Texas A&M University Agriculture Headquarters W e e k l y R e p o r t : 6 / 7 1 0 - 6 / 11 / 1 0
North View of HQ
MEP Rough-In in Exhibit Area
Main Entrance at HQ
Scaffold at VC Exterior Columns
Vanity Supports
Gates & Louvers for Service Yard
•
Completed MEP above ceiling rough-in on the east side of the 5th floor.
•
Tying in outside duct to the ERU’s.
•
Installation of stone at the main entrance to the HQ is 95% complete.
•
MEP rough-in in the exhibit areas of the VC is ongoing.
•
Started the installation of the standing seam roof at the eyebrow.
•
Caulking windows and installing trim caps on the southeast side of the HQ is 100% complete.
•
Continue to fire caulk the expansion joints on 1st thru 5th floors at the HQ.
•
Currently framing toilet room ceiling on the 1st floor.
•
Framing and sheathing exterior walls at the VC is 100% complete.
•
Continue to one side walls on the 3rd, 4th, and 5th floors of the HQ and frame interior partitions in the VC.