North View of HQ
MEP Rough-In in Exhibit Area
North View of VC
Scaffold at VC Exterior Columns
Elevator Shaft at VC
Glass in Exterior Windows
•
Erect scaffolding at exterior columns at VC.
•
Damproofing the exterior of the HQ is 95% complete.
•
Installing stone at the main entrance to the HQ 80% complete.
•
MEP rough-in in the exhibit areas of the VC is ongoing.
•
Metal panel installation at the eyebrow is complete on the south side and 65% complete on the remainder of the HQ.
•
Caulking windows and installing trim caps on the southeast side of the HQ.
•
Installing vanity supports at the toilet rooms.
•
Started damproofing the exterior walls on the VC
•
Framing and sheathing exterior walls at the VC is 90% complete.
•
Continue to one side walls throughout the HQ.