Texas A&M University Agriculture Headquarters Weekly Report: 5/24/10-5/28/10
North View of VC
Louver at the Penthouse
North View of HQ
High Area of VC
Installing Main Entrance Stone
Stone on Exterior VC Columns
•
Installing thermal line to the Administration Building
•
Metal panel installation at the south and north sides of the HQ is 70% complete.
•
Installing stone at the main entrance to the HQ 60% complete.
•
Double siding wall on 1st floor and one siding walls on floors 2-5.
•
Installing exterior framing at the VC..
•
Removed the west buck hoist on Thursday 5/27/10.
•
Laid the first stone at the exterior columns on the VC.
•
Damproofing the exterior of the HQ is 90% complete.
•
Stone/brick is 65% installed on the exterior of the HQ.
•
Window frame installation is 90% complete on the HQ.
•
Louvers and gates will be installed on the service yard next week..