Texas A&M University Agriculture Headquarters Weekly Report: 9/28/09-10/2/09

East Side Mud Slab at HQ

North View

Shoring for 2nd Floor Deck @ HQ

Pan on Second Floor Deck

First Floor Deck on Void Forms

Continue to install the 30” Storm Sewer Run-out to Inlet Boxes.

Replacing CSS fill with gravel on the 30” storms.

Poured the remaining first floor slab over void forms west of the crawlspace on Tuesday9.29.09.

Poured the east side mud slab for HQ on Tuesday 9.29.09.

100% complete on the cisterns miscellaneous drain lines (6”-12”) to building.

Shoring for the second floor deck is ongoing.

Installing reinforcing, post tensioning cables, and pans for the second floor deck.

Grade beams at VC are ongoing.

Back filling cistern area to subgrade.

Poured columns at first floor grid 1-7.

Laid out foundation for mock-up.