Texas A&M University Agriculture Headquarters Weekly Report: 12/28/09-1/1/10
North View of HQ
Overview of VC
Equipment Yard
Interior Partition Framing
2nd Floor at VC
Roof Drains on Penthouse Roof
•
Penthouse roof deck was placed on 12.30.09.
•
Poured the equipment yard foundation on 12.30.09.
•
Completed all the 2nd floor column at the VC.
•
Poured the east approach at parking lot 97 on 12.31.09.
•
Place concrete pans @ stair 1 on 12.31.09.
•
Installing misc steel at windows and exterior skin at the HQ.
•
Installing the 37ft columns at the VC first floor are ongoing.
•
Ran conduits to hoist location.
•
Excavation for the cistern tank will begin the first week of January.
•
The jobsite is closed Friday through Sunday for the New Year Holiday.