CDB GeoSmart Initiative Supporting Geothermal Energy Development in the Eastern Caribbean

The CDB GeoSmart Initiative represents all of the Caribbean Development Bank’s resource mobilisation efforts to support geothermal energy development


What is Geothermal energy? Geothermal energy is a renewable energy source drawn from and generated by the earth’s heat, particularly in locations of volcanic activity. Why Geothermal energy? Geothermal plants provide “baseload� power, which means that they produce electricity consistently, running 24 hours a day, seven days a week, and are not subject to resource variability as with solar and wind. Therefore, they can directly and costeffectively replace diesel generation, which is currently the baseload power source in the Eastern Caribbean. Harnessing the potentially large geothermal energy resource in the Eastern Caribbean could transform the energy supply mix, significantly reducing dependence on imported diesel fuel and reducing carbon emissions. How should we finance Geothermal? Experience globally has shown that in order to successfully develop and implement geothermal energy projects, it is important that appropriate risk mitigation mechanisms are used to address the various financial risks of such projects, which vary depending on the stage of the project cycle. This is particularly the case in developing countries with limited resources. Some main financing instruments include grants for earlystage exploration and test drilling, contingent grants for full size test wells and field development, and concessional loans for plant construction (See Figure 3).


Model for financing projects

Figure 1: PPP Model

The CDB’s GeoSmart Initiative will make grants available for Eastern Caribbean Governments to enable them to support early-stage, exploratory drilling which will help determine the country’s true geothermal energy potential.

Government

Private Developer

$

$

It is envisaged that government support of these early-stage drilling projects will form part of their equity stake in a Special Purpose Vehicle (SPV) established as a Public-Private Partnership (PPP) with a private developer. This will allow the citizens of the country to have a share in the power generation entity.

Geothermal SPV

A PPP arrangement is the CDB’s preferred project structure.

$

$

Parallel Financing


Figure 2: Funding sources under the CDB Geosmart Initiative

This chart highlights resources mobilised so far under the CDB GeoSmart Initiative. CDB and IDB also contribute from their own resources.

Clean Technology Fund

$

$

$

Global Environment Facility

Green Climate Fund

Inter-American Development Bank

$

SEF The Sustainable Energy Facility for the Eastern Caribbean is a loan and grant package provided through the IDB to CDB for RE/EE but with focus on Geothermal development

Caribbean Development Bank

$

$

$ $ $

Government of Italy

EU-CIF Geothermal Risk Mitigation Programme

Government of New Zealand

United Kingdom Foreign Commonwealth and Development Office (formerly known as Department for International Development (DFID))


Initial funding and resource mobilisation Most of the resources have been provided through the Sustainable Energy Facility for the Eastern Caribbean Programme of CDB and IDB from IDB’s own resources, Clean Technology Fund, Global Environment Facility, Green Climate Fund and Government of Italy. The current resources which are available through the Initiative include grants, contingent grants and loan resources as appropriate for the relevant stages of the GE development. The Government of New Zealand also provides technical assistance support. CDB continues to work to source funding and resources through existing and new funding partners so as to provide suitable and adequate resources for the various stages of the project cycle (see Figure 1).


Figure 3: Typical Geothermal Energy Project Cycle Showing: Stages, Risk and Cost Profiles

(Progress of the geothermal energy projects in countries superimposed; also shown, are the financing instruments appropriate for each stage)

High

100%

SK

Pro j e c t R i s k

GRE SLU SVG

Moderate

50%

NEV DOM Risk

Low

0 Slim-hole well Full-size well

IV

I

II

III

Stages of Project

Surface studies - 3Gs

Exploratory drilling (SHW* and FSW**)

Production/ development drilling

Construction of power plant, steam, and associated infrastructure

Power plant operation and maintenance

Financing Instruments

Grants for governments

Concessional loans

Concessional loans

Commercial loans

*Grants for Slim-hole wells

**Contingently Recoverable Grants for Full size wells

Source: World Bank ESMAP, further elaborated by CDB and IDB

V

Cum ul a t i v e Co s t

Cost



CDB Geosmart Initiative Partners

Renewable Energy/Energy Efficiency Unit Caribbean Development Bank P.O. Box 408 Wildey, St. Michael BB 11000 Barbados

(246) 539-1600

reee@caribank.org

www.caribank.org


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.