Texas A&M University Agriculture Headquarters Weekly Report: 7/20/09-7/24/09
Aerial Photo
North Elevation
Sanitary Sewer Installed
Domestic Water Line Installed
Pile Cap Form/Reinforcing
Temporary Construction Road
•
50% complete with auger cast piles on the Headquarters Building
•
Formed/Reinforced and Poured 12 pile caps on the HQ building
•
Tying pier cages for the visitors center with drilling to commence Monday 7/27.
•
Fire hydrants installed
•
Hydro tested and chlorinated the water loop for the site
•
Continuing site grading around building
•
Storm sewer installation ongoing at 55% complete onsite
•
Sanitary sewer installation ongoing at 90% for underground
•
Temporary construction road being installed around site
•
Saw cut approaches that will be demoed
•
Fire hydrants installed