Streamlined Supply Chain: Maximized Results
Micki M. Maynard Project Manager & Lead Print Buyer Legrand, North America
Micki M. Maynard
Started out in publishing in 1978 Specialty – Large Project Management McGraw-Hill – Established an In-House Publishing Group Capital Cities/ABC – Transitioned from traditional typesetting/mechanicals to desktop publishing
Wiremold - Established an In-House Publishing Group; Became World Class Kaizen & Lean Thinking Leaders
Legrand Limoges, France – Acquired Wiremold in 2000
How Would You Go About Adding $338,000 to your print budget?
The Challenge: Legrand Global Purchasing Mandate to Achieve Print Savings Legrand, North America (LNA) comprised of seven independent companies Seven long-standing vendor relationships Seven unique purchasing practices (No longer quoting, except on very large projects)
No LNA-wide standards on job tracking, spec collection, quarterly reporting No LNA lead buyer No volume discounts on 2007’s $3 million spend
The Scope
Determine needs - web & sheet printing Investigate standardized stock options Investigate Print-on-Demand (POD) options Develop tracking/reporting processes Construct/negotiate contracts Implement across all of LNA
The Support
France – Global Purchasing Management North America – Executive Management Individual LNA Entity MarComm Management Individual LNA Entity Delegates LNA Purchasing Champion Total Team of 8 committed members
The Timeline
Project Challenge Accepted March 2008 Implementation of New Program October 2008 Program Fully Operational January 2009
Milestones
Vendor Selection / Data Collection
Each LNA entity ranked & submitted the vendors they wanted team to consider Total of 16 vendors were considered Sheet & Web Each entity collected 2007 spend / spec details Catalogs Sheet Projects
Critical Tools
Request for Information - RFI Key Performance Indicators - KPI Project Tracker Request for Proposal – RFP / Master Spec Decision Matrices
Needs Assessment - RFI
Request for Information (RFI) developed Overview of Project Ability to provide all printer services needed Analyze needs of all 7 companies Recommend actionable improvements Drive productivity improvements in print processes Assist LNA with Green initiatives Experience w/similar multi-company structures preferred
Needs Assessment – KPI (aka CTQ – Critical to Quality)
Key Performance Indicators (KPI) developed Short List – Qualifying Questions (Y/N) Vendor Qualifications Company History; Performance Metrics; Actual Performance Data; Experience; Add’l Terms & Conditions Scope of Work Requirements; Assumptions; Risk Assessment; Differentiators; Proposed Tools; Subcontractor Relationships Estimated Implementation Steps & Timeline
Tools – Project Tracker
Microsoft Excel File Used to track: Meeting attendance Project steps/status Sent out to team each week with next week’s agenda & previous meeting’s minutes Submitted as monthly update to LNA management team
Copyright 2008 – Legrand – All Rights Reserved
Master Spec
Included Details from all 7 Companies Separate Web & Sheet Specs Team Agreed on Classification / Project Names Catalogs; Pricebooks; Brochures; Cutsheets; Sell Sheets; Installation Instructions; Spec Sheets; Stationery Elements; Specialty Items (Counter Mats, Wall Charts, etc.) Did NOT include packaging in this review
All 7 Companies Printed Item
Spec List
Spec Details, by Company
Narrowing the Field
Initial RFI / KPI – results analyzed by team Resulted in elimination of 10 of the 16 vendors 16-page RFP & Master Spec was sent out to 2 Web printers & 4 Sheet printers References checked WebEx - Vendors ask specific clarifiying questions on the RFP Two week deadline – Completed RFPs & printed samples submitted
Tools - Decision Matrix
Used by each team member to rank vendors from 1-10 in 9 key areas – no ties allowed Catalog Printing Sheet Printing POD Model Digital Workflow Process Customer Service Sustainability Reporting Disaster Recovery Plan Partnering for the Future
Paper Sub-Buy
During the evaluation process, we decided to manage our own paper buy Printer quotes we requested were for production only, no paper Negotiated a separate paper contract for additional savings
Final Factors
Vendor presentations on-site to our team Site visits to vendors by our team Review onsite scores Final Decision Made Contract Negotiations with Finalists Contracts Signed Exit Letters Sent to Incumbent Partners Implementation
First Year
Implementation Plan – Q4 of 2008 and Q1 of 2009 Quarterly Program Reviews with CGX, Paper Vendor, LNA Purchasing & LNA Lead Buyer Daily Report Developed for Each LNA Entity by CGX (includes Paper) Quarterly Report of all 7 companies sent to top management Weekly Update Conference Calls Established (include CGX, Agency, Designers, Fulfillment House, LNA Lead Buyer)
Daily Report
Daily Report
Lessons Learned
Critical Factors in the success of a project of this magnitude Open Minds Consensus of Core Team Agreement by each Entity’s Upper Management Establish Regular Communication Sessions Establish Reporting Processes Establish Exception Rules / Approval Process Open Communication throughout the process
Tangible Project Results
Goals set were based on the 2009 spend On a Spend of $1,500,000
Savings achieved: $338,000
Critical Results of this Initiative:
Seven independent companies now working together as Legrand One master vendor relationship with local options Documented Purchasing SOPs with contracts LNA SOPs - job tracking, spec collection, quarterly reporting LNA lead buyer Volume discounts = achieved savings Regular communications sharing best practices between Legrand, North America and Legrand Global Paved the way for integrated, consistent branding across LNA
The End‌