Texas A&M University Agriculture Headquarters Weekly Report: 9/21/09-9/25/09
Shoring for 2nd Floor Deck @ HQ
North View
Carton Forms at HQ
Luffing Crane
View @ Northeast Corner of HQ
Shoring for Elevated Decks
•
Site work was very minimal throughout the week because of all the rain.
•
Electrical rough-in at the service yard is ongoing.
•
Had 2.40” of rain this week.
•
Tuesday 9.22.09 was considered a rain day.
•
Installing carton forms on the west side of the crawl space at the HQ.
•
Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing.
•
50% complete on the cisterns miscellaneous drain lines (6”-12”) to building.
•
The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck.
•
Stopped backfill at the crawlspace walls at the VC because of rain.
•
Started grade beams at VC.
•
Storm lines to underground tank ongoing.