Texas A&M University Agriculture Headquarters Weekly Report: 8/17/09-8/21/09
Columns to 2nd Floor
North View
First Column to Level 2
Waterproofing at Crawlspace
Mudslab in Crawlspace
Electrical Ductbank
•
All piers and piles are completed
•
HQ building crawlspace walls complete
•
Mudslab complete in HQ crawlspace
•
Demobilized 100 ton crane and auger
•
Pile caps for the HQ building are complete
•
Cistern Canopy pile caps completed
•
10 Columns poured for level 2 support on the HQ building
•
Approaches from John Kimbrough are ongoing
•
Primary electrical duct bank installation ongoing (90% complete)
•
Storm line and equalization line from cistern pile caps 90% complete for tie into storm line
•
Began installing storm sewer headwalls