab.

TABLE 18: LABOUR PRODUCTIVITY ROOF SLAB

5.12 Labour productivity ( pour 6)

PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
T +91 7926302470 F +91 7926302075
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
57
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
ACTIVITY ELEMENT MATERIAL LABOUR COST TEP SCAFFOLDING PROFIT TOTAL COST formwork ROOF SLAB 332955 605355 7500 204832 78378 1071329 concrete 4321422 71200 114606 - 464332 5040396 reinforcement 3316900 3513700 157392 - 359488 4600289 TOTAL 7971277 4190255 279498 204832 902198 10712014
skilled Unskilled Man day total man/days total man/days quantum Productivity skilled Productivity unskilled STAGING 15 15 8 120 120 5125 42.70 42.73 SHUTTERING 15 15 6 90 90 545 6.05 6.05 REINFORCEMENT FIXING AND CHECKING 25 15 8 200 120 82000 410 683.33 CONCRETE 35 40 1 35 40 915 26.14 22.87 total 90 85 23 STAGING SHUTTERING REINFORCEMENT FIXING AND CHECKING CONCRETE 0 50 100 150 200 250 300 350 400 450 labour productivity (skilled) Series1 4190255 279498 204832 902198 7971277 0 1000000 2000000 3000000 4000000 5000000 6000000 7000000 8000000 9000000 ITEM
MATERIAL PROFIT AND OVERHEAD CHARGES SCAFFOLD TEP labour cost 10% 47% 43% 0% TOTAL COST formwork concrete reinforcement STAGING, 42.70833333 SHUTTERING, 6.055555556 REINFORCEMENT FIXING AND CHECKING, 683.3333333 CONCRETE, 22.875 0 100 200 300 400 500 600 700 800 STAGING SHUTTERING REINFORCEMENT FIXING AND CHECKING CONCRETE Labour productivity (unskilled) Series1

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.13 TIME CYCLE ANALYSIS

TABLE 19: TIME CYCLE ANALYSIS ROOF SLAB

DURATION OF ACTIVITIES(OBSERVED)

*There are 2 shifts – day and night with each shift of 12 hours including 2 hour break

Total time cycle as observed is of 31 days for one pour of roof slab at CST station

Table 20: Time cycle break up.(pour wise)

Inference: compared to the planning by contractor (HCC) Total time taken was 96 days till back filling And 76 days till water proofing.As per observation on site for pour 6 there was less time taken which is 71 days till its water proofing, because foreman were available,Machines and equipments were available on time and were efficient ,staging and fixing was carried out in full fledge due to availability Of workers on site. Rebars were transported to site on timely basis from WTC.

Kasturbhai

STAGING SHUTTERING REINFORCEMENT FIXING AND CHECKING CONCRETING OF SLAB CHART:

Column1 days as oberved time days(schedule)

CHART:

Bhumika Raj (UC5316) Semester-08 PROJECT TRAINING 2019-2020

7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91
58
SR. NO DESCRIPTION QTY WORKING HOURS PRODUCTIVITY DURATION START FINISH As per observation on site STAGING 5125 171 29.97076023 8 0 8 SHUTTERING 545 125 4.36 6 8 14 REINFORCEMENT FIXING AND CHECKING 82 288 0.284722222 8 14 30 CONCRETING OF SLAB 816 22 37.09090909 1 30 31
0 5 10 15 20 25 staging fixing shuttering reinforcement concrete blind strut curing strut removal1 water proofing time cycle analysis ( observed vs scheduled by contractor)
8 6 8 1 0 1 2 3 4 5 6 7 8 9 activities
BY ACTIVITIES
1 TIME TAKEN
(DAYS)
3: COMPARISON BETWEEN TIME TAKEN AS PER OBSERVATION AND AS PER CONTRACTOR CHART: 2:AS PER CONTRACTOR

TABLE 21: ANALYSIS FOR ENTIRE STATION LENGTH

5.14 ANALYSIS OF ROOF SLAB FOR ENTIRE STATION LENGTH ( pour 6) total grid lines 25 are there one pour covers 2.5 grid lineTotal pour to be done : 10

for one pour entire roof slab Of CST

length of entire station 250m length of 1 pour=25m so total pour to be done are 10 for entire station length

From the above data we can say that it would take 310 mandays and rs.107120140 to complete all roof slabs at CST station

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 59 Kasturbhai
Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 element formwork concrete reinforcement F/C R/C roof slab 1108 915 82000 1.210929 89.61749 ACTIVITY TOTAL COST FOR ALL SLABS formwork 1071329 10713290 concrete 5040396 50403960 reinforcement 4600289 46002890 TOTAL 10712014 107120140
Lalbhai
skilled workers 90 900 unskilled 85 850 time taken( TILL CONCRETE) 31 310 cost 10712014 107120140

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.15 ALTERNATIVE SUGGESTION

OBSREVATION :15% OF COST SAVING CAN BE DONE IF COUPLERS ARE USED

TABLE 22:RATE FOR COUPLERS

40 DIA REBAR MATERIAL 24653*40=986120

INCREASE IF LAPPING IS PROVIDED 1187956

IF COUPLERS ARE PROVIDED 1001416

DIFFRENCE 186540

DIFFRENCE IN % 15%

TABLE 23: PROVIDED ALTERNATIVES

Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
60
Kasturbhai

5.16 ACTIVITY OVER VIEW

5.17 Construction of adit and central cavern by NATM methodology

 Element: Adit 3 between gridline 5 & 7 and central cavern

 Location: upline tunnel at kalbadevi station.

 Clear width: 6 m

 Length of entire adit :23.5M

 Width of cavern:9.5

 Grade of Concrete for shot crete: M35

 Grade of Steel for wire mesh: Fe500D : 150*150*6 mm

 Diameter of rebars for rock bolts: 32mm dia

 Blasting : explosive name – ideal power 90

 Electronic detonators

 Soil strata: grade 2 rock

Quantum of work observed for Adit

 Total excavation:167 m3

 Total shotcrete:37.5m3

 Total explosives :35.36kg

Quantum of work observed for central cavern

 Total explosives :86 kg

5.18 NATM PROCEDURE

New Australian tunnelling method is adopted at places when one has to widen the areawhere underground works are to be carried out and there is no sufficient space available on top for carrying out the activity.It is carried out by the drilling charging and blasting.At Mumbai metro line 3, UGC-02 it is carried out at kalbadevi station which is completely underground.

Main parameters to be kept in mind while carrying out NATM are:

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 61 Kasturbhai
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura
ROCK STRATA AT THAT AREA WATER TABLE INSTRUMENTATION AND MONITORING SAFETY OF WORKERS VENTILATION AIR CONTROL MONITORING TYPE EXPLOSIVES USED

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.19

OBSERVED ACTIVITY LOCATION

Raj (UC5316)

PROJECT
380009, Gujarat T +91 7926302470 F +91 7926302075
Bhumika
Semester-08
TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
62
ALIGNMENT PLAN

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.20 ADITS AND CENTRAL COVERN PLAN

PROJECT
T +91 7926302470 F +91 7926302075
Bhumika Raj (UC5316) Semester-08
TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
63

5.21 Organisation chart

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 64 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
tunnel works PRELIMINARY ACTIVITIES FEASABILI TY SRUDY SELECTION OF AGENCIES PLANNING DESIGN EXECUTIO N LAUNCHIN G OF TBM INTIAL DRIVE MAIN DRIVE NATM CROSS PASSAGES ADITS ADIT 1 ADIT 2 ADIT 3 SHOTCRET E WIREMES H ROCK BOLT ADIT 4 ADIT 5 ADIT 6 ADIT 7 SUMP PASSAGE CENTRAL CAVERN DRILLING AND BLASTING WORKS QUALITY INSPECTIO N MISCALLA NEOUS LAYING OF TRACKS / VENTILATI ON ETC Observed activity project manager execution tunnel manager site engineer site supervisor support geotechincal geologist instrumentation and monitoring survey manager surveyor qa/ac quality enginner construction manager NATM

5.22 STRATIGRAPHY OF SOIL CONDITION AT KALBADEVI STATION ACCORDING TO THE GEOLOGICAL INVESTIGATION REPORT

Geological setting as per face mapping and probing

Conclusion: During the TBM excavation frequent probing & face mapping was carried out for Kalbadevi station.The geological profile shown below is based on mapping & probing data, RMR at the tunnel face varies here from 64 to 71 thus good quality basalt (grade II) is considered at the excavation face of NATM tunnels as well.

T

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
65
GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
F +91 7926302075
FIGURE 10: GEOLOGICAL PROFILE AT KALBADEVI STATION

5.23 GEOLOGICAL PROFILE DETAILS (KALBADEVI )

TABLE 24: GEOLOGICAL DETAILS AT KALBADEVI

During the TBM excavation frequent probing & face mapping was carried out for Kalbadevi station.The geological profile shown below is based on mapping & probing data, RMR at the tunnel face varies here from 64 to 71 thus good quality basalt (grade II) is considered at the excavation face of NATM tunnels as well.

T +91 7926302470

F +91 7926302075

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
66
GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat FIGURE 11: DIMENSIONS FOR ADITS

5.24 DESIGN METHODOLGY

Analytical methods are based on RMR system.

FEM based analysis uses 2D FEM models with construction stages to work out the stability of the construction process for NATM tunnels and ensure the adequacy of primary supportGround water table is considered at ground level and maximum surcharge is considered asper actual of maximum 130 KPa at foundation level, assuming 10 storey building. The relaxation,capacity of the rock is estimated from the Panet‐ Chern theory.

5.25 Analytical Approach

The RMR‐system

a) Uniaxial compressive strength

b) RQD

c) Spacing of discontinuities

d) Condition of discontinuities

e) Ground water conditions

f) Orientation of discontinuities

The RMR of the rock is worked out as per the above properties and the support is designed for 22 considered excavation using following GUIDELINES FOE

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 68 Kasturbhai Lalbhai
University Road,
Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
Campus
Navrangpura
T
F
ROCK MASS EXCAVATION ROCK BOLTS SHOTCRETE STEEL RODS 1 VERY GOOD RMR 81-100 Full face 3 m advance Generally
rock bolting II GOOD ROCK RMR 61-80 Full face 1-1.5 m advance Complete support 20m from face 3-2m long bolts spaced 2.5 mm with ocassional wire mesh 50m crown where required none III FAIR ROCK RMR 41-60 Top heading and benching 1.5-3 m advance in top heading Systematic bolts 4m long spaced 1.5-2 m in crown with wire mesh 100-150mm
crown Light to
ribs spaced 1.5 m where required
METHODOLOGY ANALYTICAL FEM
EXCAVATION AND SUPPORT SPANNING 10 M IN TUNNEL ACCORDING TO RMR METHOD
no support required except
in
medium
Table 25: RMR TAB Note-Yellow highlight shows the grade of rock observed at kalbadevi

5.26 INSTRUMENTATION AND MONITORING

• 3D Targets

• Strain gauges

The 3D Targets –FUNCTION

For 3D Targets, the total station used for the monitoring should measure up to the required precision level. To obtain accurate results both high quality 3D targets and a high precision total station are required. For typical details monitoring instruments and procedures reference shall be taken to design manual and NATM specification.

The 3D Targets –LOCATION

5.27 They are located at the periphery of the face of excavation, one on

3D OPTICAL TARGETS

3D OPTICAL TARGETS

3D OPTICAL TARGETS

3D OPTICAL TARGETS

FIGURE 12: INSTRUMENTATION AND MONITORING

DIFFICULTIES FACED

WATER INGRESS

There is always a risk of heavy groundwater inflow in tunnels. Hence, dewatering pumps shall beinstalled while near unsupported face. A detailed calculation for the same would be included in definitive design.

3D OPTICAL TARGETS

3D OPTICAL TARGETS

The crown is always at a higher risk then rest of the tunnel while excavation. Hence, excavation shall begin form crown and then going towards invert.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
69 Kasturbhai
380009, Gujarat
+91 7926302470
+91 7926302075
ROAD.
Lalbhai Campus University Road, Navrangpura Ahmedabad –
T
F

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.28 NATM AT KALDADEVI IN A GLANCE

ENTERING INSDIE

ROCK BOLTING MAIN TUNNEL

STEEL SUPPORT

EXACACVTION USING SPLITTER

PROFILE MARKING

DRILLING AND BLASTING

PROFILE MARKING

CORE CUTTING

SEGMENT REMOVAL

GROUT REMOVAL

FACE READY FOR EXACVATION

FACE DRILLING

FACE DRILLING

CONTROLLED CHARGING

INTIAL CUT TO START SPLITTING

SCALING

CONTROLLED BLASTING

Kasturbhai Lalbhai Campus University Road, Navrangpura

Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

MUCKING

DEFUMING

MIS FIRE CHECKING

GOING FOR NEXT ROUND TO COMPLETE BLASTING ACTIVITY

SCALING AND MUCKING

PRELIMANRY SUPPORT

NEXT CYCLE

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
70

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.29 PROCEDURE FOR CONSTRUCTION OF ADIT AT KBD STATION

PROVIDING TEMPORARY SUPPORT

CORE CUTTING

SCALING

IT IS CHIIPING AWAY OF LOOSE MATERIASL WHICH ARE NOT COMPLETELY RELEASED FROM THE ROCK DURING BLASTIC PROCEDURE

MUCKING

AFTER SCALING MUCK IS REMOVED BY LOADER AND DUMPED TO THE DISPOSAL AREA WHICH WILL BE LIFTED FROM GANRY CRANE TO MUCK PIT AND LOADED INTO DUMPERS TO DESIGNATED SITES

SURVEY AND FACE MAPPING THE GEOLOSIT WILL INSPECT THE CUT SURFACE AND REMOVE ALL SUSPENDED MATERIAL EXCAVATION PROFILE WILL BE CARRIED OUT BY THE SURVEYOR

PRIMARY LINING

SHOTCRETE

50 MM THICK SHOTCRETE IS DONE THROUGH SHOTCRETE MACHINE

WIRES MESH

150*150*^6 SIZE OF WIRE MESH IS LAID ON THE TOP AND BOTTOM WITH OVERLAPPING OF 150 ON TOP AND 0.3 ON SIDES

ROCK BOLTING 32MM DIA OF BAR IS USED AND INSERTED AT 2.5 M DEPTH ALONG WITH 2 RESIN CAPUSLESNAND FACE PLATES.

WATER PROOFING

SECONDARY LINING

T +91 7926302470

F +91 7926302075

METRO LINE 3 – PACKAGE 2 UGC02
MUMBAI
71
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
BREAKING OF SEGMENT
FACE EXCAVATION DEFUMING MUCK REMOVAL

MARKING

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 72 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
5.30 PROCEDURE SKETCH FOR ADIT CONSTRUCTION
PLAN VIEW OF JUNCTTION AT ADIT AND TBM
OF SEGMENTS

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

EXCAVATION IN TRANSITION ZONE

EXCAVATION UPTO PLATFORM LEVEL

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
73
4 5

5.31 BLAST DETAILS FOR ADIT

SKIN TO SKIN HOLES ARE PROVIDED ON THE PERIPHERY THEY HAVE 102 DIA AND THEIR FUNCTION IS TO TANSFER THE VIBRATION TO THE ADJACENT MASS SO THEY HAVE LARGER DIA

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

REAMER HOLES ARE PRESENT ON THE FACE O IN THE MIDDLE THEIR PURPOSE IS TO PROVIDE CLEAR FACE FOR NEXT CYCLE

PRODUCTIVE HOLES ARE PROVIDED IN THE CENTRE BETWEEN PHERIPHERY AND REAMER HOLES

+91 7926302075
Bhumika Raj (UC5316) Semester-08 PROJECT TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F
74
F
14:
FIGURE 13:
ADIT
IGURE
BLAST DETAILS FOR ADIT
SET OUT POINTS FOR

5.32 QUANTITY

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 75 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
ESTIMATION
EXPLOSIVES
ADIT FOR ADIT 3 EXPLOSVES(kg) EXPLOSIVES(no) EDS 35.36 kg 282 9 Adit 3D/L. From (m) To (m) Pull (m) Qty (Cum) PF. Chainage :- 5.3 6.45 1.15 21.51 0.2 Sr.No. Description No Of Holes Charge Date Blast Timing CATRIDGE USED(NO) Eds TLDs 1 Round 1 6 2.25 06-112019 2.14pm. 18 1 2 Round 2 11 3.68 3.39pm. 29.44 1 3 Round 3 10 3.5 07-112019 11.55am. 28 1 4 Round 4 12 2.875 12.42pm. 23 1 5 Round 5 17 4.3125 2.44pm. 34.5 1 6 Round 6 19 4.375 5.56pm. 35 1 7 Round 7 28 6.187 08-112019 4.06pm. 49.496 1 8 Round 8 18 4.25 5.52pm. 34 1 9 Round 9 18 3.93 09-112019 12.50pm. 31.44 1 Total 139 35.36 282.876 9 0 SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE:UC5316 PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02) Measurement Sheet
OF
FOR

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

5.33 PROCEDURE FOR CENTRAL CAVERN

AFTER BREAK THROUGH IN ADIT DONE PROCESS FOR CENTRAL CAVERN IS I INITITATED

BLASTING IS TAKEN

DEFUMING FOR SAFTEY PURPOSE IS DONE

CONTROLLED BLASTING FOR HEADING CARRIED OUT ON FACE FOR THAT MARKING ID DONE BY SURVEYOR

DRILLING OF PERIPHERY HOLES ON FACE FOLLOWED BY REAMER AND PRODUCYIVE HOLES

STEMMING IS DONE WHICH FILLING UP THE1/3 HOLES WITH SAND

CONNECTING WITH THE ELECTRONIC DETONATORS

CHECKS BY THE EXPERTS AFTER THAT PRELIMANEY WORK IS WARRIED OUT SCALING AND MUCKING OF LOOSE MATERIALS

ATTACHING GELATTIN/ CATRIDGE INTO HOLES DRILLED SPACERS ARE INSERTED AS REQUIRED

PRELIMINARY WORKS LIKE PROVIDING AND FIXING WIRE MESH. SHOTCRETE IS CARRIED OUT

SAME PROCESS IS REPEATED FOR BENCHING AND FOLLOWED ALONG THE ENTIRE LENGTH OF CAVERN

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

METRO LINE 3 – PACKAGE 2 UGC02
MUMBAI
78
FIGURE 15: SET OUT POINTS AT CENTRAL CAVERN

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

AFTER THE SEGMENT ID REMOVED DRILLING BY EXACAVTION MEAN IS STARTED

JUMBO DRILLER IS USED TO DRILL INTO THE SEGMENTS

AT EVERY 1 M ADVANCE WIREMESH IS FIXED 150*150*6 MM IN SIZE

DETAILS OF RESIN CAPSULE shelf life: 6 months,gel time: 30 seconds,setting time:120 seconds,dia 33 mm,length300mm,storage 25 degree .They are provided so they can gel the rod inside the drilled holes

