Placed 5th floor deck grid 7-11.5 on Tuesday 11.24.09.

MEP above ceiling rough-in at the 1st floor is ongoing.

Install edge forms, MEP rough-in, reinforcing, and carton forms for 1st floor grid 3.5-7.

Columns on the 5th floor deck are 30% complete.

Installing the North Crane Road.

Preparing the service yard foundation is ongoing.

Installing service feeders from TTI.

Installed shoring for 2nd floor deck @ VC.

Started MEP rough-in and reinforcing for the 2nd floor deck @ VC.

Poured sample columns at the mock-up.

The jobsite is closed Thursday thru Sunday for the Thanksgiving Holidays.