2009-12-18

Page 1

Texas A&M University Agriculture Headquarters Weekly Report: 12/14/09-12/18/09

Southeast Elevation

First Floor West Overhead

North Elevation

ERU Delivery

First Floor West Overhead

Visitor’s Center

Placed roof deck grid 7-1 on Wednesday 12.16.09.

Removing reshores on level 2 east and west wings.

Wrecking forms and pans on roof level grids 16-11.5 and reshoring.

Completed slab on carton forms at Visitor’s Center.

Pans complete for Visitor’s Center second floor scheduled to pour Tuesday.

Reinforcing on going at Visitor’s Center second floor.

West stair (stair #1) at 60% complete at HQ building.

Continue framing exterior and interior walls on the 1st floor @ HQ.

Second floor ductwork delivered and installation ongoing.

Cast iron tested and passed in crawlspace of HQ.

Energy Recovery Units delivered to the jobsite.

Completed domestic cold water riser through third floor.

Temporary power energized at building.

Thermal piping installation ongoing