SHOTCRETE IS CARRIED OUT IN ADIT BY PNEUMATIC SHOTCRETE MACHINE

NOTE : Drilling and blasting cannot be carried out initially on the face as it can damage the allignment of other adjacent rings to it so firstly excavation is done through excavator and after some distance geologist t intervenes in the process and approves that when it is safe to carry out blasting

At adit 3, excavation was carried out till 5.3 m after that distance blasting was carried out till next 18.63m through out the adit length

Bhumika Raj (UC5316) Semester-08

TRAINING
PROJECT
2019-2020
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302075
T +91 7926302470 F
77
BY TH E MEANS OF EXCAVATOR THE EXCAVATION IS CARRIED OUT FURTHER

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

PRODUCTIVE HOLRS

PERIPHERY HOLES

PERIPHERY HOLES

PROJECT TRAINING
Kasturbhai
University Road,
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Bhumika Raj (UC5316) Semester-08
2019-2020
Lalbhai Campus
Navrangpura
77
FIGURE 16: BLAST DETAILS FOR CENTRAL CAVERN

ROCEDUR FOR BLASTING WITH EXPLOSIVES

DRILLING OF HOLES 1.2 M DEPTH

1) PERIPHERY

2) REAMER

3) PRODUCTIVE

INSERTION OF EXPLOSIVE IN HOLE

INSERTING EXPLOSIVE INSIDE THE HOLES AND ADDING SPACER AS REQUIRED WITH THAT ATTACHING THE ELECTRONIC DETONATOR

STEMMING IS DONEWHICH IS FILLING THE HOLE WITH SAND FSO DURING BLAST THERE IS NO REBOUND OF EARTH MATERIIALS

SKIN TO SKIN HOLES ARE PROVIDED ON THE PERIPHERY THEY HAVE 102 DIA AND THEIR FUNCTION IS TO TANSFER THE VIBRATION TO THE ADJACENT MASS

REAMER HOLES ARE PRESENT ON THE FACE O IN THE MIDDLE THEIR PURPOSE IS TO PROVIDE CLEAR FACE FOR NEXT CYCLE

BLASTING IS CARRIED OUT WHICH IS FOLLOWED BY DEFUMING

PRODUCTIVE HOLES ARE PROVIDED IN THE CENTRE BETWEEN PHERIPHERY AND REAMER HOLES

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
ROAD. 78 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
GRANT
Bhumika Raj (UC5316) Semester-08

5.34 OBSERVED QAUNTITY FOR BLASTING CENTRAL CAVERN THROUGH ADIT 3

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 79 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
QUANTITY
SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE :UC5316 MUMBAI METRO LINE3 UGC-02 MEASUREMENT SHEET Central . Cavern From (m) To (m) Pull (m) Qty (Cum) PF. NO OF CATRIDGE Chainage :- 0 1.2 1.1 21.12 Sr.No. Description No Of Holes Charge Date Blast Timing Remark. CHARGE/0.125 1 Bottom tightness 24 5 21.01.2020 12.05pm No. Of ED:01 40 2 Round 1 mmct 5 0.875 01.40pm No. Of ED:01 7 3 Round 2 mmct 7 2.625 3.31pm No. Of ED:01 21 4 Round 3 mmct 10 2.5 5.36pm No. Of ED:01 20 5 Round 4 mmct+ bottom tightness 14 7.125 22.01.2020 12.01pm No. Of ED:01 57 6 Round 5 mmct 19 4.75 1.01pm No. Of ED:01 38 7 Round 6 mmct 24 6 2.51pm No. Of ED:01 48 8 Round 7 mmct 24 6 4.06pm no. Of stld:01 NO. Of ED-01 48 9 Round 8 mmct 7 2.1875 5.51pm no. Of stld:01 NO. Of ED-02 17.5 Total 103 29.875 296.5
Table 26:
FOR
BLASTING
AT CAVEN ROUND 1

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

FOR ALL THREE ROUNDS

NOTE – ROUND 1 CTS, it refers to the blasting started from chattrapati shivaji station side and same for Mumbai central station mmct.

*Blasting pattern remains same refer blasting pattern drawing , some improvisations are done on site as site conditions vary,( no of holes may differentiate and no of rounds may reduce or increase )

*The variation is based on the experience of blasting head and engineer and geological condition

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
80
University Road,
Ahmedabad – 380009, Gujarat
7926302470
Kasturbhai Lalbhai Campus
Navrangpura
T +91
F +91 7926302075
Table 27:QUANTITY FOR BLASTING AT CENTRAL CAVERN ROUND 3
SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE :UC5316 MUMBAI METRO LINE3 UGC-02 MEASUREMENT SHEET CENTRAL CAVERN From (m) To (m) Pull (m) Qty (Cum) PF. NO OF CATRIDGE Chainage :- 2.4 3.8 1.4 26.88 Sr.No. Description No Of Holes Charge Date Blast Timing Remark. CHARGE /0.125 1 Round 1 cst 7 2.625 27.01.2020 12.51pm NO. Of ED-01 21 2 Round 2 cst 9 3 1.42pm NO. Of ED-01 24 3 Round 3 cst 16 5 2.54pm NO. Of ED-01 40 4 Round 4+5 cst 34 8.5 4.38pm NO. Of ED-01 68 5 Round 7 mmct 23 3.875 5.52pm NO. Of ED-01 31 Total 89 23 184 TOTAL
OBSERVED TOTAL EXCAVATION 71..04Cu.m. AVERAGE PULL 1.2 M CATRIDGES 830 NO.
QUANTITY

5.35 TIME CYCLE ANALYSIS FOR ADIT 3

total 2 shifts of 11 hours with 1 hour break each , pull of 1.15 at adit is observed

surveyor comes in shifts one in morning and then in evening.

1 hours taken to remove muck everyday for 6 pulls

two layers of wiresmesh is laid after every excavation round which consumes 1.5 hours so for 6 pulls

for rock bolting in one pull 2 hours are consumed so for 6 pulls

in 2 rounds it is done and is carried out simultaneously with excavation at every 1.15 m its done which consumes 4 hours for one pull so for 6 pulls

ACTIVITY WISE TIME BREAK UP

INFERENCE :Maximum time consumed is observed in excavation as many diffiuclties like placing and moving the excavator carryoying out activity according to the vibration limit, while least time is carried out in mucking.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 81 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
sr. no FOR ADIT UNIT DETAILS DESCRIPTION 1 area m2 89.25 2 peripheral length m 12.5 3 effective pull m 1.12 4 excavation hours 88
Table 28: TIME CYCLE ANALYIS FOR ADIT TIME CYCLE FOR ADIT 3 ( CLASS 2 ROCK)
5 survey and mapping hours 2
6 mucking hours 6
7 wire mesh hours 18
8 rockbolting hours 12
9 shotcrete hours 48
10 total time for activity hours 174 total time taken for adit l=7.140 11 conigency hours 17.4 contingency @10% 12 total time for activity hours 191.4 13 working hours hours 22 22 working hours ( break of 2 hours) 14 working days wd/month 25 deducting sundays and holidays 15 advance per days m/day 1.75 Daily excavation 16 monthly progress excavation m/month 43.75 Monthly excavation=working days * advance each day 51% 1% 3% 10% 7% 28%
excavation survey and mapping mucking wire mesh rockbolting shotcrete

5.36 TIME CYCLE ANNALYSIS FOR CAVERN

for one face approximately 2 hours are consumed for drilling and pull is 1.2m on average so for 3 rounds

2.5 hours for entire blasting includes inserting exolosives and attaching electronic detonators for one pull so for 3 rounds

defuming for 1 hour is done after every round so for 3 rounds

5.37 Table 29: TIMECYCLE FOR CENTRAL CAVERN

ACTIVITY WISE TIME BREAK UP FOR CENTRAL CAVERN

INFERENCE :Maximum time consumed is observed in blasting and charging as no of labours were less during the activity and even generally drilling time is also more asit requires time to drill into hard rock

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 82 Kasturbhai
University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus
Time cycle for central cavern from( 0.00m adit 3 towards adit 13.8m chainage ) Exacavation quantity cu.m 71 No of holes no 329 penetration rate 10m/hr drilling for 32 mm holes hours 6
blasting and charging hours 7.5
defuming
3
total time for activity hours 16.5 conigency hours 1.65 total time for activity hours 18.15 working hours hours 22 working days wd/month 25 for one day progress cu.m/day 86 monthly progress drilling and blasting cu.m./month 2150 36% 46% 18%
blasting and charging defuming
drilling for 32 mm holes

LABOURS INVOLVED IN ACTIVITY

INFERENCE :maximum no of labour force is observed in drilling and blasting as it’s a tedious activity involving more work force while in excavation one operator operating excavator is enough for carrying out the activity

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
83
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470
F +91 7926302075
ACTIVI SUB ACTIVITY LABOURS TIME TAKEN QUANTUM UNIT LABOUR PRODUCTIVITY FOREMAN SKILLED UNSKILLED TOTAL HR MAN DAY PREMINARY EXACVATION 1 2 2 5 88 4 167 Cu.m 41.75 PRELIMANRY SUPPORT SHOT CRETE(PULL 1.2) 2 2 2 6 48 2.181818 37.5 M3 17.1875 WIRE MESH 1 2 3 6 18 0.818182 101 kg 123.4444 ROCK BOLTS 1 3 2 6 12 0.545455 63 kg 115.5 DRILLING AND BLASTING 2 5 2 9 13.5 0.613636 329 cu.m 536.1481 total 7 14 11 32 179.5 0 2 4 6 8 10
Table 30: LABOUR PRODUCTIVITY 5.38 EXACVATION SHOT CRETE(PULL 1.2) WIRE MESH ROCK BOLTS DRILLING AND BLASTING

TABLE 31: RA FOR EXCAVATION OF ADIT

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020

Measurement Sheet

Providing for and excavating for 6m wide Adit using NATM tunnelling method, as per detailed drawing and specification including lead and lift up to 1.5m

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 84 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
T
F
Item No Item Description Unit Qty Rate Amount
m3 A MATERIAL B Labour 0 operator man/day 4 1100 ₹4400 skilled man/day 8 600 ₹4800 unskilled man/day 8 500 ₹4000 ₹13200 C Machines and equipments 0 Exacavtor hitachi hours 70 934 ₹65380 D water and electricity cost(4% of A+B) ₹528 E Contingeny(2% of A+B+C+D) ₹1582.16 E miscallaneous(15% of A+B+C+D) ₹12103.524 total ₹₹92793.68 cost per m3 rs/m3 ₹555.65

TABLE 32: RA FOR SHOTCRETE

₹SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKAAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020 Measurement Sheet

Providing for and carrying out shotcreting for 6m wide cross-passage as per pecification using M35 grade of concrete including batching, transportation, spraying etc.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 85
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
Kasturbhai
T
F
Item No Item Description Unit Qty Rate Amount
kg
Material Grade of concrete :M35 37.5 7000 ₹26250 B Labour 0 operator man/day 4 1200 ₹4800 skilled man/day 4 660 ₹2640 unskilled man/day 4 540 ₹2160 ₹35850 C Machines and equipments 0 Shotcrete machine hours 48 4000 ₹192000 D water and electricity cost(4% of A+B) ₹1434 E Contingeny(2% of A+B+C+D) ₹4585.68 F miscallaneous(15% of A+B+C+D+E) ₹35080.42 total ₹295200.13 cost per m3 ₹/M3 ₹7872.00
A.

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020

Measurement Sheet

Providing for and fixing of wire mesh of size 150*150*6 after 1st and 2nd layer of shotcrete for 6m wide crosspassage including drilling, ransportation etc complete

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 86 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
33:
WIREMESH
TABLE
RA FOR
Item No Item Description Unit Qty Rate Amount
transportation,
kg A. material 150 *150* 6 wire mesh kg 101 52 ₹5252 B Labour 0 operator man/day 1 1200 ₹1200 skilled man/day 2 660 ₹1320 unskilled man/day 3 540 ₹1620 ₹4140 C Machines and equipments 0 D water and electricity cost(4% of A+B) ₹165.6 E Contingeny(2% of A+B+C+D) ₹86.112 F miscallaneous(15% of A+B+C+D) ₹₹658.7568 total 10302.4688 Cost/kg ₹/KG ₹102.0046416
spraying etc.

TABLE 34: RA FOR ROCK BOLTING

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020 Measurement Sheet

Carrying out rock bolting for 6m wide crosspassage using 32mm dia rebar with face plate of thickness 12 mm and resin capsules including transportation, drilling etc. kg

T

F

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 87
Lalbhai Campus University Road,
Ahmedabad – 380009, Gujarat
Kasturbhai
Navrangpura
+91
7926302470
+91
7926302075
Item No Item Description Unit Qty Rate Amount
A.
rock bolts 32mm kg 63.3 52 ₹3291.6 face flate 150*150*12 kg 21.15 40 ₹846 resin capsules(constect 28 mm) no 20 60 ₹1200 B Labour 0 operator man/day 1 1200 ₹1200 skilled man/day 3 660 ₹1980 unskilled man/day 2 540 ₹1080 ₹4260 C Machines and equipments DRLLING MACHINE HOURS 12 900 ₹10800 D water and electricity cost(4% of A+B) ₹170.4 E Contingeny(2% of A+B+C+D) ₹304.608 E miscallaneous(15% of A+B+C+D) ₹710.2512 total ₹21582.8592 cost/kg ₹/KG ₹213.691675
material

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020

Measurement Sheet

Providing blasting for central cavern at kalbadevi station including inserting explosives and detonators , transportation,fixing etc under supervision of general consultants(for 71.01 cu.m.)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 88 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
TABLE 35: RA FOR ROCK BOLTING
Item No Item Description Unit Qty Rate Amount
BLASTING m3 A. MATERIAL IDEA POWER 90 KG 97.25 140 ₹13615 ELECTRONIC DETONATOR NO 30 8 ₹240 B Labour 0 operator man/day 1 1200 ₹1200 skilled man/day 5 660 ₹3300 unskilled man/day 2 540 ₹1080 foreman man/day 1 1000 ₹5820 C Machines and equipments 0 D water and electricity cost(4% of A+B) ₹232.8 E Contingeny(2% of A+B+C+D) ₹121.056 E miscallaneous(15% of A+B+C+D) ₹926.0784 total ₹26534.9344 cost per m3 ₹/M3 ₹279.3150989

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

Providing for and excavating for 6m wide cross-passage using NATM tunnelling method, as per detailed drawing and specification including lead and lift up to

refer pg no.84)

Providing for and carrying shotcreting for 6m wide cross-passage as per specification using M35 grade of concrete including batching, transportation, spraying etc.( refer pg no85.)

Providing for and fixing of wire mesh after1st and 2nd layer of shotcrete for 6m wide cross-passage including drilling, transportation etc complete, transportation,

Carrying out rock bolting for 6m wide crosspassage using 32mm dia rebar with face plate of thickness 12 mm and resin capsules including transportation, drilling etc.( refer pg

Providing blasting for central cavern at kalbadevi station including inserting explosives and detonators , transportation,fixing etc under supervision of general consultants( refer

ACTIVITY WISE COST BREAK UP

INFERENCE : Maximum cost is obtained for excavation as it requires more time and equipments compared to other activities also shotcrete is 43% because rebound factor comes into play which happens on site.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 89 Kasturbhai
University Road,
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus
Navrangpura
NAME:-
BHUMIKA RAJCODE NO:-UC5316
Item No Item Description Unit Qty Rate Amount 1
PROJECT TRAINING 2019-2020 ABSTRACT SHEET
1.5m
M3 167 555.65 ₹921794 2
(
M3 37.5 7872 ₹295200 3
spraying
pg
Kg 101 102 ₹10302 4
etc.( refer
no.86)
no87 ) kg 63.3 213 ₹13483 5
pg no.88) Cu.m 71.04 279 ₹19820
52% 41% 3% 2% 2%
excavation shotcrete wiremesh rockbolting blasting

CONCLUSION:

 In NATM works excavation , drilling , blasting and charging play a very important role,.So care should be taken to carry out the blasting and charging activity safely so there is no fatality on site.

 One of the advantage at kalbadevi was that the strata was hard compared to other stations so it was faster to carry out the preliminary works like shotcrete , installing wiremesh and rock bolting( refer pg no.66 for rock strata )

 At kalbadevi there are many old buildings and it’s quite dense also so vibration limit is to maintained which is 3.5Hz which requires continuous monitoring.

 When explosives are blasted ammonium nitrate is produced which is harmful to the environment Flexible – Support provide as required by the ground conditions .

 Economical – Support provided as required by the encountered ground conditions, in contrast to TBM segments, which are designed for worst load case – if needed or not, therefore overdesigned.

 Adaptable – Optimizing equipment and crews, allowing multiple heading operations concurrent

SHOTCRETE: It forms a major part of the activity so extra care should be taken .Before shotcrete is done its trial is carried out where trials are done and compressive strength of shotcrete is measured, and the graph plotted from the data should obtained J2 curve ,below J1 curve the shotcrete should be rejected

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS
90
380009,
T +91 7926302470 F +91 7926302075
: CST, KALBADEVI, GIRGAUM, GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat
5.39 ANALYSIS OF THE ACTIVITY FIGURE 17: SHOTCRETE STRENGTH GRAPH LAGGING INDICATORS LEADING INIDCATORS Paradigm shift measure

6 CROSS PASSAGE CONSTRUCTION

 Observed activity :Construction of cross passage at Grant road station BY natm method.

