Texas A&M University Agriculture Headquarters Weekly Report: 9/14/09-9/18/09

Scaffold Training

North View

Shear Wall at HQ

Crane Assembly

West Side First Floor Concrete Pour

Fire Extinguisher Training

First floor termite protection sprayed on west half of HQ building

Poured West Side First Floor at HQ on Friday 9.18.09

Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes

Erected Crane for Elevated Work

Approaches to John Kimbrough 100% complete

Grade beams are 100% complete on the HQ Building

All pedestals on the cistern canopy pile caps are poured

Poured the first floor deck over the crawlspace at VC on Tuesday

Started backfill at the crawlspace walls at the VC

Formed, reinforced, and poured shear wall at HQ

Storm lines to underground tank ongoing