Texas A&M University Agriculture Headquarters Weekly Report: 5/10/10-5/14/10

Southeast View of HQ

North View of HQ

Window Framing at 5th Floor

One Siding Walls in HQ

West Curtain Wall Framing @ Stairs

Gutter Extension Support

Safety Cook-out held today for all workers along with a raffle give-a-way.

The installation of main feeders to the switch gears are nearly complete.

Metal panel installation on the southeast side of the HQ is ongoing.

Scaffold is being erected at the main entrance of the HQ.

Sheathing of the eyebrow is 100% complete.

Damproofing and window frame installation is ongoing along the north side of the HQ..

Started hanging sheetrock on all partitions to deck on the first floor..

MEP above ceiling rough-in is ongoing at the VC.

Started installing the misc steel supports for the Herculite doors.

Layout of radius furdowns and diffusers in the VC has started.

The curtain wall steel supports at the VC will be painted next week.