 Cross passage details: cross passage 7

 Observed activity location : total 7 cross passages from kalbadevi to grant road.,Cp 7, grant road station chainage 7510 upline . 7490 downline

 Cross passage 7 dimensions:

 Wide-3M

 Length : 14m

 Height: 3.149

 Grade of shotcrete:M35

 dimensions of wiremesh: 150*150*6

Rock bolting details

 20 mm dia rod inserted 1.2 mm deep In rock

Type of lattice girder :

 Type : 70/20/25 Placed at every 1m, steel used Fe500d

6.1 Reason for providing cross passage

 Cross passages are provided for safety purpose, incase of any emergency when passengers have to be shifted from one tunnel to another cross passages can be used for rescue.

 Provided when the distance between two stations is more than 700 m

 Provided at the distance of 250 m each.

 There are total 7 cross passages in UGC02.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
91
+91 7926302470 F +91 7926302075
GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T

6.2 ORGANISATION CHART

Activity

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 92 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
project manager execution tunnel manager site engineer site supervisor support geotechincal geologist instrumentation and monitoring survey manager surveyor qa/ac quality enginner construction manager NATM tunnel works PRELIMINAR Y ACTIVITIES FEASAB ILITY SRUDY SELECTI ON OF AGENCI ES PLANNI NG DESIGN EXECUT ION LAUNCHIN G OF TBM INTIAL DRIVE MAIN DRIVE NATM CROSS PASSAGES CP 1 CP 2 CP 3 CP 4 CP 5 CP 6 CP 7 ADITS ADIT 1 ADIT 2 ADIT 3 SHOTCRETE WIREMESH ROCK BOLT ADIT 4 ADIT 5 ADIT 6 ADIT 7 SUMP PASSAG E CENTRAL CAVERN DRILLING AND BLASTING WORKS QUALITY INSPECTION MISCALLANEOUS LAYING OF TRACKS / VENTILATION ETC
covered:

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

PROJECT TRAINING
380009, Gujarat T +91 7926302470 F +91 7926302075
Bhumika Raj (UC5316) Semester-08
2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
93
6.3 OSERVED ACTIVITY LOCATION

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

Bhumika
Semester-08 PROJECT TRAINING 2019-2020 Kasturbhai
Campus University Road,
Ahmedabad
380009, Gujarat T +91 7926302470 F +91 7926302075
Raj (UC5316)
Lalbhai
Navrangpura
94 OSERVED ACTIVITY LOCATION

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

(UC5316)

PROJECT
380009, Gujarat T +91 7926302470 F +91 7926302075
Bhumika Raj
Semester-08
TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
95
6.5 CROSS PASSAGE DETAILS
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 96 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Raj
Semester-08 PROJECT TRAINING 2019-2020
LATTICE
DETAILS
Bhumika
(UC5316)
6.6
GIRDER

6.7 PROCEDURE FOR CONSTRUCTION OF CROSS PASSAGE

PROBE HOLE DRILLING FOR SAFETY PURPOSE

EXCAVATION CARRIED OUT ON FACE 1.5M PULL DOR CROSS PASSAGE

RPROVIDING SUPPORT THEOUGH WALERS AND JACKS

BREAKING OF SEGMENT

PRIMARY LINING SHOTCRETE

50 MM THICK SHOTCRETE IS DONE THROUGH SHOTCRETE MACHINE

CYCLE IS REPEATED THROUGH OUT THE LENGTH OF THE CROSS PASSAGE

MUCKING

AFTER EXCAVATION MUCK IS REMOVED BY LOADER AND DUMPED TO THE DISPOSAL AREA WHICH WILL BE LIFTED FROM GANRY CRANE TO MUCK PIT AND LOADED INTO DUMPERS TO DESIGNATED SITES

SURVEY AND FACE MAPPING THE GEOLOSIT WILL INSPECT THE CUT SURFACE AND REMOVE ALL SUSPENDED MATERIAL

EXCAVATION PROFILE WILL BE CARRIED OUT BY THE SURVEYOR

T

WIRES MESH

150*150*^6 SIZE OF WIRE MESH IS LAID ON THE TOP AND BOTTOM WITH OVERLAPPING OF 150 ON TOP AND 0.3 ON SIDES

.LATTICE GIRDER ERRECTION IS DONE FIRST ABOVE TWO PARTS ARE ERRECTED THEN PATS AT LEGS ARE ERRECTED

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
97
Ahmedabad
380009, Gujarat
GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura
+91 7926302470
+91 7926302075
F

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

6.8 INSTRUMENTATION AND MONITORING

• PLACED ON THE PERIPHERY OF THE CROSS PASSAGE THEY CHECK WHETHER THE VIBRATION IS WITHIN THE LIMITS OR NOT

• THYE ARE PLACED AT THE SIDES AND THEIR FUNCTION IS TO SHOW THE PRESSURE DURING SHOTCRETE WHICH SHOULD NOT EXCEEED

6.9

PROJECT TRAINING 2019-2020 Kasturbhai
University Road,
Ahmedabad
380009, Gujarat T +91 7926302470 F +91 7926302075
Bhumika Raj (UC5316) Semester-08
Lalbhai Campus
Navrangpura
98
Alert level Action level Alarm level At side wall 840Kn/m2/m 1340 Kn/m2/m 1680 Kn/m2/m At crown of tunnel 1180 Kn/m2/m 1888 Kn/m2/m 2360 Kn/m2/m
At side wall 48 Kn/m2/m 77 Kn/m2/m 96 Kn/m2/m At crown of tunnel 86 Kn/m2/m 138 Kn/m2/m 173 Kn/m2/m
TARGETS
Trigger limits for tangential pressure cell Pressure on shotcrete
Trigger limits for radial pressure cells Pressure on shotcrete Alert level Action level Alarm level
OPTICAL
PRESSURE
CELLS

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

6.10 QUANTITY ESTIMATION FOR LATTICE GIRDER Bar name BAR CUT LENGTH CURVATURE LENGTH

NO OF TRIANGULAR PARTS

TOTAL CURVATURE LENGTH /TRAINGULAR BAR CUT LENGTH mm)=40

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

NAME:- BHUMIKA RAJ CODE NO:-UC5316

PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02)

Kasturbhai Lalbhai

Bhumika Raj (UC5316)

Semester-08

PROJECT TRAINING 2019-2020

F +91 7926302075
Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470
99
AIR SIDE A 2622 2622 20 25 B1 2620 2620 20 25 B2 2620 2620 20 25 C 2622 2622 20 25 Triangular part 268 10484 10 10
BAR DIA(ROCK SIDE)
Measurement Sheet Item No Item Description Unit Qty UNIT WEIGHT LENGTH BREADTH qty total LATTICE GIRDER (ALL 4 PARTS) 20 mm kg 1 2.47 10.72 26.4784 25mm kg 1 3.86 10.35 39.951 10mm kg 40 0.62 0.286 7.0928 face plates 12 mm kg/m2 12 94 0.24 0.16 43.3152 0 116.8374

TABLE 37: LABOUR ANALYSIS

6.11 LABOUR ANALYSIS FOR CROSS PASSAGE 7 AT GRANT ROAD STATION

LABOURS INVOLVED IN ACTIVITY

Highest number of labours are observed in the installation and making of attice girder while least number is found in excavation as breaking is done through excavator and few people are required for other smaller activities relaed to excavation.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 100 Kasturbhai
University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470
+91 7926302075
Lalbhai Campus
F
ACTIVITY SUB ACTIVITY LABOURS TIME TAKEN QUANTUM UNIT LABOUR PRODUCTIVITY FOREMAN SKILLED UNSKILLED TOTAL HR MAN DAY PRELIMINARY SURVEY AND MARKING 1 2 1 4 24 1.0909091 10 ROUNDS EXACVATION 1 2 2 5 88 4 516 CU/M3 129 PRELIMANRY SUPPORT SHOT CRETE(PULL 1.2) 2 1 2 5 48 2.1818182 75.6 M3 34.65 WIRE MESH 1 2 3 6 18 0.8181818 513 KG 627 ROCK BOLTS 1 3 2 6 12 0.5454545 59.78 KG 109.5966667 LATTICE GIRDER 5 2 1 8 30 1.3636364 116 KG 85.06666667 10 10 10 30 196 0 2 4 6 8 10 EXACVATION
SHOT
CRETE(PULL
1.2) WIRE MESH ROCK BOLTS LATTICE GIRDER

NAME:- BHUMIKA RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020

Measurement Sheet

Fabrication and Erection of 70/20/25Lattice Girder as per drawings and specification including fabrication of accessories, welding, bolting, transportation etc.under the supervision of general cosnultants

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 101 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
TABLE 38: RA FOR LATTICE GIRDER SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY
Item No Item Description Unit Qty Rate Amount
A. MATERIAL (ALL 4 PARTS) 20 mm kg 26.47 52 1376.44 25mm kg 39.95 52 2077.4 10mm kg 7.08 52 368.16 face plates 12 mm kg/m2 43.31 52 2252.12 B operator man/day 5.44 1200 6528 skilled man/day 2.72 660 1795.2 unskilled man/day 1.36 540 734.4 15131.72 C Machines and equipments 0 D water and electricity cost(4% of A+B) 605.2688 E Contingeny(2% of A+B+C+D) 314.739776 E miscallaneous(15% of A+B+C+D) 2407.759286 total 30970.92786 cost per kg rs/kg 326.009767

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

Inference:The chart depicts that 32 % is the labour cost and 68% is the material cost observed in the following activity.Most important material is shotcrete used in this activIty which takes up the majority part.

Inference:The chart depicts that shotcrete is the most costly activity followed by other activities least is for wiremesh.In case of shotcrete there is rebound upto 10% which adds upto the cost .

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 102 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Table 39; ABSTRACT SHEET
NAME:-
ABSTRACT SHEET Item No Item Description Unit Qty Rate Amount 1 Providing
and lift up to1.5m M3 516 381 196596 2 Providing
transportation,spraying etc. M3 75.6 7872 595123 3 Providing
drilling, transportation
complete, transportation,spraying etc. Kg 513 108 10302 4 Carrying out rock bolting for 6m
crosspassage using
of thickness 12 mm and resin capsules including transportation, drilling etc. kg 101 396 39996 5 Fabrication and Erection of 70/20/25Lattice Girder as per drawings andspecification including fabrication of accessories, welding, bolting, transportation etc.( refer pg no.101) kg 116.83 326 30970 28% 56% 6% 6% 4% ACTIVITY WISE BREAK UP AMOUNT(INR) excavation shotcrete wiremesh rockbolting lattice girder 68% 32% MATERIAL VS LABOUR AMOUNT INR MATERIAL LABOUR
BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020
for and excavating for 6m wide crosspassage using NATM tunnelling method, as per detailed drawing and specification including lead
for and carrying shotcreting for 6m wide cross-passage as per specification using M35 grade of concrete including batching,
for and fixing of wire mesh after1st and 2nd layer of shotcrete for 6m wide crosspassage including
etc
wide
32mm dia rebar with face plate

CHAPTER 4: MANAGEMENT CAR

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 103 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075

6.11.1 OWING AND OPERATING

Contarctor has separate plant and machinery department P&M for site which works as separate agency which supllies all required TEP’s on site . the selctio of size , specification and technology of the TEP is purely dependent on site location , project timeline and cost associated with it .

Type of TEP costs

Cost to P&M

IT means the cost at which P7M department buys machineryand calculates its owining and operating cost including capital cost , depreciation , running hour per month , labours ,s spares and agency repairs

Cost ro project :

After caluationg an amount , P&M department deploys machine to site as per demand and requirement of time . so contractor must pay internalhire charge if machine is owned by the company which is inclusive of cost to P&M , fuel and transportation charges , whereas there is other term called external hire charges which is to be paid to machine which are notowmed by company and it hires from other agencies or sub contractors

6.11.2 BUY AND LEASE OPTIONS:

As per observation and data information, about 60% equipments are owned and 40% equipments are hired by the company. This depends on whether the equipment will give enough returns for the project as per desired output required. If the work required to be carried out is more than purchasing is better than leasing/ hiring any equipment.As per financial aspects; it is checked whether the theoretical owning and operating cost, maintenance and operator cost for monthly usage is as per contractor’s hiring cost. Based on this, it is decided to hire/ purchase any equipment. However, there is no calculation done by DSJV for monthly owning and operating cost.

Also, it depends on the type of work to be carried out (like for specialised work in piling, Keller engineering group, Meher foundation is hired to execute work).The P&M department maintains register of their assets, which includes Hired cost register, Maintenance register, Fuel consumption schedule and Usage hours register.All the owned and some hired equipments are operated by CJV staff only. Sub-contractor is just to execute the work with their equipments.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 104 Kasturbhai
T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

6.11.3 BILLS

Advance Bills:

Advance bills are prepared for Mobilization of P&M on site, so that afterwards, RA bills can be prepared.It includes-

 .Mobilization Advance -This is based on the work we are giving to other sub-contractors.

 .It is generally about 10 to 15% and maximum of 20% of contract cost.

 .General Advance- It includes Bank Guarantee

RA Bills:

It is made by contractor at site and then, it is compared with sub-contractor working. It includes following things:

 .Measurement sheets- Prepared at site and signed by GC representative.

 Reconciliation sheet, for reinforcement or concrete consumption

 .Summary sheet

 Taxes paid during RA Bills: GST [GOODS AND SERVICE TAX] (18%) of goods value

Escalation Bills

Generally carried out for Diesel, Concrete, Steel, P&M, Labour. It is claimed when rates of all these items change above 20% & their substantial usage of same. This is covered from:

.Profit obtained, by selling steel scrap to authorized recyclers

.Adding wastage to price of steel

 The difference between both will add up to tender quoted by MMRC and CJV.

.The recovery of taxes and advances are done by the clients from every month payment, done to the contractor.It includes deduction of Labour cess ), Education cess), TDC , Surcharge , Mobilization advance from every month payment.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 105 Kasturbhai
380009,
T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat

Quality Manual:

Set out the structure and content of management system, linking the policy & objectives with system elements and procedure.

Sets out project organisation, responsibilities. Sets out project organisation, responsibilities and authorities

.Quality Procedure:

Provide detail instruction as what is to be done by whom, where and when and how are the steps to be carried out.Method Statement,Work Instruction/ Work Procedure,.Inspection and Test plan [ITP],Conformance reports/ Check sheet/ Work report sheet

Others

Environmental air monitoring , noise monitoring on daily basis, conducting programs on various subjects so the enginners and workers can improve their efficiency. Example BIM programs, integrated planning programs . drilling and blasting methods sessions etc , also for workers such programs are conducted.

MANAGEMEMENT INFORMATION SYSTEM (MIS)

 Daily progress report

The daily progress report is sent on a daily basis to the client as well as the contractor comprising of the amount of work done on the previous day and details about the work that has been done so far and the amount of work to be done.It also provides information about the daily targets set by the contractor

 The monthly progress report is sent on the first day of the new month, giving a summarized view of the work performed in the previous month.It also contains the reasons for the slow work progress (if any). This report mainly deals at the macro level and can be very helpful in picturing the overall progress of the package.

REPORT INCLUSIONS

• RECONCILATION

• monitor the wastages that are incurred on site.If wastage is more than allowable limit, factors that cause more wastage are mentioned.Status of reconciliation statement of Reinforcement and Cement is made on monthly basis. It has record of total indent quantity, total receipt

• Scrap on site for that month

• .% wastage (wastage/Total Issue

QUALITY EVALUATION SYSTEM:

Quality evaluation is done on various stages and by various internal and external parties. Third Party Inspection is also carried out for quality assurance and evaluation of construction activities.

•Each activity has a list of quality checks which needs to be filled before and after the construction activity. These Checks include Formwork, Reinforcement, Concreting, Boring & General Inspection checklists.

•Each check list is filled, observations are recorded and is submitted which is evaluated and final conclusions are included in the monthly progress reports

 Non-conformance report

A non-conformance is raised by the QA/QC department if the department while inspecting thestructure finds it not meeting the required quality standards. In case of non-conformance, the root cause is identified and preventive measures are suggested.The preventive measures are applied and the quality is assured and the report is closed and saved. so that precautions and preventive measures for any similar non-conformance can be reviewed at a later stage

MATERIAL HANDLING

VALUATION AND SELECTION OF VENDORS/ SUB-CONTRACTORS

• Material issued till previous month, Material issued in this month, Total Material issued till date

• Book stock balance (material on sitematerial issued)

•CJV shall procure materials and services from pre-qualified vendors Qualification of vendors is on the basis of evaluation of their ability to meet the required specifications and delivery This evaluation will include the following as applicable

•Supplier who hold a current ISO 9001 registration

•Review of past records of performance

•Review of supplier's/sub-contractor's quality

•Facility survey Checking with previous clients

•Financial capabilities

MATERIAL HANDLING STORES AND MATERIAL HANDLING

•To make any kind of purchase of the material, the store manager does a complete market study of the material, with at least 3 quotations (varies with project to project) with him, before he can order

•.Indent slips- This document is kept in record by the store keeper It is for 2 types of materials on site- Chargeable Items (nails, hammer etc.) and Free Issue (machines, tools etc.). 2 copies- 1 for store and 1 for accountant

MATERIAL HANDLING RECORD KEEPING

•Purchase orders- These are prepared for materials that are to be authorized by the P M directly 3 copies- 1 for store, 1 for supplier and 1 for accountant

•Delivery challan,Stock register- After every month, the stock of the materials present at site is noted in this register, to calculate the usage for each month

PROJECT TRAINING 2019-2020 Kasturbhai
– 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI,
ROAD. 106
Bhumika Raj (UC5316) Semester-08
Lalbhai Campus University Road, Navrangpura Ahmedabad
GIRGAUM, GRANT
6.11.4 MANAGEMNET ASPECTS OF SITE. 6.12 FEASAIBILIYY

Feasibility Study:

The ridership figures for the Colaba – Bandra – SEEPZ Metro corridor are provided by MMRDA based on the results of its CTS Transport Demand Model The proposed Metro Corridor is expected to have a daily ridership of 16.99 Lakh and Max. PHPDT of 42000 by 2031. The daily ridership and PHPD on the corridor are shown in Table 1

STATUTARY APPROVAL

Indian Road Congress Code IRC: SP:55-2001‘Guidelines on safety in Road Construction Zones’

National Building Codes 2005

RIDERSHIP DETAILS

Inference :So this chart shows that the ridership increases with years , this survey is carried out so one can get an idea of number of passengers to be witnessed for the project and the increment is also predicted . If all. the data and survey suffice the criteria of project then the project can be predicted to be feasible.

