Texas A&M University Agriculture Headquarters Weekly Report: 4/19/10-4/23/10
South View of HQ
VC High Roof
Glass Installed in Windows
Metal Panels at Penthouse
Hot and Chilled Water Line Flush
Bus Duct
•
Exterior framing is 80% complete on the north side of the HQ.
•
50% of the north side of the HQ is damproofed.
•
Window frames are installed on the south side of the HQ with the north side window frame installation ongoing.
•
The eyebrow framing on the HQ is 95% installed.
•
Installing metal panel at the penthouse.
•
VC high roof is installed.
•
MEP above ceiling rough-in is ongoing at the VC.
•
Hot and chilled water lines are being flushed.
•
Installing limestone on the southwest side of the HQ.
•
MEP above ceiling rough-in at the HQ is complete through the 4th floor.
•
Glass is being installed on the south side of the HQ.