Texas A&M University Agriculture Headquarters Weekly Report: 12/14/09-12/18/09
Southeast Elevation
First Floor West Overhead
North Elevation
ERU Delivery
First Floor West Overhead
Visitor’s Center
•
Placed roof deck grid 7-1 on Wednesday 12.16.09.
•
Removing reshores on level 2 east and west wings.
•
Wrecking forms and pans on roof level grids 16-11.5 and reshoring.
•
Completed slab on carton forms at Visitor’s Center.
•
Pans complete for Visitor’s Center second floor scheduled to pour Tuesday.
•
Reinforcing on going at Visitor’s Center second floor.
•
West stair (stair #1) at 60% complete at HQ building.
•
Continue framing exterior and interior walls on the 1st floor @ HQ.
•
Second floor ductwork delivered and installation ongoing.
•
Cast iron tested and passed in crawlspace of HQ.
•
Energy Recovery Units delivered to the jobsite.
•
Completed domestic cold water riser through third floor.
•
Temporary power energized at building.
•
Thermal piping installation ongoing