Texas A&M University Agriculture Headquarters Weekly Report: 8/17/09-8/21/09

Columns to 2nd Floor

North View

First Column to Level 2

Waterproofing at Crawlspace

Mudslab in Crawlspace

Electrical Ductbank

All piers and piles are completed

HQ building crawlspace walls complete

Mudslab complete in HQ crawlspace

Demobilized 100 ton crane and auger

Pile caps for the HQ building are complete

Cistern Canopy pile caps completed

10 Columns poured for level 2 support on the HQ building

Approaches from John Kimbrough are ongoing

Primary electrical duct bank installation ongoing (90% complete)

Storm line and equalization line from cistern pile caps 90% complete for tie into storm line

Began installing storm sewer headwalls