North View of HQ

First Floor Restroom Rough-In’s

Southwest View of HQ

Framing Full Height Partition at VC

Metal Wall Panel at Penthouse

Exterior Brick Veneer

Window frame installation is ongoing along the HQ north side.

Damproofing the northwest side of the HQ is complete.

Stone is being installed on the west side of the HQ.

Glass is being hung on the north side 1st and 2nd floors of the HQ.

Metal panels are completely installed at the penthouse.

VC low roof installation is complete.

MEP above ceiling rough-in is ongoing at the VC.

Brick installation on the southeast side of the HQ is complete with the southwest side starting.

Eyebrow framing at the HQ is complete with sheathing of the eyebrow at 85% complete.

Starting the installation of metals panels on the exterior of the HQ.