Texas A&M University Agriculture Headquarters W e e k l y R e p o r t : 9 / 8 / 0 9 - 9 / 11 / 0 9
Columns and Seal Slab at HQ
North View
Cistern Pedestal
Reinforcing over VC Crawlspace
Termite Control prior to Seal Slab
Walk at John Kimbrough
•
First floor termite protection sprayed on west half of HQ building
•
Seal slab poured over termite protected area
•
Electrical rough-in at service yard is ongoing
•
Service yard foundation to start next week
•
Approaches to John Kimbrough 90% complete
•
Grade beams are 97% complete on the HQ Building
•
2 of the 4 pedestals on the cistern canopy pile caps were poured
•
Backfill at crawlspace walls on the HQ building near complete
•
Coring of existing manholes for telecom tie in
•
Storm lines to underground tank started
•
1.31” of rain this week