Texas A&M University Agriculture Headquarters Weekly Report: 8/31/09-9/4/09
Columns for Level 2 Support at HQ
North View
Sidewalk Superintendent
Crawlspace at Visitors Center
First Floor Deck Over Crawlspace
Electrical Secondary
•
First floor columns are 65% complete on the HQ building
•
Approaches off John Kimbrough are ongoing
•
Site cuts and fills at building areas are ongoing following site utilities
•
Electrical secondary and telecom to building is 100% complete
•
Poured first floor deck at crawl space on Wednesday
•
Backfill at crawlspace walls for the HQ building is 90% complete
•
Prep and poured mud slab at the Visitors Center crawlspace
•
Completed waterproofing of crawlspace walls at the Visitors Center
•
Forming and pouring grade beams are 75% complete on the HQ Building
•
Detention pond structure is complete.
•
Main distribution for telecom coming out of the HQ building has started
•
Friday 9.4.09 was considered a rain day on the jobsite.