MEXICO EARTHQUAKE RECOVERY UPDATE OCTOBER 2019
TOTAL IMPACT (MITLA)
119
STUDENTS IMPACTED
97
VOLUNTEERS
1176 2
VOLUNTEER DAYS
CLASSROOMS IN PROGRESS
Current Activities Kindergarten "Itzcoatl" - To this day, we have poured the floor slab to both classrooms and the office. The walls brickwork has advanced greatly, and is almost done! Also, we've started with the rebar installation. As for the new WaSH, we have completed the superstructures for the septic tank and the absorption pits. Also, we've prepared the base slab and we are about to start pouring the concrete in the roof in the next weeks. Watch our new video here Elementary School "Revolution" - We've demolished the bands, including capping to confine masonry walls. The concrete roof slab demolition has been completed by the contractors. We are still removing all the bathroom tiles. We have completed the installation of the new double panel for the library's roof and office / WaSH; poured the new concrete beams; installed the breaker box and the electric pipes; changed and cleaned the plumbing pipes. As for the kitchen, we've reinforced the windows, completed the doors, and we're about to finish the plasterwork on its exterior walls.
Disaster Risk Reduction (DRR) Training Our Community Coordinator (CC) is implementing this program. We’ve had the participation of 78 community members in our evening educational sessions. During this training, basic concepts about recurring disaster risks have been taught, community vulnerabilities have been evaluated, reduction solutions have been discussed and at least one drill has been done. At the moment, we have formed two DRR committees, one for each school.
Learn about our programs at
allhandsandhearts.org