Texas A&M University Agriculture Headquarters W e e k l y R e p o r t : 1 / 11 / 1 0 - 1 / 1 5 / 1 0
North View of HQ
West View of VC
Cistern Tank Delivery
Setting ERU on HQ Roof
Buck Hoist
Sheetrock on 1st Floor HQ
•
Installed the 40,000 gallon cistern tank on Wednesday 1/13/10.
•
Set the Energy Recovery Units on the roof on 1/12/10.
•
Completed stair 1 at the HQ.
•
Placed the low roof at the VC on Tuesday 1/12/10.
•
The installation of the west and east buck hoist is about 90% complete.
•
Started framing and forming for the upper roof at the VC.
•
Pouring the 37ft columns at the VC is ongoing.
•
Started hanging the steel for stair 3 at the east end of the HQ.
•
All the Air Handling Units will be delivered and placed on the HQ by the end of next week.
•
Formed and poured the south entry stoop at the HQ
•
Will place concrete pans at stair 2 beginning next week.
•
Started putting sheetrock on interior partitions.
•
MEP above ceiling rough-in is continuing up the building with the 1st floor nearly complete.