Texas A&M University Agriculture Headquarters Weekly Report: 3/8/10-3/12/10
South View of HQ
Classroom Risers
Service Yard
Window Frames
HQ Main Roof
HQ East Elevation Eyebrow
•
CMU block installation for the service yard in 100% complete.
•
Installing the main roof on the HQ.
•
Continue to frame and sheath the south exterior wall of the HQ.
•
Start damproofing the 1st floor windows on the south elevation of the HQ.
•
Installing the eyebrow on the east elevation of the HQ.
•
Penthouse roof completed.
•
Damproofing the parapet walls on the HQ.
•
Framing and lining the elevator shaft walls are complete through the 4th floor.
•
Installing fan power boxes on the 2nd floor.
•
Damproofing penthouse exterior walls are complete.
•
Installing support curbs at the exterior columns at the HQ.
•
Start installing window frames next week.