Texas A&M University Agriculture Headquarters Weekly Report: 7/5/10-7/9/10

North View of HQ

Furdowns in Classrooms

Northwest View of VC

Stone @ VC Columns

Continue to implement the site logistics revision to accommodate for the Admin building.

Installing lintel covers at window heads on the southeast corner of the HQ.

Installed the curtainwall at the northeast entrance to the HQ.

Framing furdowns throughout the HQ.

50% complete with installing stone on the north exterior VC columns.

Elevator installation is ongoing.

Damproofing the VC exterior wall is 30% complete.

Installation of window frames at the VC is about 90% complete.

Framing of furdowns in the exhibit area is about 85% complete.

Cistern Canopy will be erected next week.