2009-09-25

Page 1

Texas A&M University Agriculture Headquarters Weekly Report: 9/21/09-9/25/09

Shoring for 2nd Floor Deck @ HQ

North View

Carton Forms at HQ

Luffing Crane

View @ Northeast Corner of HQ

Shoring for Elevated Decks

Site work was very minimal throughout the week because of all the rain.

Electrical rough-in at the service yard is ongoing.

Had 2.40” of rain this week.

Tuesday 9.22.09 was considered a rain day.

Installing carton forms on the west side of the crawl space at the HQ.

Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing.

50% complete on the cisterns miscellaneous drain lines (6”-12”) to building.

The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck.

Stopped backfill at the crawlspace walls at the VC because of rain.

Started grade beams at VC.

Storm lines to underground tank ongoing.