Texas A&M University Agriculture Headquarters Weekly Report: 4/12/10-4/16/10
North View of HQ
Exterior Limestone
Insulated Duct Work
Fan Power Box Connections
Limestone Block @ Quarry
Sprinkler Piping at the VC
•
Exterior Limestone block installation is ongoing on the South elevation.
•
Damproofing is 100% complete on the south side of the HQ.
•
Window frames are 90% installed on the south side.
•
The north west exterior of the HQ is completely framed and sheathed.
•
Exterior framing is continuing east along the north side of the HQ.
•
Steel framing for the eyebrow at the HQ is 80% complete..
•
VC steel columns and beams for the curtain wall support are being welded out.
•
Above ceiling MEP rough-in at the VC is ongoing..
•
Sheathing of the eyebrow is 100% complete on the south and west side of the HQ.
•
VC roof is 75% complete.