Texas A&M University Agriculture Headquarters Weekly Report: 7/5/10-7/9/10
North View of HQ
Furdowns in Classrooms
Northwest View of VC
Stone @ VC Columns
•
Continue to implement the site logistics revision to accommodate for the Admin building.
•
Installing lintel covers at window heads on the southeast corner of the HQ.
•
Installed the curtainwall at the northeast entrance to the HQ.
•
Framing furdowns throughout the HQ.
•
50% complete with installing stone on the north exterior VC columns.
•
Elevator installation is ongoing.
•
Damproofing the VC exterior wall is 30% complete.
•
Installation of window frames at the VC is about 90% complete.
•
Framing of furdowns in the exhibit area is about 85% complete.
•
Cistern Canopy will be erected next week.