Texas A&M University Agriculture Headquarters Weekly Report: 4/19/10-4/23/10

South View of HQ

VC High Roof

Glass Installed in Windows

Metal Panels at Penthouse

Hot and Chilled Water Line Flush

Bus Duct

Exterior framing is 80% complete on the north side of the HQ.

50% of the north side of the HQ is damproofed.

Window frames are installed on the south side of the HQ with the north side window frame installation ongoing.

The eyebrow framing on the HQ is 95% installed.

Installing metal panel at the penthouse.

VC high roof is installed.

MEP above ceiling rough-in is ongoing at the VC.

Hot and chilled water lines are being flushed.

Installing limestone on the southwest side of the HQ.

MEP above ceiling rough-in at the HQ is complete through the 4th floor.

Glass is being installed on the south side of the HQ.