CASH FLOW

Cash flow management forms an important part of the organisation, as the money payment and advances are decided based on this, which includes cash inflow and outflow for the project

CASH INFLOW + CASH OUTFLOW= PROJECT PROGRESS FOR THE SITE

[Note: This is done either weekly/ monthly/ quarterly]

This works as per the advances obtained for major materials, before execution of the work [e g For cement, steel, concrete; certain advances are obtained as a revenue from the client i.e. MMRC]. From this revenue, work is executed and hence, earnings is obtained, which is in turn paid to the sub-contractors for execution of their work.

Contractor Labour Act, 1970 and rules 1950

Environment Protection Act, 1986

Motor Vehicle Act, 1999 and Central Motor Vehicle Rule, 1989

Factory Act 1948

FINANCIAL FEASABLITY: The basic Project cost of the metro corridor prices is estimated at Rs 150551 Million. The cost of land is estimated at Rs.15,865 Million. Of the total land cost,Rs 4,985 Million is cost of private land and the cost of government land has been estimated at Rs 10,880 Million. The total cost of project including land, is estimated at Rs 166,416 Million.The Central and State taxes and duties (Customs, Excise and VAT) amount to Rs 25,467Million. Of the total taxes and duties, Rs 20,432 Million are central taxes (Customs and Excise duty) and Rs 5,035 Million are state taxes (Value Added Tax). The component towards Octroi and insurance works out to be Rs. 2121 Million and Rs. 831 Million respectively.For the purpose of financial analysis, only cost of private land being a cash payout has been added to the project. The government land is expected to be available on transfer basis. Further, JICA is expected to part fund the project through soft loan. The completion cost including IDC works out to Rs 217,523 Million

Bhumika Raj (UC5316) Semester-08 PROJECT TRAINING 2019-2020 Kasturbhai
University Road,
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 107
Lalbhai Campus
Navrangpura
Corridor 2016 2025 2031 Max. PHPDT Daily Ridership (in Lakh) Max. PHPDT Daily Ridership (in Lakh) Max. PHPDT Daily Ridership (in Lakh) Colaba-Bandra - SEEPZ 25700 10.06 39000 13.87 42000 16.99 Train operation plan with train carrying capacity @ 6 persons per square meter of area is considered Table 2: Transport Capacity Provided on the Corridor Train operation plan with train carrying capacity @ 6 persons per square meter of area is considered 6.13 25% 34% 41% DAILY
2016 2025 2031 Year Colaba – Bandra Bandra – SEEPZ Section 2016 2025 2031 2016 2025 2031 Cars per train/ Trains Per Hour 6/ 14 6/ 20 6/ 24 6/ 9 6/ 10 6/ 12 Avg. Head way (seconds) 260 180 150 400 360 300 Avg. PHPDT Demand 25000 36000 40000 16000 18000 20000 PHPDT Capacity Available 25088 35840 43008 16128 17920 21504
Table 1: PHPDT and Daily Ridership for 2016, 2025 and 2031

PART 2 TASK 1: PROJECT DELAY

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 108 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075

7

INTRODCUTION TO PROJECT DELAY

India, there are currently more than 26 metro rail projects at various levels of planning, construction and operation. A number of new phases of metro rails are being planned and will be launched soon. Various studies have documented delays in planning and execution of metro rail projects in India as well as the world.

In this report, an attempt has been made to understand various issues or impediments which are faced by the metro rail corporation in executing the metro rail projects. There are numerous factors which may cause hindrance to the project execution such as funding capacity of governments, finance arrangements, competing technologies, feasible operational model, stakeholder issues etc

Construction delays can be defined as the late completion of work compared to the planned schedule or contract schedule. Construction delays can be minimized only when their causes are identified. The objective of this study was to identify the major causes of construction delay , methods of delay and methods to minimize delays.In this report prepared , all the factors that hindered the progress of package 2 are discussed.their quantification is done along with their impact on duration of project and remedial solution is also given.A. study on reserach papers are also carried and comparison is done with the data and delays of package 2 with the three research papers.This comparison helped to know which kind of delay was more dominant on the package2 and why was it dominant and what role the authorities played into it.

In the analysis part comparison with research papers is also carried out, which bifurcates the delays witnessed in the project into different types, and relative index calculation is also carried out which helped in identifying which delay played a crucical role in the lag of the project. Why study delays: They help in analyzing which activity was dominant in causing the delay, so if in future it can be learnt what actions are to be taken and what actions are to be avoided for smooth completion of project

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 109 Kasturbhai
T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

7.1 Reasons of delays in developed vs developing countries. Table

Reasons

Developing countries

Developed countries.

Delays in payment by client Weather/ ground conditions

Delays in drawings changes and error in deisgn

Contractors financial difficulties

Delays in drawings changes and error in deisgn

Sub contractor and supplier related issues

Deficincies in planning and scheduling Change orders and increase in scope of work

Dealys in delivery of materials

Slow decision making by owners

Subcontractor related isssues

Delay in monthly payments

Force majeure

Poor site conditions

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 110 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
40: comparison between developed and developing countries
EUROPE AMERICAL CHINA INDIA
IGURE
F
18: WORLD MAP

7.2 Task overview

 Enlist delays

 Quantify

 Work out reasons . work out impact

 on overall duration of project.

 Work out corrective action to

 be taken by all project participants

Chronology of of delay in package 2

so if we take into consideration Mumbai metro line 3 project, over all there have been many issues related to this magnum project which bears the responsibility of giving mumbaikars a new transport system. In specifically package 2, is taken into consideration there have been many issues rel

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 111 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
CHRONOLOGY OF DELAYS 2/3/17 utility diversion issues at grant road station 6/7/2017 Nosecant piling work carried out during night time 12/8/201 7 delay at girgaon sttaion due to ganesh mahotsav 7/01/201 8 global procurement issue of lifting pin 21/05/20 18 TBM#2 was on halt due to Parsi fire temple issue 3/2/18 main drive transfer issue 7/8/18 NATM WORKS KALBADE VI STATION 3/12/18 Sewer Line diversion Works: grant road 4/3/19 Land accquisition issues feb 2019 mining and segment productivity decrease 24 jan 20 pour 4, no concrete pump was vaialable so work was halted so 11 hours 22 march 20 covid 19
F IGURE 19: CHRONOLOGY OF DELAYS

7.3 Time line of delays

FIGURE 20: TIMELINE OF DELAYS

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 112 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
2/3/17 Utility diversion issue at Grant Road station 6/7/20 17 no secant piling work carried out at night time(10pm6am) 12/8/1 7 delay odue to ganesh mahotsavat at girgaon station 7/1/18 global procurement issue 21/5/1 8 TBM hault due to parsi temple issue 3/2/18 main drive transfer issue july 2017 land accquisition issue 3/12/1 8 tbm mode chnaged 4/3/19 NATM works at kalbadevi station feb 2019 mining and segment productivity decrease 24.03. 20 Non availability of concrete pump covid 19 22 march 20 Start 5/7/17 Utility diversion issue at Grant Road station 22/3/2 0 no secant piling work carried out at night time(10pm6am) 5/9/17 delay due to ganesh mahotsavat at girgaon station 8/1/18 global procurement issue 10/12/ 2018 TBM hault due to parsi temple 20/2/1 8 main drive transfer issue july 2018 land accquisition issue 2 weeks tbm mode change 3/10/1 9 NATM works at kalbadevi station march 2019 mining and segment productivity decrease 27.03.20 non availablility of concrete pump at CST covid 19 20 april 20 127 days uncertain 23 days 1 day 135 days 17 days 365 days 14 days 171 days uncerta in 2 days 28 days till 22 mar ch

7.4 QUANTIFICATION FOR DELAY OF WORK ,TIME AND COSTOVERUN.

Working time caluculation

description unit duration

Total shift hours per day (11 hours per shift * 2 shifts) Hrs 22

Lunch hour per day hr 1

Dinner hour per day Hr 1

Total working hours per day hr 22

For planning purpose, 7 days a week with alternate Sunday off that count of total 28 working days in a month and 10 public holidays / year are considered.

Table 41: working time calculation

Method used for quantification

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 114 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
A IDENTIFY NUMBER DAYS (LAG)FROM PLANNING SCHEDULE B DERIVE PER/DAY QUANTUM OF WORK CARRIED OUT C=A*B QUANTUM OF WORK DELAYED /UNIT IS OBTAINED D COST OF ACTIVITY/UNITE C QUANTUM OF WORK DELAYED /UNIT IS OBTAINED E=D*C COST OVERRUN

7.5 Impact of tbm hault: Proceedings were carried out in court :

1 21.05.2018

2 23.05.2018

Petition filed in the court by the Anjuman Atash Behram (Parsi Temple)

Court ordered not to cross Parsi Temple, till the verdict

Court has asked to setup a 5 member (IAS officers) committee to make a detailed report on the issue. MMRC-MD was also a part of the committee.

Court has directed the committee to handover the report on 12.06.2018 4 15.06.2018

3 08.06.2018

5 20.07.2018

6 25.07.2018

5 member committee submitted its assessment report on the issue.

CJV has been instructed by Engineer and Employer to stop the TBM-2 works.

Court has asked VJTI an external body to prepare a detailed expertise report in 10days duration.

It was the 10th day, however report was not been submitted by VJTI and they seek 3 days extension for the submission of report. 8 9.08.2018 VJTI submitted the report to court.

7 06.08.2018

9 13.08.2018

Court hearing took place and asked MMRC to show the implementation of VJTI recommendations.

10 17.08.2018 MMRC briefed the , however the bench has been changed.

11 20.08.2018

12 24.08.2018

New bench has asked both the parties to brief the issue in next 3 days. Also, announced to have the next hearing on 18.09.2018.

Chamber of summons issued by MMRC to pre-pone the case.

13 27.08.2018 ime loss has resulted in no discussion on the issue.

14 28.08.2018

Court has asked MMRC to brief the case on 7th / 10th /11th of September

15 27.09..2018 Explanation on the issue and the stand of each parties were briefed till 29.09.2018

16 28.09.2018

17 28.09.2018

Atash Behrams has provided 8 new proposals on the subject matter for review; However MMRC has not considered the same as a part of petition 18raised.

Also, Considering the Supreme court verdict On”SHABARIMALE” HC has asked both the parties to interpret their opinion in our case as wel

18 28.09.2018 Next hearing on the subject matter is on 08-10-2018

19 28.09.2018 Also, Considering the Supreme court verdict On "SHABARIMALE " HC has asked both the parties to interpret their opinion in our case as well.

20 28.09.2018 in our case as well. 20 28.09.2018

21 18.10.2018 Next hearing on the subject matter is on 08-10-2018

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 114 Kasturbhai
University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus
Sr.no Date Proceedings

22 22.10.2018

All arguments and substantiations from both the parties are over , now it left to the Court to give the final verdict.

MMRC has consulted the court for the tentative date of the verdict, in response the court has assured to give the verdict before 3.11.2018 as after 3rd nov-2018 court will be in vacation of Diwali holidays for the next 10 days.

23 30.11.2018 MMRC plead to expedite the verdict and the same is expected by Nov-18 end

24 6.12.2018 Petitioner challenges the verdict in supreme court and mining stopped on 6.12.18

25 10.12.2018 Supreme Court gives it verdict in favour of MMRC and mining resumes on 0.12.18

So due to the parsi temple issue,its impact on the project was such that the tunnel boring machine was halted unnecessary for 134 days. Due to which mining was stopped, so the tbm could not move further in kalbadevi. Other activities like natm were also stopped as it was linked to tbm’s mining activity, so all the activities which had a start to finish relationship with tbm’s activity were affected and delay.

There was unnecessary delay and high cost overruns of about 14 crores was observed

7.5.1 Impact due to Geogology

CJV (construction joint venture ) encountered the change in geological condition after starting the main drive of TBM (downline) later after discussion with gc the rate of mining was considered 10mm/min which gives production of 7 rings a day where as in planned schedule it was considered to be 9 rings a day

So the productivity of tbm was decreased as per decided norms. Hence it would take longer time to erect the segments than that derived by the contractor.Leading to delay in project time line.CJv also carried out bore holes to ascertain the geology to define TBM drive if dual mode was required . In accordance with the lungeon value and grade of roc encountered , the length has been marked where tbm is to be anticipated in closed mode .

7.5.2 The rate of mining will be affected in closed mode from 7 to 3 rings per day Additional 2 weeks for interchanging the tbm mode

7.5.3 Land acquisition issue at kalbadevi

Land Handing Over Details-As per the contract document –Employer’s requirements – Access to works area; the contractual land handing over for Kalbadevi station was to be made at 364 days from the commencement of the project i.e. on 17.07.17 and few parcel by 15.01.18 whereas land were handed over in piece and parcel, the trail of it is mentioned in following table

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
115
T +91 7926302470 F +91 7926302075
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
Table 42: proceedings

7.5.4 Impact due to delayed natm works

Referring to the tender sequence the central cavern was planned after completion of K1 and K2 Block excavation. But due to delay in land handing over and delay in finalisation of layout there:direct impact on central cavern NATM works. To expedite the work CJV changed the sequence of work to breaking of stationcross passages (adits) and commence central cavern works. The adits works started after TBM# 1 retrieval.

As per the geology the grade of rock encounter is of Grade II and Grade III, hencedrilling blasting methodology is adopted to achieve better progress rate. Due to Parsi fire temple issue, the vibration limits are further restricted to lower than permissible values. Secant piling

7.5.5 Impact due to encountered uncharted utilties

The uncharted utility found in the secant pile layout at the garden side required additional time to carry out diversion works hence obstructing the piling works

The secant pile works was affected in garden area due to this uncharted utilities for which application of diversion was done on 28 02 17 and site visit from concerned authority was conducted on 2 03 17 and approval received on 5 07 17

Impact due to Covid -19

Site remained close for 28 days so the entire project schedule is delayed for one month and further even if site will commence from 20 april there will be less labours on site due to safety guidelines of covid 19 and hence the productivity will drastically decrease leading of substantial increase in timeline of the project

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 116 Kasturbhai
– 380009,
T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad
Gujarat
Table 43: building demolition status
Building name Contract date Handing over Float 1. CTS 663 (Jain Bhavan) 17-Jul-17 12-Jul-18 361 2 CTS 667 (Chhatriwala Kantawala) 17-Jul-17 05-Jul-18 354 3 Alim Bhavan 17-Jul-17 13-Nov-18 485 4 Amrut Niwas 17-Jul-17 16-Nov-18 488 5 Fish Market 17-Jul-17 10-Dec-18 512 6 Jan Bhavan / Flower Mansion 17-Jul-17 16-Nov-18 488 7 K2 BLOCK 17-Jul-17 8 Pookhraj Building 17-Jul-17 14-Aug-18 394 9 Khan House 17-Jul-17 22-Nov-18 494 10 Dharamsee Building 17-Jul-17 04-Feb-19 568

7.6 Project key dates and delays

COMENCEMENT DATE : 8 JULY 2016

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 117 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 TABLE 44: PROJECT KEY DELAYS DELAY Start /finish Base line Start/finish difference
KALBADEVI STATION Tbm hault due to parsi temple issue 10/12/18 21/5/18 -135 Land accuiqusition issue July 2018 July 2017 -360 Natm works at kalbadevi station 4.3.19 3.10.19 -171 GRANT ROAD STATION Delay In handing over land Form commencement 14.01.18 106 Tree plantation and cutting issue Form commencement 20.02.17 157 Traffic diversion issue 24.10.16 17.7.17 266 Utility diversion issue 2.3.17 5.7.17 127 Limited hours of working 6.7.2017 Till future GIRGAON STATION Tree plantation and cutting issue 9/2/17 17/05.17 83 Traffic diversion issue 14.12.16 17.5.17 132 Utility diversion issue 2.3.17 5.7.17 107 Delay in productivity of secant piling due to noise issue. 6.02.17 Uncertain-tilll furture Delay due to ganesh mahotsav so excavation work was effected 12.8.17 3.09.17 23 Non availability of strut and waler 29 feb 20 24 feb 20 5 CST STATION Tree plantation issue 19.01.17 26.08.16 189 No availability of concrete pump for pour no 6 27 jan 2020 24 jan 2020 2 Main drive transfer issue 20 deb 2019 3 feb 19 -17 208

7.7 COMPARISON WITH RESEARCH PAPER NUMBER

The classifications of delays are categorized into four basic ways:

1) Critical or Noncritical delays

2) Excusable or Non-excusable delays

3) Compensable or Non-compensable delays

4) Concurrent or Non-concurrent

 Delays that affect the duration or completion of project are critical delays. The delays do not affect duration or completions of project are noncritical delays.

 The delays which are not predicted under any activity which is apart from the control of contractor are excusable delays. In this type, no one is responsible by law for penalty. In Non-excusable delays, the delays are beyond the control of contractor and these delays are deal with contractor and client may be claim to something for the compensation.

 A compensable delay is a delay where the contractor is designated to prolong the time and to add the compensation. Excusable delays are able to compensate. In Non-compensable delays, the contractor is not able to claim for the compensation from the excusable delays.

 A concurrent delay is the concept of presenting an analysis for common construction delays. The argument of concurrency is not to determine the critical delays point of view but from an attitude responsible for damages connected with the delay to the critical path.

