Texas A&M University Agriculture Headquarters Weekly Report: 1/4/10-1/8/10

North View of HQ

Mock-up

Buck hoist Delivery

North View of VC

Installing roof drains at the HQ is ongoing.

Installation of stair two is complete through the fourth floor.

Tie-backs are installed on the HQ roof.

Poured sidewalks at parking lot 97 approach on 1.6.10.

The material buck hoist was delivered to the site on 1.6.10.

Installing misc steel at windows and exterior skin at the HQ.

Installing the 37ft columns at the VC first floor are ongoing.

Framed, formed, and reinforced the low roof at the VC.

Excavation for the cistern tank will begin on Monday 1.11.10.

The low roof at the VC will be placed next week.

Southeast View

Columns at the VC