Texas A&M University Agriculture Headquarters Weekly Report: 8/31/09-9/4/09

Columns for Level 2 Support at HQ

North View

Sidewalk Superintendent

Crawlspace at Visitors Center

First Floor Deck Over Crawlspace

Electrical Secondary

First floor columns are 65% complete on the HQ building

Approaches off John Kimbrough are ongoing

Site cuts and fills at building areas are ongoing following site utilities

Electrical secondary and telecom to building is 100% complete

Poured first floor deck at crawl space on Wednesday

Backfill at crawlspace walls for the HQ building is 90% complete

Prep and poured mud slab at the Visitors Center crawlspace

Completed waterproofing of crawlspace walls at the Visitors Center

Forming and pouring grade beams are 75% complete on the HQ Building

Detention pond structure is complete.

Main distribution for telecom coming out of the HQ building has started

Friday 9.4.09 was considered a rain day on the jobsite.