CONSTRUCTION PHASE

QUANTIFICATION OF TYPE OF DELAYS

Quantification of delays

Inference: In MMRL-3 UGC02 external factors are highest cause of delay followed by client related isssues. Contractor related issues are fewer and lowest are that of consultants.

So external factors are dominant in causing the delay in the project

STUDY OF DELAY DURING VARIOUS PHASES OF CONTRUCTION

Planning/scoping phase: Delay can be significant when litigation is initiated.

• Development phase: Permitting (environmental, fish and wildlife, railroad, etc.), right-ofway acquisition, and utility agreements can be significant causes of delay.

• Contracting phase: Generally, this phase has less incidence of delay but can still have issues.

• Construction phase: This phase has numerous opportunities for delay and is often the delay most visible to the public

non critical excusable non excusable compensable non compensable

type of delays

Inference: In MMRL-3 UGC02 critical delays and non excusable delays are major and least delay is caused by excusable and compensable factors

• Permission for utility diversion issues at grant road station 60

• rehabilitation issue at kalbadevi and girgaon land accquisition issue for kalbadevi station box 365

• less awareness lead to protests to oppose the project

• procurement of tunnel boring machine 146

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM,
118
PROJECT TRAINING 2019-2020 Kasturbhai
T +91 7926302470 F +91 7926302075
GRANT ROAD.
Bhumika Raj (UC5316) Semester-08
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
0 1 2 3 4 5 6 7 8 9 10 critical
FIGURE 21: QUANTIFICATION OF DELAYS 0 1 2 3 4 5 6 7 8 CLIENT RELATED ISSUES CONTRACTOR RELATED CONSULANT RELATED ISSUES EXTERNAL FACTORS
COMPARISON OF DELAYS Column1 Column2
PRE
PHASE • delay at girgaon sttaion due to ganesh mahotsav 14 • delay for natm works at kalbadevi 171 • global procurement issue of lifting pinz 1 • Sewer line diversion at grant road 127 • tbm hault due to parsi temple issue. 135 • slow piling due to noise issue• revision in girgaon station pile plan 30 • non avalibility of strut and waler 10 • (pour 4 )concrete pump unavailability 2 • increase in scope of work of bcs(building condition 20 survey) • traffic diversion issue at grant road 266 • Late response from MGL at girgaon for div. scheme 201 • tree plantation issue at grant road 157 • covid 19 28
CONSTRUCTION

CONSTRUCTION PHASE DELAYS

•COVID 19

•TREE PLANTATION ISSUE AT GRANT ROAD

•LATE RESPONSE FROM MGL AT GIRGAON FOR DIV.

•TRAFFIC DIVERSION ISSUE AT GRANT ROAD

•INCREASE IN SCOPE OF WORK OF BCS(BUILDING

•(POUR 4 )CONCRETE PUMP UNAVAILABILITY

•NON AVALIBILITY OF STRUT AND WALER

•REVISION IN GIRGAON STATION PILE PLAN

•TBM HAULT DUE TO PARSI TEMPLE ISSUE.

•SEWER LINE DIVERSION AT GRANT ROAD

•GLOBAL PROCUREMENT ISSUE

•DELAY FOR NATM WORKS AT KALBADEVI

•DELAY AT GIRGAON STATION DUE TO GANESH

Inference : from the above dashboard we can say that the majority delay was caused due to the delay at grant roadstation due to traffic diversion which tokk a lot of time for approvals from authorities while leasr delay is caused due to unavailablility of strut and waler because of the unavailabiliy of material from contractor side

Inference: from the adjacent dashboard we can say that in pre-constructio phase the majority delay is caused due to the rehabilitation issue at kalbadevi and grant road station.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 119 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 0 50 100 150 200 250 300 350 400 tility diversion issues at grant road station rehabilitation issue at kalbadevi and girgaon •procurement of tunnel boring machine PRE CONSTRUCTION DELAY DAY Column1 Column2 14 171 1 127 135 30 10 2 20 266 201 157 28
Description of delay DAYS

Total duration of the project in contract was 1638 days, but the setback is that the delay is about 93% of the total time duration which is 1526 days.So the project is delayed majorly due to delays in construction phase which is 883 days and in pre construction phase also delay of about 643 days is observed. ( refer pg no.118,119)

As delays till 22 march are curated the project lags behind substantially and it will take almost twice times the time taken for completion and handing over which is tentative 6 nov 2023 instead of 10 jan 2012.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 120 Kasturbhai
University Road,
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus
Navrangpura

7.8 CONCLUSION:

Construction of infrastructure project like metro in a developing country like India is quite a task, due dilligence and patience is required for carrying out the same.Mumbai metro is one of those mega projects of india, because Mumbai is a mega city with highest number of commuters, but it’s not easy there are obstacles that slow down the cost project time and cause cost over runs

When comparing with the research paper and from my study and observation of delays, majority caused are due to external factors in Mumbai metro line 3 –UGC02, also client related administrative factors have cause delay. Contractor related issues are still prevelant but not at large scale, as they are linked with the client tasks.

In a city like Mumbai which is densely populated and carrying out mega construction in congested and century old areas like kalbadevi and girgaon it’s a task it self. So geography and city’s development also plays an important role in identifying the delays or assuming the delays

So if client related tasks get delayed (eg tbm hault at kalbadevi)

 Entire project time line is disturbed if each project is linked as they have a start to start type relationship.( all tbm related activities hindered)

 Start to finish relationship are not that much affected as they are not linked with any other task( as they are independent( stations works at kalbadevi not hindered)

Effect and project duration

 Total duration of the project in contract was 1638 days, but the setback is that the delay is about 93% of the total time duration which is 1526 days

 As delays till 22 march are curated the project lags behind substantially and it will take almost twice times the time taken for completion and handing over which is tentative 6 nov 2023 instead of 10 jan 2012. ( refer pg no 118,119 )

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
121
+91
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F
7926302075

TASK 2: DESIGNING A LABOUR COLONY

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 122 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075

8 DESIGNING A LABOUR COLONY:

PURPOSE :The temporary housing project provides the migrant construction workers and their families a stable option despite the transient nature of their work.Due to rapid urbanisation throughout India, large-scale housing developments litter city margins, catering to a growing middle class. Migrant workers building these high-end developments temporarily live on the construction sites in labour colonies. The labour colonies are innovative and productive, but highly susceptible to dysfunction, suffering from a lack of any basic infrastructure.

Drawing from My site experience and data , I have designed a temporary housing system to accommodate 250 workers and their families. The system aims to improve living conditions for the inhabitants by providing practical aspects of drainage, insulation, ventilation, sanitation, safe spaces for women and children as well as social spaces for communal daily activities, a children’s crèche and open spaces that allows movement.My main aim is to build a housing colony which is sustainable and economically suitable.So the materials and technologies are choosen in such a way that they justify the aim of the project.

CHALLENGES FACE:Mostly the challenges faced are that quality of labour colony provided in india at majority of construction is quite unsuitable. This poses threat to the workers life and their families residing in. Also the contractors usually fail to provide a habitable housing colony,, they end up compromising with the workers habitat. The situation is not that grave now but the difficulties still prevail.

Zonw

Zone

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 123 Kasturbhai
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura
DETAILS OF PROPOSED LABOUR COLONY Place MUMBAI No of labours 250 Couples 50 Men 200 Location BYCULLA Soil conditions SOFT SOIL Type of construction: Modular steel and concrete Zone 1:labour accomodation 3 buildings 2 storey eachIncluding semi private an private areas Zone 2 : dining area 30*11 m dining area
3:latrines Bio toilet blocks
4: creches 10*8 m crèche for infants
Recycling composite on site.
45: LABOUR COLONY DETAILS
Zone 5:community gathering Zone 6:water/ drainage facilities
TABLE

IDEALOGY USED:

ZONE 1:LABOUR ACCOMODATION

Total three buidlings

Two buildings with 2 storey accommodating bachelors with 5 person in one unit, so total 40 units accommodating 200 labours . And for couples 25 accomodations are provided each couple allotted a room of size 4*4 m.

Further semi private area is provided for cooking some minor things so the private area in room doesn’t get affected and damaged by the smoke produced by chulahs and also for the easy movement and keeping in mind privacy.

ZONE 2 : DINING AREA

Dining area is provided adjacent to the boundary of site which is approx. 30% of the labour accommodation including washing area. Drinking water facilities and cooking area also and 20 m away from toilet areas.

ZONE 3:WASHROOMS

The ratio is kept 1:15 for men and women for bathing areas and toiltes as per the They are kept in the vicinity of the labour accomodation so it is safe and also bio toilet blocks are used so the water can be recycled and the methane gas can be stored in form of energy and used for other activities.

 ZONE 4: CRECHES

It is a very important aspect because of most of the female labours in india have infants, Also according to the cenus by an NGO, organisation of labour presented that about 60% of the women labours have infants.

So it was very important to provide a crèche ,so in the designed project is placed in centre of the accommodation so they can keep a check.

 ZONE 5:COMMUNITY GATHERING

A Community space is needed for the activities to be carried out on the labour colony , there can be awareness program or any other programs can be conducted easily.

 ZONE 6:WATER/ DRAINAGE FACILITIES

So four septic tanks are provided for the same purpose , where water can be used for Daily activities and also reverse osmosis water plant is provided which ensures that the people on site get sufficient and safe water for drinking purpose. Sceptic tanks are also provided for waste collection from the site. Per person consumption of water is 4 litres, so for 250 people about 1000 litres of water is needed everyday so each tank of capacity of 250 litres is provided on site.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 124 Kasturbhai
Ahmedabad
380009,
T +91 7926302470 F +91 7926302075
Lalbhai Campus University Road, Navrangpura
Gujarat
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 125 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 126 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316)
FIGURE 22: GRID LAYOUT FIGURE 23: FOOTING LAYOUT FIGURE 24: COLUMN LAYOUT
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 127 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316)
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 128 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
IGURE 26:
PLAN FIGURE 25: ROOF PLAN
Bhumika Raj (UC5316)
F
MEZZANINE ROOF
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 129 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020 8.3
Bhumika Raj (UC5316)
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 130 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Semester-08 PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316)
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 131 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
PROJECT TRAINING 2019-2020
Bhumika Raj (UC5316) Semester-08

8.6 METHODOLOGY

1 AFTER FOUNDATION WORK IS DONE BASE PLATE AND COLUMNS ARE CONNECTED TOGETHER

2 AFTER VERTICAL ELEMNTS ARE ERRECTED , HORIZONTAL ISMC IS FIXED WITH NUT AND BOLT

3 TUBULARS ARE PLACED ON THE ISMC AT THE SPACING DECIDED

4 ROOFING SHEET IS ATTACHED AR GROUND LEVEL THEN SAME PROCESS IS REPEATED FOR SECOND FLOOR

BENEFITS OF USING MODULAR STEEL AND CONCRETE STRUCTURE

QUALITY SPEED REUSE

5 IN THE END ALL THE PALL PANELS ARE ASSEMBLED and doors and windows are attached

SUSTAINABLE LESS MAN POWER

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 132
Lalbhai Campus University Road,
Ahmedabad – 380009, Gujarat
+91
+91 7926302075
Kasturbhai
Navrangpura
T
7926302470 F
FIGURE 27: METHODOLOGY OF MODULAR CONSTRUCTION

FACULTY OF TECHNOLOGY (PROJECT TRAINING 2020) CEPT UNIVERSITY) ABSRACT SHEET

Name: BHUMIKA RAJ Code : UC5316

Project Name: LABOUR COLONY MMRC-3 UGC02

1.01

Excavation in hard rock / boulders (more than 1/2 Cum in size) by chiselling to required level for foundation, trenches, rafts, plinths, levelling area etc , upto required depth including disposing off excavated material at a location within site as per direction of the PM by stacking or spreading compacting as per direction of PM; shoring, strutting, stepping,dressing,gradding, cleaning, removing and excavating loose pockets and consolidating them by backfilling as directed by the PM etc. All complete as detailed in

specification and conforming to safety rules of authority from time to time.

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge

1.03

Back filling /Filling with approved good quality earth in plinths, area levelling etc. In layers each not exceeding 200mm in depth, breaking clods, watering, compacting each layer with vibratory compactor and at inaccessible places with wooden/steel rammers to achieve 95% proctor density at optimum moisture content; dressing up embankments; if required bailing/pumping out of water by localised dewatering system to keep site dry while back filling; costs includes transportation of all materials, labour, machinery etc, complete as per direction and to the satisfaction of the

T

F

Delhi Schedule of Rates/2.1.1 /Pg7 9)

(Refer Delhi Schedule of Rates/2.25/ Pg11 6)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 133
380009,
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat
+91
7926302470
+91 7926302075
Ite m No. Item Description Unit Quantit y Rate Amount Remarks 1.00 EARTHWORK
Cu.M. Refer Delhi Schedule of Rates/2.6.1 /Pg8 1 a For Labour Colony Cu.M. 171.00 181.85 31096.35 b For Canteen Cu.M. 48.34 181.85 8790.63 c For creche Cu.M. 15.50 181.85 2818.68
1.02
Sq.M.
a For Labour Colony Sq.M. 38.12 92.55 3528.01 b For Canteen Sq.M. 70.69 92.55 6542.36 c For Creche Sq.M. 52.16 92.55 4827.41
(Refer
Cu.M.

1.04

Consultants and or Technical Specifications..

2.00

Anti-Termite Treatment

Supplying and spreading pesticides CHLORPYRIPHOS or other chemical approved by central insecticides Board as directed by the manufacturer and spraying the mixture uniformly by sprayer as pre-construction anti- termite treatment at the rate of 7.5 litres (or as directed by the manufacturer specification) per sqm on vertical and 5 liters. (or as directed by the manufacturer specification) per sqm on horizontal surfaces of the sub- structure, within the trenches, 50% of the emulsion to be filled in the holes made in trenches at 150 mm centre to centre etc. complete all as per IS 6313 Part-II(latest) specification & as directed by the Engineer-incharge.

2.02

CONCRETE

Providing, transporting, pumping and laying approved M25 grade designed mix batched, controlled reinforced cement concrete, manufactured at site , conforming to with minimum cementitious content as per IS including flyash upto maximum 33% of the cementitious material and maximum water cement ratio 0.45 or as specified by Structural Consultant including using approved quality ingredients and admixtures and placed either with pump/manual/lift of concrete at any lead, lift, height or depth, including compacting with vibrators,curing and hacking / preparing the exposed surface wherever required to receive plaster or floated with powered rafts / foundations, steel troweled surface wherever specified, curing etc.

For Footing

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 134 Kasturbhai
T +91 7926302470 F +91 7926302075 c For Toilet Block M. 75.19 28.25 2124.12 d For Creche M. 30.00 28.25 847.50
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
Cu. M. (Refer
181 )
Delhi Schedule of Rates/5.1/Pg
a For Labour Colony Cu. M. 79.19 7718.2 6 611209.0 1 b For Canteen Cu. M. 22.39 7718.2 6 172811.8 4 c For CRECHE Cu. M. 7.19 7718.2 6 55494.29
a For Labour Colony Cu.M. 82.86 219.65 18200.20 b For Canteen Cu.M. 25.98 219.65 5706.51 c For creche Cu.M. 8.30 219.65 1823.10
M.
a For Labour Colony M. 102.00 28.25 2881.50 b For Canteen M. 78.00 28.25 2203.50
(Refer Delhi Schedule of Rates/2.35 .1/Pg 126)

3.00 BRICK MASONRY

3.01

Providing and laying common burnt claybuilding brick having crushing strengthnot less than 35 kg/sq.cm. in cement mortar 1 : 6 (cement : fine sand )including transportation, tools, curing and erecting in line and level above plinth etc. complete

4.00 FORMWORK

4.01

Designing, Providing, erecting and fixing in position customs / system designed form work true to line and level, for foundation, columns etc with use of plywood with required steel props and staging, applyingshuttering removal emulsion/oil as approved, required bracing, making leak proof joints etc, complete at all heights, depths, leads and lifts. System design should be such that staging, supporting, holding shall be strong enough not to allow any sagging, deformation, bending, curving, undulation in vertical plane and in length. Exposed surfaces shall be free of blemish, residues of curing compound uniform in colour, free of construction joint System to be from approved proprietary make to achieve approved no of days cycle. Form work should be designed for fixing at interned location allowing expected dead and live loads during working. Also it should be able to carry dynamic loads side thrust etc.Also include removing and dismantling the aforesaid assembly after specified or as approved period from the day of casting of concreting to the satisfaction of the PM. All staging and formwork systems must be designed for the loading criteria stipulated by the consultant and such design shall be approved by the PM before implementing on the site. The rate quoted shall be for erecting staging, form- work dismantling, dewatering etc.. All Supporting system of form work will be only with steel props & staging shall be duly designed to carry proposed loads.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 135
T
F +91
b For Canteen Cu. M. 42.26 7718.2 6 326173.6 7 c For Toilet Block Cu. M. 27.59 7718.2 6 212946.7 9 d For Creche Cu. M. 9.96 7718.2 6 76873.87
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
7926302075 For grade slab
Cu. M. (Refer Delhi Schedule of Rates/6.3.1/P g2 75) a For Canteen Cu. M. 52.58 7722.6 5 406056.9 4
Sq.M
(Refer Delhi Schedule of Rates/5.9.1/ 5.9. 2/Pg188,189 )
Footings Sq.M. 402.00 284.85 114509.70
a For Labour Colony

5.00 REINFORCEMENT

5.01

Providing, Supplying, Transporting to site, storing, decoiling, straightening, cutting, bending, spirally hooping, bundling and placing, in position HYSD Fe500 reinforcement bars, to correct shape and size as per detailed drawings, specifications preparing and getting approved bar-bending schedules for all reinforced concrete work such as footings, walls, columns / slab columns, beams, slabs, staircase, rafts etc. with correct size of concrete cover blocks (of equivalent approved) of same grade as of concrete and galvanized binding wire of 18 gauge; required dewatering, Provide required labour and machine / equipment's / tools / tackles for handling, shifting, bending, binding, etc.

