Texas A&M University Agriculture Headquarters Weekly Report: 12/21/09-12/25/09
North View
Stairs @ West End of HQ
Service Yard
Interior Partition Framing
Columns at VC
Reinforcing on 2nd Deck @ VC
•
Placed the 2nd roof deck at the VC on Wednesday 12.23.09.
•
Continue the electrical rough-in in the slab at the service yard.
•
Installing frames, forms, MEP rough-in, reinforcing, and PT cables for the penthouse roof.
•
Replacing East approach at parking lot 97.
•
Installing stair 1 & 2 at the HQ.
•
Installing misc steel at windows and exterior skin at the HQ.
•
Framing classroom risers.
•
Columns at the VC first floor are ongoing.
•
Excavated hoist foundation.
•
Finished installing masonry and stone on the mock up.
•
The jobsite is closed Thursday thru Sunday for the Christmas Holidays.