Texas A&M University Agriculture Headquarters Weekly Report: 9/14/09-9/18/09
Scaffold Training
North View
Shear Wall at HQ
Crane Assembly
West Side First Floor Concrete Pour
Fire Extinguisher Training
•
First floor termite protection sprayed on west half of HQ building
•
Poured West Side First Floor at HQ on Friday 9.18.09
•
Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes
•
Erected Crane for Elevated Work
•
Approaches to John Kimbrough 100% complete
•
Grade beams are 100% complete on the HQ Building
•
All pedestals on the cistern canopy pile caps are poured
•
Poured the first floor deck over the crawlspace at VC on Tuesday
•
Started backfill at the crawlspace walls at the VC
•
Formed, reinforced, and poured shear wall at HQ
•
Storm lines to underground tank ongoing