6.00 STRUCTURAL STEEL

6.01

Providing, preparing shop drawings, obtaining Structural Consultants approval, supplying, fabricating in accordance with IS:800, delivering at site, hoisting and fixing in position at all locations, heights, lifts, leads and levels, including all temporary staging and supporting work and making all structural steel work in accordance with the design, drawings prepared by the Consultants. The rate of steel work shall include cutting, grinding, machining, assembly, welding, jointing, of single / building up new sections with anchors, angles, beams, canopy, supports, column, trenches angel protections, trench covers etc. cost of fasteners (nuts, bolts and washers), pre-heating the sections to temperatures up to 250 degree C if thickness of the section is equal to or more than 25mm. Fabrication wall involve connections using plates, channels and angles, gusset plate, foundation bolts, cleats, fasteners, stiffeners etc. as per drawing steel conforming to IS : 226 and IS : 2062 with minimum yield strength of 350 Mpa.The rate shall also include one coat of rich primer after properly cleaning the steel surface with wire brush and mild acid solution followed by washing with water and drying the surface completely, to be applied to individual fabricated parts of the structure prior to their erection & assembly in their final place. The rate shall also include the synthetic enamel paint system in approved shade and of approved make as per recommendations of the paint manufacturer to the approval of PM etc.complete

(Refer Delhi Schedule of Rates/10.1/Pg 66 7)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 136
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Footings Sq.M. 186.80 284.85 53209.98
b For Canteen
Footings Sq.M. 44.22 284.85 12596.07
c For Creche
Kg a For Labour Colony Kg 2030 54.36 110350.80 b For Canteen Kg 574 54.36 31202.64 c For creche Kg 261 54.36 14187.96
KG

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

Providing and laying Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1cement : 4 coarse sand) including tools, labours etc. complete

Providing and fixing M.S. angle 96x48x1.6 mm to act as nosing with lugs of M.S. flat 10x5 mm, 10 cm long, forked at end 60cm apart (minimum three lugs to be provided), including necessary welding and applying a priming coat of approved primer on exposed surface etc. complete.

(Refer Delhi Schedule of Rates/11.35/P g7 71)

ROOFING

Providing and fixing corrugated G.I. sheet roofing 0.07 mm thick with zinc coating not less than 275 gm/m² including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required etc. complete

(Refer Delhi Schedule of Rates/12.1.1/P g 80)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
137
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470
F +91 7926302075
GROUND FLOOR (50 x 50 x 2)mm Kg 566.75 86.05 48768.84 TUBULAR(96 x 48 x 1.6)mm Kg 7381.44 86.05 635172.91 ISMC 150 Kg 2116.8 86.05 182150.64 FIRST FLOOR (50 x 50 x 2)mm kg 769.44 86.05 66210.31 purlin Kg 5536.08 86.05 476379.68 ISMC 150 Kg 2116.8 86.05 182150.64 b Creche kg 522.96 86.05 45000.71
a For Labour Colony
7.00 FLOORING
Sq.M. (Refer Delhi Schedule of Rates/11.26.1/ P g761) a For labour colony Sq.M. 264 1531.85 404408.40 b for canteen Sq.M. 305 1531.85 467214.25 c For Creche Sq.M. 55.5 1531.85 85017.68
Sq.M.
For Second Floor of Labour Colony Sq.M. 264 132.25 34914.00
8.00
Sq.M.
a For Labour Colony Sq.M. 864.00 1234.25 1066392.0 0 b For Canteen Sq.M. 360.00 1234.25 444330.00 C For Creche Sq.M. 80.00 1234.25 98740.00

9.00 WALL PANELS

d

Providing and fixing partition upto ceiling height consisting of G.I. frame and required board, including providing and fixing of frame work made of special section power pressed/ roll form G.I. sheet with zinc coating of 120 gms/sqm(both side inclusive), consisting of floor and ceiling channel 50mm wide having equal flanges of 32 mm and 0.50 mm thick, fixed to the floor and ceiling at the spacing of 610 mm centre to centre with dash fastener of 12.5 mm dia meter 50 mm length or suitable anchor fastener or metal screws with nylon plugs and the studs 48 mm wide having one flange of 34 mm and other flange 36 mm and 0.50 mm thick fixed vertically within flanges of floor and ceiling channel and placed at a spacing of 610 mm centre to centre by 6 mm dia bolts and nuts, including fixing of studs along both ends of partition fixed flush to wall with suitable anchor fastener or metal screws with nylon plugs at spacing of 450 mm centre to centre, and fixing of boards to both side of frame work by 25 mm long dry wall screws on studs, floor and ceiling channels at the spacing of 300 mm centre to centre., Galvanised M.S. fixing channel of 99 mm width (0.9 mm thick having two flanges of 9.5 mm each with zinc coating of 120 gms/sqm(both side inclusive)) to be provided at the horizontal joints of two boards.

10.00 WHITE WASHING

Providing and finishing with white washing lime on walls to give even shade after throughly brushing surfaces to remove dirts, remains of loose particles including scaffolding, tools and labours etc. complete

11.00 DOOR,WINDOW

Providing and fixing ISI marked flush door shutters conforming to IS : 2202(Part I) non-decorative type, core of block board construction with frame of 1st class hard wood and well matched commercial 3 ply veneering with vertical grains or cross bands and face veneers on both faces of shutters: 35 mm thick including ISI marked Stainless Steel butt hinges with necessary

12.00 MISCELLANEOUS

Providing bio toilet of Dimension 1*1*2.5 m of Color White of suitable brand of Material PUF Panel Feature Portable and Prefab Bidet Size 600 x 450 mm on site with specific drainage facitlities and water pipe facilties

F

(Refer Delhi Schedule of Rates/9.105/P g5 59)

(Refer Delhi Schedule of Rates/Vol.2/13 .3 8/Pg931)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 138
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
T +91 7926302470
+91 7926302075
Sq.M.
For Labour Colony Sq.M. 2198.52 1741.15 3827953.1 0 For creche Sq.M. 207.52 1741.15 361323.45
Sq.M.
a For Canteen Sq.M. 987.98 11.50 11361.77
Sq.M.
a For Labour Colony Sq.M. 135.36 1886.70 255383.71 b For Creche Sq.M. 2.98 1886.70 5622.37 c For canteen Sq.M. 5.64 1886.70 10640.99
(Refer Delhi Schedule of Rates/9.21.1/Pg 459)s
No. a bio toilets No. 30.00 10000.00 300000.00 TOTAL COST RS 11298148.8

ALTERNATIVE ACTIVITY

This activity aims to to provide an alternative to the Natm method used at kalbadevi station, so the alternative adopted ADECCO-RS method which uses the concept of Analysis of Controlled Deformation in Rock & Soils. ADECCO-RS method is proposed for the construction adit 3 and central cavern length of Kalbadevi station of Mumbai Metro Line 3 –UGC_02

Details of the project:

Name of the project: Mumbai metro line 3-UGC-02

SITE OFFICE ADDRESS – Gate 3, Azad Maidan, Nr. Metro Cinema, Mumbai – 400001, Maharashtra

SCOPE OF WORK – Design and construction of Underground Stations namely CST Metro, Kalbadevi, Girgaum and Grant Road and Twin Tunnel between CST and Mumbai Central – Up Line (from Ch. 3770.58 m to Ch. 7842.62 m) and Down Line (from Ch. 3801.05 to Ch. 7860.22 m) by TBM including Scope of works comprising of Civil, Architectural, E&M works as defined in agreements.

PROJECT TYPE – EPC (Engineering, procurement and construction) Contact. EPC Contractor is responsible for all activities engineering, procurement and construction and hand – overs the project to the owner.

Scope of the Alternative : kalbadevi station consists of three adits and one central cavern

And its work is carried out natm method(New Australian Tunnelling Method) so the alternative suggested is Adecoo-RS method .

Elements observed: Proposed alternative method Adecco-RS method on stretch of 451m from Kalbadevi to Girgaon station.Elements covered are : one adit and central

Alternative activity suggested: This activity aims to to provide an alternative to the Natm method used at kalbadevi station, so the alternative adopted ADECCO-RS method which uses the concept of Analysis of Controlled Deformation in Rock & Soils. ADECCO-RS method is proposed for the construction adit 3 and central cavern length of Kalbadevi station of Mumbai Metro Line 3 –UGC_02

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 139
T +91 7926302470 F +91 7926302075
3
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
TASK

8.7 METHOD STATEMENT FOR CONSTRUCTION OF TUNNEL BY ADECCO-RS

DESCRIPTION OF ADECCO-RS METHOD

This method was developed in eighties in Italy by Professor Lunardi. As the name ADECORS (L’Analisi delle Deformazioni Controllate nelle Rocce e nei Suoli) says, it is a method of controlled deformation. Its introduction to tunnelling practice can be dated as occurring in 1985 when it was tried out for the first time in the world by the Professor Lunardi and Doctor Bindi during the construction of some tunnels on the Florence-Arezzo section of the new high speed railway line between Rome and Florence.

1)PURPOSE

This document sets out the method statement for exacavtion, mucking and deposition in order to carry out works In a planned and systematic manner. The aim of this document is to carry out outline the method to be deployed for construction of adit , widening of tunnel and excavation for central cavern

2)SCOPE

To set out the requirements for adit , cavern and tunnel widening by ADECCO-RS works on the kalbadvei station of MML-3 and maintaining safety quality and environmental compliance

3)

8.8 METHODOLOGY INTRODUCTION(ADECCO-RS)

This method was developed in eighties in Italy by Professor Lunardi. As the name ADECORS (L’Analisi delle Deformazioni Controllate nelle Rocce e nei Suoli) says, it is a method of controlled deformation. Its introduction to tunnelling practice can be dated as occurring in 1985 when it was tried out for the first time in the world by the Professor Lunardi and Doctor Bindi during the construction of some tunnels on the Florence-Arezzo section of the new high speed railway line between Rome and Florence.This method is based on the Analysis of the COntrolled DEformation in Rocks and Soils” (ADECO-RS).

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 140 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Equipments: 1 Casagrande drilling rig 2 Fiat-Hitachi excavators 3 Fiat-Kobelco wheeled loaders 4 2 concrete spraying machines 5 Manitou MRT1850 hoisting platform

Survey phase/Design phase

Design Stage

Diagonsis phase stabilisation measures

 Survey Phase - Determine the Characteristics of the medium.

1)Geological, geo-morphological and hydro-geological characteristics of the area.

2)Location and definition of terrain through which the alignment passes.

3)Tectonics, geological structure and the stress state of the rock mass.

4)Hydro-geological regime of the rock mass. 5)mechanical characteristics of the materials

 Diagnosis Phase – Divide the tunnel sections in Category A, B or C, defining the details of deformation development and types of loads mobilised by excavation.

1)Using Analytical and/or Numerical Methods, predict the behavior category and deformation response for various sections of the tunnel alignment

 Therapy Phase – Decide type of confinement and/or pre-confinement and test their effectiveness by mathematical modelling

1)Decide about confinement and/or pre-confinement measures, for various sections of tunnel alignment.

2)Decide about excavation systems also, simultaneously, for various sections of tunnel alignment.

 By using this approach, which is based on a clear distinction between the design stage and the construction stage of tunnels. it was possible to reliably estimate construction costs and times for the project in advance and this in turn made it possible to award contracts for the work on a lump sum “turnkey” basis for the first time in the history of underground works for projects of these dimensions and difficulty.

 Other important characteristics of the ADECO-RS approach are the centrality of the deformation response of the ground to the action of excavation and the use of full face advance employed even under the most difficult condition

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 141 Kasturbhai
380009,
+91 7926302470
+91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat T
F

DIAGONIS

Characterisation of the medium in terms of rocks

Deciding the intervention measures in the basis of behaviour categories

composition of tunnel section type

longitudinal and cross section

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 142
PHASE FIGURE 28: ZONES FOR CONSTRUCTION FIGURE 29: TIMELINE FOR ADDECO -RS APPROACH

8.9 DEFINITION OF CASES

On the basis of the methodologies adopted there were three outcomes wbich were analysed.

Case Type-1

Stable Core Face - Rock Type Behaviour

The face as a whole is Stable. Only local instability is found due to the fall of isolated blocks. Stabilisation techniques needed for preventing deterioration of rock and to maintain profile of the excavation.

Case Type-2

Stable Core Face in Short Term - Cohesive Type Behaviour

if Medium is stressed in the “Elasto-plastic range”.

 Stress sate is low in relation to the characteristics of the medium.

 Sufficient to intervene on cavity only using radial action and no longitudinal intervention in advance core is needed.

Instability manifests in the form of widespread spalling at the face and around the cavity.Allows sufficient time to employ traditional radial confinement measures, after passage of face.In some circumstances, it may be necessary to resort to pre-confinement of cavity, to contain deformation within acceptable limits.Presence of water to be prevented by suitable drainage arrangements.

Case Type - 3

 If Medium is stressed in the “Failure range”.

 Stress state is high in relation to the characteristics of the medium.

 It is of primary importance to stiffen the advance core with pre-confinement of cavity, which may be supplemented with confinement of cavity after the passage of the face.Deformation is unacceptable because it develops immediately in failure range. Ground reinforcement needed ahead of face to

380009, Gujarat

T +91 7926302470

F +91 7926302075

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
KALBADEVI,
143
STATIONS : CST,
GIRGAUM, GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – FIGURE 30: EXAVATION FOR HARD ROCK FIGURE 31: EXCAVATION FOR COHESIVE ROCK FIGURE 32: EXCAVAVTION FOR SOFT ROCK

develop pre-confinement action. Presence of water is absolutely unacceptable and shall be prevented by drainage arrangements.

8.10 STABILITY MEASURES

On the basis of the deformation response there is ANALYSIS done and further stbaility/ intervention measures are suggested on basis of that

1 Protective Intervention :The intervention channels the stresses around the advance core to perform protective function, that ensures that the natural strength and deformation properties of the core are conservedFull face sub horizontal grouting Full face mechanical precutting

Reinforcement Intervention The intervention acts directly on the consistency of the advance core to improve its’ natural strength and deformation properties by means of appropriate ground reinforcement techniques.

8.11 STEPWISE PROCEDURE

T

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
144
380009,
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat
+91 7926302470
+91 7926302075
F
STEP 1 REINFORCEMENT OF CORE FACE USING FIBRE GLASS TUBULAR ELEMENTS
STEP 2 FULL FACE EXCAVATION BY CASCAGER STEP 3 PLACEMENT OF LAYER OF SHOTCRETE ON FACE STEP 4 PRECUTTING STEP 5 Positioning of the Steel Rib under the last precut and shotcreting STEP 6 The Cycle continues repeating Phase-2, 3, 4 & 5,until advance length is complete STEP –7 : Excavation and Casting of Invert STEP -8: The Cycle returns to Phase-1 STEP -9 : Waterproofing is placed and Final lining is cast

STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.

8.11.1 Methodology :

UNDISTURBED ZONE

Phase–1: Reinforcement of the Core Face using fibre Glass Tubular Elements

TATA HITACHI EXCAVATOR

DRAINAGE PIPES FOR DEWATERING

REINFORCED TUBE EXTENDED ABOUT 1224 M LONG

UNDISTURBED ZONE

UNDISTURBED ZONE

Phase-2: Full Face Excavation

AUTOMATIC SHOTCRETE MACHINE IS USED FOR THIS PURPOSE

EXCAVATION OF THE FACE IS CARRIED OUT TILL 1M ADAVANCE

UNDISTURBED ZONE

Phase-3 : Placement of a layer of Shotcrete on the Face

STEEL RIB/ LATTICE GIRDER IS PLACE AT INTRVALS OF 1M.

Phase–4: Positioning of the Steel Rib under the last pre-cut and shotcreting

Kasturbhai Lalbhai Campus University Road, Navrangpura

Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

SHOTCRETE IS CARRRIED OUT TILL 1M

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
145

NATM(New Australian tunnelling method)

HOW METHODOLGY DIFFERS FROM NATM

ADECCO-RS

 It was first developed in alpine region used for excavation and widening purposes .drilling and blasting plays a major role in this method

 Full face excavation is carried out according to the marking profile made by the blast experts, so that design is followed by the engineers facing setbacks like undercut and over cuts.

 There is no provision like tubes made in the area beyond the face of excavation for stabilisation of soil ahead, natm is carried out solely on the basis of drilling blasting methods.

 Also there is no provision made to reduce or eliminate the hydraulic pressure caused due to water ingress it can be detected only when problem is faced not like Adecco-rs method where we can reduce the water levels by dewatering

 After excavation of one cycle of 1m , the structure is supported by rockbolting , wiresmesh and shotcrete which is called the primary lining and secondary lining is done quite later .

 At MMRCL-LINE3 UGC02 Shotcrete is carried out by pneumatic shotcrete machine

 Advance per day achieved is about 1 m in rocky stable soil condition(basalt rock in South Mumbai )

• The ADECO-RS, an Italian tunnelling method known also as the Lunardi method, was used for the excavation. Full-face excavation without regard to geological conditions is a typical feature of this method.

• The full-face excavation was carried out under the protection of canopy tube presupport; the excavation was stabilised by horizontal jet grouting and, under extremely bad geological conditions, even by 12m long glassfibre reinforced plastic anchors

• Stabilisation of the excavation roof by long boreholes; pressure injection of grout into the boreholes for the 13m long perforated tubes forming the canopy tube pre-support; injection of grout into the tubes

• Each of each borehole provided with a drainage casing pipe, which was designed to eliminate the hydraulic pressure on the excavation face. The abovementioned operations were carried out by means of a Casagrande drilling rig and a high-performance grouting set, which was placed on the surface.

• Before the work on the stabilisation of the excavation face and roof could begin, it was necessary to support the concavely moulded excavation face by a 15cm thick layer of steel fibre reinforced shotcrete.to optimise the effect of the grouti

• ng and reinforce the excavation face so that it resisted the ground and grouting pressures.

