Texas A&M University Agriculture Headquarters Weekly Report: 10/5/09-10/9/09
North View
Shoring for 2nd Floor Deck @ HQ
Second Floor Slab
Forms for Second Floor Columns
Concrete Perimeter Beam on 2nd Deck
Replacing Mulch @ Parking Lot w/ Rock
•
Complete with replacing CSS fill with gravel on the 30” storms.
•
Had our first elevated concrete pour on the 2nd deck, grid 11.5-16, on Wednesday 10.7.09.
•
Placed foundation for mock-up.
•
Started replacing the mulch with 1 to 2 inch rock at the parking lot.
•
Shoring for the second floor deck is ongoing.
•
Installing reinforcing, post tensioning cables, and pans for the second floor deck grid 7-11.5.
•
Installing MEP rough-in @ 2nd floor deck grid 7-11.5.
•
Started framing and forming 2nd floor deck grid 1-7.
•
Started placing reinforcing cages and forms for the columns supporting the 3rd deck.
•
Friday, 10.8.09, was considered a rain day on the jobsite.