Texas A&M University Agriculture Headquarters Weekly Report: 4/26/10-4/30/10

North View of HQ

VC Above Ceiling Rough-In

Southeast View of HQ

Curtain Wall Framing at HQ

Metal Wall Panel

Service Yard

Exterior framing is 90% complete on the HQ.

Damproofing the north side of the HQ is ongoing.

Stone is being installed on the west side of the HQ.

Window frame installation has started on the north side of the HQ.

The eyebrow framing on the HQ is 95% installed.

Metal panel installation is complete on 3 sides of the penthouse.

VC low roof installation is ongoing.

MEP above ceiling rough-in is ongoing at the VC.

Hot and chilled water line flush is complete.

Brick installation on the southeast side of the HQ in 85% complete.

Curtain wall framing at the front entrance to the HQ is installed.

Glass is being installed on the south side of the HQ.