North View
2nd Floor Shoring @ VC
North Crane Road
Service Yard
Mock-Up
Southeast View
•
Placed 5th floor deck grid 7-11.5 on Tuesday 11.24.09.
•
MEP above ceiling rough-in at the 1st floor is ongoing.
•
Install edge forms, MEP rough-in, reinforcing, and carton forms for 1st floor grid 3.5-7.
•
Columns on the 5th floor deck are 30% complete.
•
Installing the North Crane Road.
•
Preparing the service yard foundation is ongoing.
•
Installing service feeders from TTI.
•
Installed shoring for 2nd floor deck @ VC.
•
Started MEP rough-in and reinforcing for the 2nd floor deck @ VC.
•
Poured sample columns at the mock-up.
•
The jobsite is closed Thursday thru Sunday for the Thanksgiving Holidays.