Texas A&M University Agriculture Headquarters W e e k l y R e p o r t : 11 / 9 / 0 9 - 11 / 1 3 / 0 9

North View

1st Floor MEP Rough-In

First Floor SOC @ VC

SW Corner of Building

Placed 4th floor deck grid 7-11.5 on Tuesday 11.10.09.

MEP above ceiling rough-in at the 1st floor has started.

Finished placing the last section of the 4th floor deck grid 1-7 on Friday 11.13.09.

Installing temporary X-formers and power at the site.

Excavating for the service yard foundation.

Finish installing filter fabric and base at the East parking lot.

Poured the mud slab for the VC on Tuesday 11.10.09.

Continue to place columns at the VC 1st floor and HQ 4th floor.

Placed the west side 1st floor slab on carton forms on Friday 11.13.09 @ the VC.

Going to place 5th floor deck grid 11.5-16 and 7-11.5 next week along with the remaining 1st floor SOC at the VC.