North View
1st Floor MEP Rough-In
First Floor SOC @ VC
SW Corner of Building
•
Placed 4th floor deck grid 7-11.5 on Tuesday 11.10.09.
•
MEP above ceiling rough-in at the 1st floor has started.
•
Finished placing the last section of the 4th floor deck grid 1-7 on Friday 11.13.09.
•
Installing temporary X-formers and power at the site.
•
Excavating for the service yard foundation.
•
Finish installing filter fabric and base at the East parking lot.
•
Poured the mud slab for the VC on Tuesday 11.10.09.
•
Continue to place columns at the VC 1st floor and HQ 4th floor.
•
Placed the west side 1st floor slab on carton forms on Friday 11.13.09 @ the VC.
•
Going to place 5th floor deck grid 11.5-16 and 7-11.5 next week along with the remaining 1st floor SOC at the VC.