• Shotcrete is carried out by automatic shotcrete machine instead of pneumatic shotcrete

• Advance per day is about 3 m for per day excavation for face

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 146

8.12 QUANTITY ANALYSIS

Note :refer car 3 for detailed analysis of quanity for (explosives , detonators and other activities ) for natm

*Considering the dimensions of adit and central cavern remain same so for both methods the quantity for shotcrete and installation lattice girder/ steel rib stays same(refer car 3)

*Change is seen in the no of holes as for ADDECO –rs method there are drainage holes and holes for reinforced glass tubes also provided which increases the no of holes compared to natm

QUANTITY ESTIMATION BY ADDECO RS METHOD BY ADECCO-RS

Tubular holes

Drainage holes

Drainage holes: 6 Holes OF Length 9 m for 10 m long cavern face( reference comparison of natm and adeco-rs methods,Using monte cuneo tunnel, italy, as an example Peter balušík, libor MAŘÍK)

Tubular holes: At the distance of 200mm 13 m long beneath the roof stabilising boreholes so total 250 number in grid pattern ( reference comparison of natm and adeco-rs methods,Using monte cuneo tunnel, italy, as an example Peter balušík, libor MAŘÍK)

Total holes - 6+250=256

=6*9*0.05 – 2.7 m3

=250*13*0.05-162.5m

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 147 Kasturbhai
Road,
Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
Lalbhai Campus University
Navrangpura

8.13 TIMECYCLE FOR ADECCO –RS METHODLOGY

( reference comparison of natm and adeco-rs methods,Using monte cuneo tunnel, italy, as an example Peter balušík, libor MAŘÍK)

of

with 1 hour break each , pull of 1.15 at adit is observed

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 148 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075
TIME CYCLE FOR ADIT 3 ( CLASS 2 ROCK) sr. no FOR ADIT UNIT DETAILS DESCRIPTION 1 area m2 89.25 2 peripheral length m 12.5 3 effective pull m 1.00 4 Core face reinforcement days 120
shifts
5 survey and mapping hours 2
and
in evening. Advance 1-6m 6 Including tunnel advance, mucking, installation of 6 to 8 steel ribs (2 IPE 240, step 1.0 m) with strut in the invert, shotcreting (30 cm thick) days 60 72 hours taken to remove muck everyday for 1 pulls OF 6M 7 for excavation, reinforcement and concreting of 6 ÷ 8 m kickers hours 12 Advance 1-6m 8 Including tunnel advance, mucking, installation of 6 to 8 steel ribs (2 IPE 240, step 1.0 m) with strut in the invert, shotcreting (30 cm thick) days 60 72 hours taken to remove muck everyday for 1 pulls OF 6M 9 for excavation, reinforcement and concreting of 6 ÷ 8 m kickers hours 12 10 total time for activity hours 266 total time taken for adit l=7.140 11 contigency hours 26.6 contingency @10% 12 total time for activity hours 270.6 13 working hours hours 22 22 working hours ( break of 2 hours) 14 working days wd/month 25 deducting sundays and holidays 15 advance per days m/day 5 Daily excavation 16 monthl y progress excavation m/month 125 Monthly excavation=working days * advance each day
total 2
11 hours
surveyor comes in shifts one in morning
then

8.14 COST ANALYSIS FOR ADDECO-RS

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY NAME:-

RAJCODE NO:-UC5316

PROJECT TRAINING 2019-2020 ABSTRACT SHEET

Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by percussion drilling method using waggon drill or other suitable drilling equipment including cost of all materials, machinery, labour, ventilation, lighting, drainage etc., complete.

Grouting Drilling 35 mm diameter grout holes in concrete / rock by percussion drilling using jack hammer or stooper drills as directed to specified depth for consolidation / contact grouting including cost of all materials, machinery, labour, ventilation, lighting, drainage, cleaning holes, and all other ancillary operations etc., complete.

Grouting cement slurry in grout holes under specified pressure for consolidation / contact grouting including cost of all materials, machinery, labour, ventilation, lighting, drainage, redrilling wherever necessary, and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

Providing for and carrying shotcreting for 6m wide cross-passage as per specification using M35 grade of concrete including batching,

Steel rib Fabrication and Erection of 70/20/25Lattice Girder as per drawings andspecification including fabrication of accessories, welding, bolting, transportation

Providing for and fixing of wire mesh after1st and 2nd layer of shotcrete for 6m wide cross-passage including drilling,transportation etc complete,transportation, spraying etc.

Providing for and carrying shotcreting for 6m wide cross-passage as per specification using M35 grade of concrete including

TABLE 46: COST ANALYSIS ADDECO-RS METHOD

T

346.00(refer pg

item no 6.21

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 149
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91
+91
7926302470 F
7926302075
BHUMIKA
Item No Item Description Unit Qty Rate Amount
rm 54
72
schedule
Tunnel
18684 2
1
of rates
and allied works)
rm 3250
69
schedule of rates Tunnel and allied works) 1134250
349.00(refer pg
item no 6.21
M3 162.5 13120.00 (refer pg 71 item no 6.21 schedule of rates Tunnel and allied works) 2132162.5 3
transportation,
kg 63.3 213(car 3) 13483 4
M3 167 555.65 car 3) 921794 5
spraying etc
etc.
M3 167 555.65 car 3) 921794 6
transportation,
M3 167 555.65 car 3) 921794 6063962
batching,
spraying etc

METHOD

ADECCO-RS

Concept It is the method of controlled deformation

Construction phases

It is carried out on the basis of deformation response

Approach While this method deals with 3dimensional approach

Geological conditions

Hydrological conditions

equipments

NATM

It is based on the principle of controlled blasting and drilling

It is based on RMR (Rock mass classification)

It deals in 2 dimensional approach

No stabilisation is done, directly drilling or blasting is carried out. Settlement risk is less Settlement risk is higher

Ground is stabilised by using reinforcement tubular fibre glass

Dewatering is done by Drainage pipes which used before carrying out the excavation

Due to dewatering it is possible to eliminate the hydraulic pressure on the excavation face

Equipments used are a bit costly, like tunnel rig which is not traditionally used in india

labour Labour force required in this process is low but high as highly skilled labours are used

Environmental impact Low noise and vibrations encountered .

No explosives used so air quality is not detoriated and does not impact the quality of life there.

saftey Life of workers is at potential risk due to drilling and blasting

Instrumentation and monitoring

3D optical targets and strain guage are used

Time Advance of 5m /day is observed (refer pg- timecycle derived

cost It is avery expensive method but ensures safety and quality

No facility of dewatering is possible

Hydraulic pressure cannot be controlled

Equipemnsts are comparartively cheap and easily available

Labour force required in this process is quite high as highly skilled labours are used

Noise and vibrations are comparatively high

Air quality detoriates as explosives emit ammonium nitrate which is hazardous to workers and exacerbates the quality of air

Life of workers is at potential risk due to drilling and blasting

3D optical targets and strain guage are used

Advance of 1m is observed per day (refer pg- time cycle derived

Its I less expensive compared to the addecoo-rs aapproach

T

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
150
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
F +91 7926302075

8.15 PIPE JACKING

Activity : Proposing the construction of cross passage by pipe jacking method as an alternative method of construction of cross passage over the maual excavation method at grant road (UGC_02) at Mumbai Metro Line 3 with the objective to propose an alternative and comparing both with parameters such as quality , safety , time and cost.

8.16 Details of cross passage :

 Cross passage details:

cross

passage 7

 Observed activity location : total 7 cross passages from kalbadevi to grant road.,Cp 7, grant road station chainage 7510 upline . 7490 downline

 Cross passage 7 dimensions:

 Wide-3M

Length : 14m

Height: 3.149

What is pipe jacking

Pipe jacking/microtunnelling* is a non-disruptive method of installing utility tunnels and conduits by thrusting pipes through the ground as controlled excavation is undertaken at the face. Pipes manufactured in a variety of materials to include concrete, clay, grp and steel can be jacked and standard pipe diameters generally range from 150mm to 2,400mm, or greater when required.

Jacking lengths achievable can be considerably in excess of 1km depending on pipe diameters, ground conditions and excavation methods. Drive lengths are only limited by practical engineering considerations and economics and drives either in a straight line or to a radius or a series of radii are readily achievable.

Pipe jacking can deliver environmental benefits in excess of 75% as measured by reduced carbon emissions compared to disruptive open-cut construction, which requires considerably greater amounts of excavation and substantial backfill material. Long- term damage to existing installed infrastructure is alsominimised.

*Microtunnelling - originally used todescribetheconstructionoffully automated non man entry pipe jackedtunnelsinsmallerdiameters, the term is now also sometimes appliedtofullyautomated pipejacks in larger diameters which may be controlledfromaboveground

JACKING METHOD:

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
151
+91 7926302470
+91 7926302075
ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T
F

DESCRIPTION OF PIPE JACKING METHOD:

Pipe jacking/microtunnelling* is a non-disruptive method of installing utility tunnels and conduits by thrusting pipes through the ground as controlled excavation is undertaken at the face. Pipes manufactured in a variety of materials to include concrete, clay, grp and steel can be jacked and standard pipe diameters generally range from 150mm to 2,400mm, or greater when required.

1)PURPOSE:This document sets out the method statement for exacavtion, mucking and deposition in order to carry out works In a planned and systematic manner for cross passage . The aim of this document is to carry out outline the method to be deployed for construction of cross passage and its activities

2)SCOPE: Total scope is 7 cross passages in the entire UGC-02 package .To set out the construction requirements for construction of cross passage on the kalbadvei station to girgaon station stretch of MML-3 UGC-02 and maintaining safety quality and environmental compliance.

8.17 METHODOLOGY

thrust and reception pits are constructed,

A thrust ring, mounted on the jacking rig, is used to transfer the loads. The jacks are interconnected hydraulically to ensure that the thrust from each is the same

Pit sizes will vary according to the excavation methods employed,

A thrust wall is constructed to provide a reaction against which to jack.To ensure that the jacking forces are distributed around the circumference of a pipe being jacked,

A reception pit of sufficient size for removal of the jacking shield is normally required at the completed end of each drive

To maintain accuracy of alignment during pipe jacking, it is necessary to use a steerable shield, which must be frequently checked for line and level from a fixed reference

First box enters the opening at other end.

˗ Finally, jacks between the boxes are removed one by one and gap is closed successively.

˗ Joints are sealed to prevent ingress of water in the opening

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 152 Kasturbhai
380009,
+91 7926302470
+91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad –
Gujarat T
F

8.18 SCHEMATIC DIAGRAM FOR PIPE JACKING SYSTEM

CUTTER HEAD TYPE: BACKACTER SHIELD

BENTONITE SLURRY

CONCRETE PIPE

JACKING SYSTEM

Pipe jacking/microtunnelling* is a non-disruptive method of installing utility tunnels and conduits by thrusting pipes through the ground as controlled excavation is undertaken at the face. Pipes manufactured in a variety of materials to include concrete, clay,grp and steel can be jacked and standard pipe diameters generally range from 150mm to 2,400mm, or greater when required. ly in excess of 1km depending on pipe diameters, ground conditions and excavation methods. Drive lengths are only limited by practical engineering considerations and economics and drives either in astraight line or to a radius or a series of radii are readily achievable

Jacking lengths achievable can be considerable ,When PIPE is ready for pushing, pockets are cleaned and pushing pins are fixed in them followed by fixing of jacks. Thereafter, pushing is carried out in increments. Once a box is completely pushed from thrust bed, another box is placed behind it and pushing is continued along with excavation of soil.

 The process is continued until all boxes are pushed.

 First box enters the opening at other end.

 Finally, jacks between the boxes are removed one by one and gap is closed successively.

 Joints are sealed to prevent ingress of water in the opening.

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
153
+91 7926302470 F +91 7926302075
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T
FIGURE 33: PIPE JACKING METHOD CUTTER HEAD

Machinery selection criteria :

refer (Copyright © Pipe Jacking AssociationISBN 978-1-5272-0341-9)

DRY GROUND

WET GROUND

EXCAVATION METHOD

PIPELINE INTERNAL DIAMETER

(Drycohesive,drynon-cohesiveanddry mixed and fillconditions)

(Wet cohesive, wet non-cohesive and wet mixed and fill conditions)

Only applicable to stable face conditions, including rock

Only applicable to stable face conditions

Cutter boom shield

Only applicable to strong cohesive soils and soft rock -

Chemical stabilisation Suspension grouts Well points

Only applicable to stable face conditions -

Deep wells

Backacter shield

In-built method -

Additives in certain ground conditions Limited to water pressure head

Note :*So green highlighted portion shows the type of cutter head used due to the geological conditions prevailing , Mumbai metro line 3-UGC-02 encountered basalt rock which is strong and quite stable so backacter shield was best suitable on basis of that assumption

Cutter head

Open face shield in which a mechanical backacter is mounted forexcavation

Concrete pipes are aligned with the help of jacking system

FIGURE 35: CUTTER HEAD

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat

T +91 7926302470

F +91 7926302075

FIGURE 34: CONCRETE PIPE

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02
154
STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD.
FACE SUPPORT REMARKS FACE SUPPORT REMARKS Open
TBM 1200-3000
face
None
Pressurised slurry machine In-built method -
Earth pressure balance machine 1400-3000 -
Microtunnelling 150-1000 - Dependant
on type of machine -

Type of materials used for pipe

Pipesarenormallysuppliedinlengths ofbetween1.2and2.5mandfeature a joint incorporating an elastomeric gasket to provide a watertight connection.Thejointdesignincludes including capacityforjointdeflection and draw as defined in the product standard. Secondary seals may be incorporatedintothejointifrequired.

Quantity estimation

*Total length is 14 m for cross passage so concrete pipes of length 4 m each are provided along the entire length of cross passage , yellow blocks indicate the plan view of concrete pipes assembled and connected by bolting system and blue blocks indicated the space needed for the thrust bed and jacking assembly So total 3.5 pipes used

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 155 Kasturbhai
380009, Gujarat
+91 7926302470
+91 7926302075
Lalbhai Campus University Road, Navrangpura Ahmedabad –
T
F
FIGURE 36:PLAN VIEW OF CROSS PASSAGE INDICATING THE ORIENTATION OF CONCRETE PIPES TO BE INSTALLED
3.5 3 2 1
CONSTRUCTION OF CROSS PASSAGE BY PIPE JACKING
14m
Tunnels acting as space for installation of steel thrust beds Tunnels acting as space for installation of steel thrust beds

TIME CYCLE FOR ADIT3 ( CLASS 2 ROCK)

8.20 RATE ANALYSIS

TABLE 47:COST ANALYSIS FOR CROSS PASSAGE BY PIPE

total 2 shifts of 11 hours with 1 hour break each , pull of 1.15 at adit is observed

surveyor comes in shifts one in morning and then in evening.

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge. M3

Providing and erecting concrete pipe of thickness 275 mm using hydraulic jacks and bolting including transportation of pipes in the tunnel, etc. complete as per engineer in

and GC.

381(refer pg 74 DSR 20142015)

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 156
Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91
+91 7926302075
Kasturbhai
T
7926302470 F
Item Item Description Unit Qty Rate Amount 1
516
196596 2
charge
NO. 3.5 200000 700000 TOTAL 896596
sr. no FOR ADIT UNIT DETAILS DESCRIPTION 1 area m2 89.25 2 peripheral length m 12.5 3 effective pull m 1.12 4 excavation hours 88
5 survey and mapping hours 2
6 mucking hours 6 1 hours taken to remove muck everyday for 6 pulls 7 wire mesh hours 18
of wiresmesh is
round which consumes 1.5 hours so for 6 pulls 8 rockbolting hours 12 for rock bolting in one pull 2 hours are consumed so for 6 pulls 9 shotcrete hours 48
2 rounds
is
is
10 total time for activity hours 174 total time taken for adit l=7.140 11 conigency hours 17.4 contingency @10% 12 total time for activity hours 191.4 13 working hours hours 22 22 working hours ( break of 2 hours) 14 working days wd/month 25 deducting sundays and holidays 15 advance per days m/day 1.75 Daily excavation 16 monthly progress excavation m/month 43.75 Monthly excavation=working days * advance each day
two layers
laid after every excavation
in
it
done and
carried out simultaneously with excavation at every 1.15 m its done which consumes 4 hours for one pull so for 6 pulls

TECHNOLOGY FOR CROSS PASSAGE

MANUAL METHOD( PRACTISED ON SITE) PIPE JACKING( ALTERNATIVE METHOD)

Concept It is method involving excavation by excavators , in sequential manner the excavation is done and then mucking and disposal is carried out.

Primary lining and secondary lining is also carried out

Excavation by exacavtors and breaker or splitters followed by primary linings and settings

Easy checking and inspection through directly connected house connections

It is a trenchless method of pipe installation where a pipe is jacked behind cutter Machine which is shoved forward as the pipe is installed by avoiding man entry. Generally guided by a laser and most often used for the installation of gravity flow systems

Speed ofinstallation onsiderably less joints than asegmental tunnel

Easy checking and inspection through directly connected house connections

Geological conditions More risk of settlement Less risk ofsettlement

Hydrological conditions Water ingress is a major issue which has occurred on site while construction of cross passage.

equipments

Less heavy machiney is required

labour More labours are required for carrying out primary lining and secondary lining in the process

Environmental impact Due to more disposal of excavated material more vehicular motion results in more carbon emissios

saftey It is comparatively lacks behind in term of workplace safety

Time Advance of 1m /day is observed (refer pg-35 timecycle derived

cost Cost is comparatively low

Prevention of ground water ingress by use of pipes with sealed flexible joints.

Cutter head, excavators and cranes so heavy machinery is required for it.

Use of labour is reduced to quite an extent due to mechanisation and elimination of primary lining

This in turn leads to reduced vehicle movements and subsequently less associated disruption

In many cases the use of pipe jacking techniques instead of open trenching will contribute positively towards workplace safety

Advance of 25 m is observed per monthrefer pg-34 time cycle derived

Cost is comparatively high

NOTE AND COMPARISON :ADOPTED METHODOLGY VS ALTERNATIVE METHODOLOGY

T

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 157 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
+91 7926302075
F

8.21 DIAPHRAGM WALLS

This activity aims to to provide an alternative to the Secant piling method used at CST station, so the alternative adopted Diaphgram wall method which uses the concept. Diaphgram wall method is proposed for the cst station near ancillary building areas .

