Texas A&M University Agriculture Headquarters Weekly Report: 7/20/09-7/24/09

Aerial Photo

North Elevation

Sanitary Sewer Installed

Domestic Water Line Installed

Pile Cap Form/Reinforcing

Temporary Construction Road

50% complete with auger cast piles on the Headquarters Building

Formed/Reinforced and Poured 12 pile caps on the HQ building

Tying pier cages for the visitors center with drilling to commence Monday 7/27.

Fire hydrants installed

Hydro tested and chlorinated the water loop for the site

Continuing site grading around building

Storm sewer installation ongoing at 55% complete onsite

Sanitary sewer installation ongoing at 90% for underground

Temporary construction road being installed around site

Saw cut approaches that will be demoed

Fire hydrants installed