Texas A&M University Agriculture Headquarters Weekly Report: 8/24/09-8/28/09
Columns for Level 2 Support at HQ
North View
Grade Beam for HQ
Columns for Level 2 Support at HQ
First Floor Deck Over Crawlspace
Electrical Ductbank
•
15 Columns poured for level 2 support on the HQ building
•
Approaches off John Kimbrough is ongoing
•
Primary electrical duct bank installation complete
•
Site cuts and fills are still ongoing
•
Electrical secondary to building has begun
•
Setup first floor deck at crawl space to be poured next Tuesday
•
MEP rough-in at first floor crawlspace is complete
•
Backfill at crawlspace walls is 90% complete.
•
Completed forming and pouring all walls at the crawlspace at the Visitors Center
•
Installed all sleeves for wall penetrations at Visitors Center
•
Forming and pouring grade beams is ongoing
•
Detention pond structure is 60% complete