Texas A&M University Agriculture Headquarters W e e k l y R e p o r t : 11 / 1 6 / 0 9 - 11 / 2 0 / 0 9
North View
1st Floor MEP Rough-In
1st Floor SOCF @ HQ
Main Entrance Stone Soffit
Mock-Up
Texas A&M AGC Chapter Jobsite Visit
•
Placed first deck slab on carton form between grid 1-7 on Thursday 11.19.09.
•
MEP above ceiling rough-in at the 1st floor is ongoing.
•
Placed 5th floor deck grids 11.5-16 on Tuesday 11.17.09.
•
Started columns on the 5th floor deck that will support the roof deck.
•
Preparing the service yard foundation in ongoing.
•
Installing service feeders for TTI.
•
Placed first floor slab on carton forms @ the VC.
•
Continue to place columns at the VC 1st floor.
•
Completed the MEP rough-in at the first floor on the VC.
•
Held Texas A&M AGC Chapter jobsite visit on Friday 11.20.09 @ 11:30AM.
•
Skanska will have a Tailgate for the Baylor game on Saturday 11.21.09 at the jobsite.