Texas A&M University Agriculture Headquarters Weekly Report: 9/28/09-10/2/09
East Side Mud Slab at HQ
North View
Shoring for 2nd Floor Deck @ HQ
Pan on Second Floor Deck
First Floor Deck on Void Forms
•
Continue to install the 30” Storm Sewer Run-out to Inlet Boxes.
•
Replacing CSS fill with gravel on the 30” storms.
•
Poured the remaining first floor slab over void forms west of the crawlspace on Tuesday9.29.09.
•
Poured the east side mud slab for HQ on Tuesday 9.29.09.
•
100% complete on the cisterns miscellaneous drain lines (6”-12”) to building.
•
Shoring for the second floor deck is ongoing.
•
Installing reinforcing, post tensioning cables, and pans for the second floor deck.
•
Grade beams at VC are ongoing.
•
Back filling cistern area to subgrade.
•
Poured columns at first floor grid 1-7.
•
Laid out foundation for mock-up.