8.22 Method statement

REFERENCE : (Guideline for construction of d-walls, vol 2 )

Guide wall – guide wall is two parallel concrete beams constructed along the side of the wall as a guide to the clamshell which is used for the excavation of the diaphragm wall trenches.

Trench excavation – In normal soil condition excavation is done using a clamshell or grab suspended by cables to a crane. The grab can easily cut through soft ground. In case of encountering boulders, a gravity hammer (chisel) will be used to break the rock and then take the spoil out using the grab.

Excavation support – the sides inside the trench cut can collapse easily. Bentonite slurry is used to protect the sides of soil. Bentonite is a specially selected fine clay, when added to water, forms an impervious cakelike slurry with very large viscosity. The slurry will produce a great lateral pressure sufficient enough to retain the vertical soil.

Reinforcement – reinforcement is inserted in the form of a steel cage, but may be required to lap a few sections in order to reach the required length. Concreting – placing of oncrete is done using tremie pipes to avoid the segregation of concrete. As Concrete being poured down, bentonite will be displaced due to its lower density than concrete.

Bentonite is then collected and reused. Joining for the diaphragm wall panel – Diaphragm wall cannot be constructed continually for a very long section due to limitation and size of the mechanical plant. The wall is usually constructed in alternative section

Two stop end tubes will be placed at the ends of the excavated trench before concreting. The tubes are withdrawn at the same time of concreting so that a semi-circular end section is formed. Wall sections are formed alternatively leaving an intermediate section in between.

The in-between sections are built similarly afterward but without the end tube. At the end a continual diaphragm wall is constructed with the panel sections tightly joined by the semi-circular groove.

T

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT
158
ROAD.
Kasturbhai
380009, Gujarat
+91
+91
7926302470 F
7926302075
Excavation
Reinforcement Bentonite is then collected and reused
Guide wall
Trench excavation
support
Hydrofraise panel
MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 159 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 METHODOLOGY STEPWISE
IGURE 37: METHODOLOGY
D-WALLS
F
FOR

Constructing cast-in situ RCC diaphragm wall by for diaphragm wall having thickness as per approved structural design not exceeding 600 mm, in pannels of required depth and lengths as per approved drawing, including constructing necessary guide walls as required and as specified including boring in all kinds of soils and rocks, including working in or under water and / or liquid mud, in foul conditions and pumping or bailing out of water and removing slush, including disposal of earth/ rock / slush etc. for all leads and all lifts, including preparing, providing and re-circulating bentonite slurry in the trench as and when required for all depths, including agitating bentonite slurry during trenching etc., providing and fixing stop ends or form tubes, upto the required depth of diaphragm wall as engineer in charge and General consultants authority etc

providing and laying reinforcement bars of fe500 grade for DIAPHGRAM walls as per drawings including cutting ,welding tieing with binding wires ,assembling etc and providing 40 mm cover as engineer in charge and General consultants authority

Providing and laying CONCRETE OF M40 grade for diaphragm walls for specified depth inlcuding transportation, pouring, casing with tremie pipe finishing etc as per the direction of

) 937894.68

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 160 Kasturbhai
380009, Gujarat T +91 7926302470 F +91 7926302075
RATE ANALYSIS FOR DIAPHRAM WALLS Item No Item Description Unit Qty Rate Amount 1
Lalbhai Campus University Road, Navrangpura Ahmedabad –
TIMECYCLE FOR DIAPHRAGM WALLS TIMECYCLE FOR DIAPHRAGM WALLS
CUM 56.4
2014 -2015
2
etc Kg 3106.46 44.45(CAR 1) 138082.45 3
16618.70(refer pg 104 DSR
engineer incharge. Cum. 56.4 6915.453(CAR 1) 390030.25 TIME CYCLE FOR DIAPHGRAGM WALL description quantity unit Rate of production Time required for othrt activities Time for piling rig Time required for crane total 1 Survey and setting out works 1 0.50 0.50 2 Positioning of grab 1 nos 1 1 3 Boring 4 In soft rock 10 M 3 3 5 In rock 2 M 2.5 2.5 6 Shifting of rig 0.50 0.50 1 7 Placing of reinforcement cage 11 Cum 0.30 2 2.30 8 Placing of tremie 1 NO 2 2 9 Placing of concrete RCC 0.50 0.50 10 Total time required for continuous piling @ 10% contigency 8.30 5 13.30 Total piles required@20hrs/day 1.5 No of walls per day . 1 TABLE 48: TIMECYCLE FOR D-WALLS

8.23 Outcome:

In a nutshell, the main idealogy of selection of methodology was compare the adopted and alternative technology and come to a conducive analysis of the pros and cons of both the methods. At the risk of costing ,finances over time or vice versa.

Major reasons why contractors are keen in using the traditional methodology is because they have expertise over it, not all but if few methods altered can bring quite a change in quality and speed of the construction methodology.

Like if Adecco-rs has a huge advantage of stabilising and dewatering the forth soil, which reduces the water ingress and soil settlement risk to a great extent.it uses expensive machinery but work done is quite fast and also environmental friendly as no blasting is done. ( refer pg no.150.)

If pipe jacking is carried out for cross passage instead of manual method, it elimated the cost of lining processes like shotcrete , lattice girder etc which saves the cost to

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 161
METHODOLOGY ELEMENT TECHINOLOGY COST(rs) DIFFERNECE QUALITY ADOPTED ADITS AND CAVERN NATM 1260599 4803363
ALTERNATIVE ADECCO-RS 6063962 ADOPTED CROSS PASSAGE MANUAL BREAKING 872987 839707

a considerable amount as pipes used give a good finishing.

Also cross passages are used only for safety purpose so pipe jacking is quite a suitable alternative. It requires high expertise but lot of time is saved . ( refer pg no 157.)

Main reason for adopting d-walls is they are quite rigid structures and perform better than secant piles but it requires heavy machinery like Kelly grab etc so secant pile is chosen. It gives best performance in terms of safety. ( refer pg no.160)

TABLE 49: COMPARISON TABLE

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 162 ALTERNATIVE PIPE JACKING 896596
STRUCTURES
ADOPTED RETAINING
SECANT PILING 1466007 23609
ALTERNATIVE D-WALLS 2305714
*If new methodologies which are a bit costlier but inclined to give faster results are adopted the on the principle of trading time with cost should be adopted, so cash outflow can also be recovered.And it becomes very crucial to study the alternatives too for a holistic approach and better site management.

3D MODEL OF NATM WORKS AT KALBADEVI STATION

3D MODEL OF NATM WOR KS AT KALBADEVI STAT ION

Kalbadevi station has two boxes LEFT box and RIGHT box connected by a central passage.Height of -27.3m from ground level 0.00. The Upline and Downline tunnel is connected by3 adits and further one central cavern in middle which gives acces to all the adits . ( refer pg no 164 )

PROJECT HIGH TLIGHT

Kalbadevi station is a typical station out of all the stations in MMRL-3 UGC_02

Entire station below the ground is constructed through natm ,which was caused due to the land acquisition isssues so cut and cover method was not possible so the contractor had to shift to natm method.

SCOP E Adit | total 3

Two of the Adits are 6m wide and one adit is 3m wide constructed entirely by natm method of construction.

Central cavern | total 1

One central cavern of width 10 m which connects all the adits from upline tunnel to downline tunnel whose construction is carried out through natm method.

CURRENT STATUS

Adit | adit 1 and 3 are through while benching is left for adit 2.

Temporary lining works (shotcrete, rockbolting laying wiremesh etc )are carried out

Central cavern | heading of central cavern id done while benching is still left.

Temporary lining works (shotcrete, rockbolting laying wiremesh etc are carried out

ACTIVITIES OF THE E LEMENTS

LIST

• drilling

• blasting

• laying wiremesh

• shotcrete

• rockbolting

• temporary and permanent lining

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 163
MUMBAI
LINE 3 – PACKAGE 2 UGC02 STATIONS :
164
METRO
CST, KALBADEVI, GIRGAUM, GRANT ROAD.
PROJECT TRAINING 2019-2020
University Road,
Ahmedabad – 380009,
T +91 7926302470 F +91 7926302075
Bhumika Raj (UC5316) Semester-08
Kasturbhai Lalbhai Campus
Navrangpura
Gujarat
FIGURE 38: ADIT PLAN AT KALBADEVI STATION FIGURE 40: ALIGNMENT PLAN
FIGURE 41: ALIGNMENT PLAN
FIGURE 39: 3D MODEL

SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE AND ACCESS LEVEL AT KALBADEVI STATION

SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE AND ACCESS LEVEL AT KALBADEVI STATION

SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE LEVEL AT KALBADEVI STATION

SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE LEVEL AT KALBADEVI STATION

SKETCH UP MODEL FOR PLATFORM AND UNDERCROFT LEVEL AT KALBADEVI STATION

MUMBAI
LINE 3 – PACKAGE 2 UGC02 STATIONS
165
METRO
: CST, KALBADEVI, GIRGAUM, GRANT ROAD.
PROJECT TRAINING 2019-2020 Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 3D MODEL IMAGES
Bhumika Raj (UC5316) Semester-08
OBSERVED PORTION OBSERVED PORTION ULPINE TUNNEL ULPINE TUNNEL DOWNLINE TUNNEL DOWNLINE TUNNEL CST STATION END CST STATION END GIRGAON STATION START GIRGAON STATION START KALBADEVI STATION KALBADEVI STATION

Simultaneously rock bolting is carried out by drilling in the roads and adding resin capsules ad needed inside the drill holes

Simultaneously rock bolting is carried out by drilling in the roads and adding resin capsules ad needed inside the drill holes

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 166
PROJECT TRAINING 2019-2020
T
F +91
Bhumika Raj (UC5316) Semester-08
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat
+91 7926302470
7926302075
Kalbadevi station Kalbadevi station Drilling into the segment face Drilling into the segment face Removal of segments Removal of segments Drilling into the adit after removal of segments and shot crete done through pneumatic shotcrete machine. Drilling into the adit after removal of segments and shot crete done through pneumatic shotcrete machine. Adit is made through from downline tunnel to upline tunnel. Adit is made through from downline tunnel to upline tunnel.

Adit is made through from downline tunnel to upline tunnel, after that central cavern works are carried out

Adit is made through from downline tunnel to upline tunnel, after that central cavern works are carried out

Drilling is carried for heading part in the central vaern area

Heading and bemching is carried out by using explosives and detonators

Heading and bemching is carried out by using explosives and detonators

Blasting is done by using tnt detonators placed on the working platform , tnt is pressed and blasting is carried out inside the cavern

Blasting is done by using tnt detonators placed on the working platform , tnt is pressed and blasting is carried out inside the cavern

Blast done at the cavern heading portion

Blast done at the cavern heading portion

After blasting works is over defuming is carried out and other preliminary works are like shotcrete , wiremesh and rock bolting is carried out in the cavern works

After blasting works is over defuming is carried out and other preliminary works are like shotcrete , wiremesh and rock bolting is carried out in the cavern works

MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 167
PROJECT TRAINING
Bhumika Raj (UC5316) Semester-08
2019-2020
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075

3D VIEW SHOWING ONE ADIT THROUGH THE CENTRAL CAVERN

https://youtu.be/ob5pYj-qAdA

https://www.youtube.com/watch?v=L a1JaGLr5t8

https://youtu.be/-CY5BYcBdWU

MUMBAI
LINE 3 – PACKAGE 2 UGC02 STATIONS : CST,
168
METRO
KALBADEVI, GIRGAUM, GRANT ROAD.
PROJECT
T
Bhumika Raj (UC5316) Semester-08 F
TRAINING
2019-2020
Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat +91 7926302470
+91 7926302075
AFTER THE BLASTING WORKS IN THE CAVERN AREA , PRIMARY SUPPORTING WORKS ARE CARRIED OUT SIMULTANEOUSLY LIKE SHOTCRETE , ROCK BOLTING AND LAYING WIREMESH
3d view showing One adit through the central cavern 3D VIEW OF CENTRAL CAVERN THROUGH ALL THE ADITS AT THE KALBADEVI STATION 3d view of central cavern through all the adits at the kalbadevi station Video link

So I would say that from my learnings and outcomes at Mumbai Metro Line 3 –UGC02 , Construction industry has many aspects. There are few parameters which play a crucial role are often less visible and taken into consideration one of them is lack of innovation In construction industry. Building information should be given a priority as on my site experience though there were BIM midels created there was no real time monitoring nor the model was accessible to the engineers. Only the BIM specialist could access to it, which creates problem in work flow.

Observations and Learnings

Target Value Design: This is to set the target value less than market value so if the contractor keeps the track of the graph and observes the cash flow seems to go above the market value they can work out possibilities and lower the graph .So contractor can save the money and use it for other capital investments

Better Interoperobaility :By doing the real time coordinaton with building information model the contractor can reduce rework which can save resources to an extent. As BIM can also perform 4-D( real time monitoring with time ) 5-D ( real time monitoring with cost ) and even 6-D, it can really help in reducing the time, also all the information is available on one screen which can help in using time more efficiently.Also clash detection helps in reducing reworks as changes can be made on screen if errors detected and not on field, this saves the machinery and manpower to a great extent.

As per my observation the BIM Models were generated but there was no real time monitoring Also the models were not easily accessible to the engineers.so this depicts that though innovative models are used there is no proper work flow or accessibility to them.As without a BIM specialist it was not possible for the people on field to operate them.

Inference :The dashboard shows the cash flow fluctuating between market value and target value .This shows that the target value should be set lower than the market value of the project. The contactor should keep a track of the cash flow and if the graph seems to exceed the market value the contractor can work out measures and keep the graph within the limit.The contractor can do the savings in this way and invest more efficiently.

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 169 9 Summary
0 0.1 0.2 0.3 0.4 0.5
TARGET VALUE
TARGET VALUE DESIGN
SAVING S MARKET VALUE

BLIND SPOT

Visible Parameters

OVERRUNS AND TIME LOSS DEFECTS

LATE APPROVALS BY AUTHORITIES

Less visible Parameters

POOR PLANNING , POOR FEASABILITY STUDY AND LACK IN REAL TIME COORDINATION

LABOUR STRIKES / NATURAL DISASTER(COVID 19) AND OTHERS

BUILDING INFORMATION PROJECT IS LESS PROMINENT WHICH IS LESS INNOVATIVE TECHNIQUES USED .

POOR TARINING PROGRAMS CONDUCTED

Also overall one of the most overlooked thing is not identifying the root causes for the lags and focussing only on the most visible parameter of the delay.if the root causes of the problem is addressed it will ease the impediments and create a better work flow for the professionals .

Example : In Mumbai Metro line 3 UGC-02 one of the most highlighted delay was the delay due to Parsi fire temple issue, it had created headlines for almost a year and the committee had to go through various legal proceedings.(refer pg 130: project delay task) . According to the feasibility study carried out before the project nobody from the parsi community had raised any objection. It was only after the constructed started.so if the loophole in the feasibility study would be discovered earlier about 8 months of the time could be saved.

So if in near future few of the parameters mentioned above are brought into practice the metro construction in india can really progress. Making connectivity strong is one of thr key aspects for a developing country like India,though there is a lot of capital investments and soft loan taken for such projects but there is no doubt that if the construction industry adopts innovation and addresses the root causes a lot can change.

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 170
REWORK

CONCLUSION “CONNECTING THE UNCONNECTED “

If I had to sum up my experience I would say Over all it was an amazing experienced at site to witness all the construction activities visiting tunnels and learning new technologies. On site experience plays a major role in understanding a project. This project training pretty much sufficed that parameters for me. Also the geographical location plays a major role in construction of a project and in a congested area like South Mumbai called SOBO” where logistics is an issue and also the home of majority heritage structures there was a lot to learn.

It was only after commuting in local trains I realised that why there is a need of Metro in the city, the local trains carry 6 times the passengers then their design capacity.After the construction of metro there would be a great difference in travelling experience of the people residing in the city.

After this training I am able to interpret things more technically and have evolved my understanding about how the infrastructure projects function. 3 months experience also gave me a broader perspective on every aspect of construction, whether it was execution , planning , BIM or management. Project training is the foundation for a better future and its very important to work with organised firms, and I am grateful for the opportunity I received to work with HCC. Also doing the internship from client side I gained a lot of knowledge from MMRC staff,as I got an holistic understanding of how work gets done in the organisation.

I would conclude by saying the opportunity I got changed my approach towards construction industry .I would like to apply all the learning in my professional career in future with utmost diligence .

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 171

REFERENCES:

 Monthly project report ( document)

 Study of msp schedule

 Contracts book

 Online articles

 Accelerated program report

 Method statements.

 International Journal of Current Research Vol. 6, Issue, 06, pp.7219-7222, June, 2014

 Delay analysis and its effects in construction industry Ram B. Tosniwal1, Prof. Shashank U.

International Journal of Students’ Research in Technology & Management eissn: 2321-2543, Vol 6, No 1, 2018, pp 30-39 https://doi.org/10.18510/ijsrtm.2018.615

 Delays in construction projects: a review Of causes, need and scope for further Research Prasad Kudrekodlu Venkatesh and Vasugi Venkatesan,School of Mechanical & Building Sciences, VIT University, Chennai, India, 600127

 Guideline for construction of d-walls, vol 2

 Copyright © Pipe Jacking AssociationISBN 978-1-5272-0341-9)

 Comparison of natm and adeco-rs methods,Using monte cuneo tunnel, italy, as an example Peter balušík, libor MAŘÍK

 Mmrcl official website.

Kasturbhai Lalbhai Campus University Road, Navrangpura Ahmedabad – 380009, Gujarat T +91 7926302470 F +91 7926302075 MUMBAI METRO LINE 3 – PACKAGE 2 UGC02 STATIONS : CST, KALBADEVI, GIRGAUM, GRANT ROAD. 172

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.