All Hands and Hearts Monthly Update - Mexico (March)

Page 1

MEXICO EARTHQUAKE UPDATE - OAXACA (March 2019)

CURRENT ACTIVITIES For the past two months, All Hands and Hearts has been in Oaxaca, Mexico, laying the groundwork to bring resilience to a community shaken by the Central Mexico earthquakes. Here’s what we have underway in Oaxaca: CELSO MUNOZ PRIMARY SCHOOL ● Block walls for the new classrooms have been built and concrete columns have been poured up to the bottom of the beam. ● Formwork from the column concrete pours has been removed and volunteers are preparing the rebar for the beam. ● Compaction is ongoing on all three plots, and preparation for the slabs has started. JARDIN DE NIÑOS 13 DE SEPTIEMBRE PRESCHOOL ● ●

Demolition and excavation are complete in preparation for starting construction on 11th March. Welding works on the playground roof and the main gate are in progress.

Team Leader Kam does a quality control check around the site

Demolition of Jardin de Niños 13 de Septiembre Preschool


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.