Texas A&M University Agriculture Headquarters Weekly Report: 4/12/10-4/16/10

North View of HQ

Exterior Limestone

Insulated Duct Work

Fan Power Box Connections

Limestone Block @ Quarry

Sprinkler Piping at the VC

Exterior Limestone block installation is ongoing on the South elevation.

Damproofing is 100% complete on the south side of the HQ.

Window frames are 90% installed on the south side.

The north west exterior of the HQ is completely framed and sheathed.

Exterior framing is continuing east along the north side of the HQ.

Steel framing for the eyebrow at the HQ is 80% complete..

VC steel columns and beams for the curtain wall support are being welded out.

Above ceiling MEP rough-in at the VC is ongoing..

Sheathing of the eyebrow is 100% complete on the south and west side of the HQ.

VC roof is 75% complete.