RAO II BRIDGE AND THE BIM STORY IN MTHOJGAARD VN Present by: TRAN THI MINH THU
mth.com 17 April 2013
Contents I.
Introduce MT Højgaard
II. Rao II bridge – Engineering and construction III. Tekla structures - BIM story in MTH Vietnam IV. Stratergy
2
17 April 2013
I) Introduce MT Højgaard Design, construction and refurbishment of plants, bridges, housing and commercial and industrial buildings 4,700 employees Headquartered in Denmark Focused international activities
3
17 April 2013
30% of our revenue comes from international activities such as: Tunnel, Eidi 2, The Faroe Islands
School, Mid Yell, Shetland
Bridge, SÜdertälje, Sweden Water intake, Qatar
Bridge, RAOII, Vietnam Shopping centre, Nuuk Centre, Greenland Set-up of mine, Fiskefjorden, Greenland
Hydro power plant, Changuinoula, Panama
4
17 April 2013
Commercial and fishing port, Oluvil Port, Sri Lanka Foundations for offshore wind farm, Lincs, England
I) Introduce MT Højgaard MT Højgaard Vietnam is established in 2007 Part of Design & Engineering Technical support for all departments External Design
5
April 17, 2013
MT Højgaard Vietnam Co., Ltd. Workshop Drawings Construction Drawings Material Take Out BIM for:
• 3D, 4D visualizations • Constructability Checks • Model on mobile devices
6
April 17, 2013
II) Rao II bridge – Engineering and construction
One pylon cable-stayed bridge Constant steel and concrete girder structure Length: 248 m Finish: Dec. 2012
7
17 April 2013
II) Rao II bridge – Engineering and construction +) Requests: Workshop drawings • Steel structures • Secondary steels
Working drawings • Reinforced concrete structures Erection sequences Nesting drawings
3D model for inspections +) Solutions: Using Tekla structures for both steel and concrete structures Export information to .nc files for nesting
8
17 April 2013
II) Rao II bridge – Engineering and construction
Tekla model 9
17 April 2013
II) Rao II bridge – Engineering and construction
Tekla model 10
17 April 2013
II) Rao II bridge – Engineering and construction
Tekla model 11
17 April 2013
II) Rao II bridge – Engineering and construction
On site 12
17 April 2013
II) Rao II bridge – Engineering and construction
On site 13
17 April 2013
II) Rao II bridge – Engineering and construction
On site 14
17 April 2013
II) Rao II bridge – Engineering and construction +) Additional benefits: Check geometry of cables
Preview collisions Purchase accurate amount of material • Using nesting drawings • Bar bending schedule +) Challenges: Bridge’s pre-camber 4D model Inspection
15
17 April 2013
III) Tekla structures - BIM story in MTH Vietnam +) BIM process – the fact: “Nothing says more than a building information model”
We are only on the way heading toward it 3D modeling solution is the only choice +) Purpose: Consistent model input and output More automatically Support other departments during constructions: design and engineering, manufacturer, inspectors, etc. Better communication
16
17 April 2013
III) Tekla structures - BIM story in MTH Vietnam +) Firm folder setting Minimize inconsistent input
Easy for filtering No numbering error Easy control project +) Custom component More automatically Speed up QA +) Tekla Open API Applying available shared extensions on Tekla extranet Built some small macros and applications
17
17 April 2013
Firm folder setting
Server
Firm folder
Project folder Template administrator
Engineer 1
18
17 April 2013
Engineer 2
Engineer 3...
Firm folder setting
Input
Output MTO
Assembly list
Reports
Client 3
Client 2
Part list Surface treatments…
Server Firm folder Model template
Client 1
Assembly Single part
Drawings
GA Cast-in drawing…
Using 1 server All computer have same setup for Firm folder Template guideline
19
17 April 2013
Same info as per company template
Same properties
Layer (color) Text, dimension… Printing (Same paper size, line thickness…) Scale….
Firm folder setting
20
17 April 2013
III) Tekla structures - BIM story in MTH Vietnam Custom components • Built up custom components for typical structures/details • Using extension Custom coponent Dialog editor
21
17 April 2013
22
17 April 2013
GCC project
III.2 How we create custom components?
Presentation by: BNV
Step 5 Use tool ”Custom Component Dialog Editor” extension on the extranet to edit interface of custom component.