Texas A&M University Agriculture Headquarters Weekly Report: 12/21/09-12/25/09

North View

Stairs @ West End of HQ

Service Yard

Interior Partition Framing

Columns at VC

Reinforcing on 2nd Deck @ VC

Placed the 2nd roof deck at the VC on Wednesday 12.23.09.

Continue the electrical rough-in in the slab at the service yard.

Installing frames, forms, MEP rough-in, reinforcing, and PT cables for the penthouse roof.

Replacing East approach at parking lot 97.

Installing stair 1 & 2 at the HQ.

Installing misc steel at windows and exterior skin at the HQ.

Framing classroom risers.

Columns at the VC first floor are ongoing.

Excavated hoist foundation.

Finished installing masonry and stone on the mock up.

The jobsite is closed Thursday thru Sunday for the Christmas Holidays.