Texas A&M University Agriculture Headquarters Weekly Report: 5/24/10-5/28/10

North View of VC

Louver at the Penthouse

North View of HQ

High Area of VC

Installing Main Entrance Stone

Stone on Exterior VC Columns

Installing thermal line to the Administration Building

Metal panel installation at the south and north sides of the HQ is 70% complete.

Installing stone at the main entrance to the HQ 60% complete.

Double siding wall on 1st floor and one siding walls on floors 2-5.

Installing exterior framing at the VC..

Removed the west buck hoist on Thursday 5/27/10.

Laid the first stone at the exterior columns on the VC.

Damproofing the exterior of the HQ is 90% complete.

Stone/brick is 65% installed on the exterior of the HQ.

Window frame installation is 90% complete on the HQ.

Louvers and gates will be installed on the service yard next week..