Texas A&M University Agriculture Headquarters Weekly Report: 1/25/10-1/29/10

North Aerial of HQ

North Crane Road

Setting AHU in the HQ

Above Ceiling Duct

Elevator Shaft

The luffing crane was demobilized and hauled of site on 1/27/10.

The Air Handling Units were set in the HQ.

Poured pans at stair 3 on Monday 1/25/10.

All 3 sets of stairs and the buck hoists are open and operational at the HQ.

Curbs at the penthouse were placed on 1/25/10.

The upper roof at the VC was placed on 1/27/10.

Installation of the stair going from floor 1 to 2 at the VC has started .

The high scaffolding at the VC will be removed next week.

Started exterior framing on the HQ 1st floor.

The lintel angel installation on the HQ is ongoing.

Installing the CMU parapet on the Penthouse Roof.

Cable Tray