Texas A&M University Agriculture Headquarters Weekly Report: 8/24/09-8/28/09

Columns for Level 2 Support at HQ

North View

Grade Beam for HQ

Columns for Level 2 Support at HQ

First Floor Deck Over Crawlspace

Electrical Ductbank

15 Columns poured for level 2 support on the HQ building

Approaches off John Kimbrough is ongoing

Primary electrical duct bank installation complete

Site cuts and fills are still ongoing

Electrical secondary to building has begun

Setup first floor deck at crawl space to be poured next Tuesday

MEP rough-in at first floor crawlspace is complete

Backfill at crawlspace walls is 90% complete.

Completed forming and pouring all walls at the crawlspace at the Visitors Center

Installed all sleeves for wall penetrations at Visitors Center

Forming and pouring grade beams is ongoing

Detention pond structure is 60% complete